Professional Documents
Culture Documents
FWD Analysis of Pavement Sections With Geotextile Separators
FWD Analysis of Pavement Sections With Geotextile Separators
ABSTRACT
The results from the FWD Area Program generally showed a decrease in the adjusted
deflections, and increases in the area parameter and subgrade modulus along the test
section over the 12-year period. The greatest increase in subgrade modulus occurred
in the six months following construction. The control sections exhibited behavior
similar to the sections with geotextiles, suggesting that for relatively thick pavements,
geotextiles separators may not provide a significant contribution to the long-term
performance of the pavement.
INTRODUCTION
One of the oldest applications of geotextiles is their use as separators in roadways.
However, in spite of this experience, data is lacking to quantify their contribution to
the long-term performance of the entire pavement section. To provide some insight
into these unknowns, the Washington State Department of Transportation (WSDOT)
constructed a geotextile test section near Bucoda, Washington, in June of 1991.
As part of the research, WSDOT periodically performed FWD testing at the site. The
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
results were analyzed using two recently developed interpretation methods, the FWD
Area Program (version 2.0) and Evercalc Pavement Backcalculation Program
(version 5.20). In addition to the FWD testing, test pits were excavated during
construction and 5 and 12 years after construction to observe the performance of the
pavement section, perform in situ testing, and obtain aggregate base course, subgrade,
and geotextile samples for laboratory testing.
PROJECT DESCRIPTION
The test section was constructed in 1991 on SR 507, just west of Bucoda,
Washington, as a change order to a reconstruction project along the route. The site is
located in southwest part of the state, about 20 miles south of Olympia. This section
of highway was selected for the study because it had historically problematic
performance, experiencing severe distress caused by logging truck traffic. Prior to
reconstruction, the roadway surface contained significant ruts and alligator cracking
and the water table was within 1 to 2 ft (0.3 to 0.6 m) of the road surface during
spring (Tsai et al., 1993). A review of records from a NOAA weather station about 8
miles from the site showed an average total precipitation of about 47 in., and average
minimum and maximum temperatures of 42 and 62 deg F, respectively (WRCC,
2004). Based on the weather records since 1931, the site rarely experiences any frost
penetration.
The test section is 45.7 m long, and is divided into six 7.6 m long sections in each
travel lane. The project stationing is from 177+60 to 179+10 (ft). Each travel lane
contains five different types of geotextile separators and one soil-only control section.
The test section layout is shown in Figure 1, and the properties of the geotextiles are
summarized in Table 1.
00
7+
17
STATIONING IN FEET
50
Centralia
7+
17
Hub
00
8+
18" CULVERT HB
17
50
NP4
HB
8+
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
NP4 SF
17
00
1996 TEST PITS NP6 Soil
9+
Piezometer Soil NP8
17
2003 TEST PITS
NP6
NP8
SO
U
SF NO THBO
N CENTERLINE
RT
HB UND
SCALE IN METERS FOG LINE OU
ND Bucoda
0 2 4 6 8 10 12 14 16 18 20
EDGE OF PAVEMENT
Figure 1. Layout of Test Section.
Prior to placing the geotextile fabrics, 450 mm of material was subexcavated from the
northbound lane and 600 mm was subexcavated from the southbound lane. The
initial lift of base course material over the geotextiles was 150 mm in the northbound
lane and 300 mm in the southbound lane. The base course was compacted with a
smooth drum nonvibratory roller and water was used to moisture condition the
aggregate during compaction. There were some trafficking studies performed and rut
depth measurements made. The design base course thickness was 300 mm in the
northbound lane and 460 mm in the southbound lane. The design thickness of the
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
asphalt concrete pavement was 150 mm. The results of the investigations during
construction (Phase I) were presented in Savage (1991), Tsai and Savage (1992), and
Tasi et al. (1993).
In 1996, the Phase II excavations were made after the geotextiles had been in service
for 5 years. Samples of geotextiles, subgrade, and base course materials were
exhumed for visual observation and laboratory testing. In addition, in situ soil tests
were performed on the exposed subgrade soils. Black (1997), and Black and Holtz
(1997 and 1999) described the Phase II investigation.
In 2003, Phase III investigations were conducted at the site. The field and laboratory
investigation procedures were generally the same for Phase II, and the results are
summarized in Collins (2004). This paper presents the results of the FWD testing
conducted over the 12-year period, and the results are compared to the findings of the
field and laboratory investigations.
The results were analyzed using two recently developed interpretation methods, the
FWD Area Program (version 2.0) and Evercalc Pavement Backcalculation Program
(version 5.20). Both of these programs are used by WSDOT as a means of evaluating
the structural condition of the pavement section from FWD deflection data.
Figures 2 and 3 show the adjusted deflections for the northbound and southbound
lanes, respectively. The adjusted deflection is the maximum deflection at the center
of the loading plate normalized to a 40 kN load and modified to account for pavement
thickness and temperature. The general trend was a decrease in the adjusted
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
deflection with time. The adjusted deflections decreased most in the first few months
following reconstruction, and a relatively small decrease can be seen in the three
years between the last two series of FWD tests.
4.0
04/29/91
3.5 07/24/91
11/25/91
3.0
Adjusted Deflection (mm)
03/25/96
10/04/00
2.5
08/12/03
2.0
1.5
1.0
0.5
HB NP4 NP6 Soil NP8 SF
0.0
177+35 177+60 177+85 178+10 178+35 178+60 178+85 179+10 179+35
Station (ft)
3.5
04/29/91
Adjusted Deflection (mm) 3.0 07/24/91
11/25/91
2.5 03/25/96
10/04/00
2.0
08/12/03
1.5
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
1.0
0.5
HB NP4 SF Soil NP8 NP6
0.0
177+35 177+60 177+85 178+10 178+35 178+60 178+85 179+10 179+35
Station (ft)
Figures 4 and 5, below, show the area parameters for the northbound and southbound
lanes, respectively. The area parameter has generally increased with time over the
12-year period. Just as was seen in the adjusted deflection values, the largest change
in the area parameter appears to have occurred in the first few months after
construction. In fact, the area parameter increased from about 450 to 600 mm over
the 12-year period—an indication of substantial stiffening of the pavement structure.
The trend of decreasing adjusted deflection values and increasing area parameters is
an indication that both the pavement structure and subgrade have gained strength over
time. This is in agreement with the subgrade moduli calculated by the area program,
shown in Figures 6 and 7, below, for the northbound and southbound lanes,
respectively.
700
HB NP4 NP6 Soil NP8 SF
600
Area Parameter (mm)
500
400
300
0
177+35 177+60 177+85 178+10 178+35 178+60 178+85 179+10 179+35
Station (ft)
700
HB NP4 SF Soil NP8 NP6
600
Area Parameter (mm)
500
400
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
300
100
80
60
40
20
HB NP4 NP6 Soil NP8 SF
0
177+35 177+60 177+85 178+10 178+35 178+60 178+85 179+10 179+35
Station (ft)
100
Subgrade Moduli (MPa)
80
60
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
40
20
Figures 8 and 9, below, are the backcalculated asphalt concrete (AC) moduli adjusted
to a temperature of 25 deg C and a 40 kN load. The significant increase in the moduli
in the period after construction may, in part, be attributed to compaction of the AC by
traffic and aging of the asphalt binder in the hot mix.
12,000
04/29/91 07/24/91 11/25/91
03/25/96 10/04/00 08/12/03
10,000
8,000
EAdj (MPa)
6,000
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
4,000
2,000
0
177+35 177+60
HB 177+85NP4178+10NP6178+35Soil178+60NP8178+85 SF 179+10 179+35
Station (ft)
16,000
04/29/91 07/24/91 11/25/91
14,000
03/25/96 10/04/00 08/12/03
12,000
10,000
EAdj (MPa)
8,000
6,000
4,000
2,000
0
HB NP4 SF Soil NP8 NP6
177+35 177+60 177+85 178+10 178+35 178+60 178+85 179+10 179+35
Station (ft)
Figure 10 and 11 show the change in the crushed stone base course moduli over the
12-year period since reconstruction. The figures show a general increase in the base
course modulus since construction. The 2003 FWD results in the Soil-NB and Soil-
SB sections were generally the same as the FWD results just after construction in
1991; however, the results over the period were, at best, erratic.
160
140
120
100
ECSBC (MPa)
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
80
60
160
140
120
100
ECSBC (MPa)
80
60
04/29/91 07/24/91 11/25/91
20
HB NP4 SF Soil NP8 NP6
0
177+35 177+60 177+85 178+10 178+35 178+60 178+85 179+10 179+35
Station (ft)
Figures 12 and 13 show the change in subgrade moduli over the 12-year period. The
results are similar to what was found by the Area Program. The Area Program
calculated subgrade moduli about 15 to 20 MPa higher than Evercalc, but both
programs showed an increase of 40 to 50 MPa in the time period since just prior to
reconstruction. The subgrade moduli generally increased with time over the 12-year
period, and the largest increase was in the first several months after construction. In
the figures, the soil-only sections show a similar increase in moduli when compared
with the geotextile sections.
120
04/29/91 07/24/91 11/25/91
03/25/96 10/04/00 08/12/03
100
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
80
Esubgrade (MPa)
60
40
20
120
04/29/91 07/24/91 11/25/91
80
Esubgrade (MPa)
60
40
20
HB NP4 SF Soil NP8 NP6
0
177+35 177+60 177+85 178+10 178+35 178+60 178+85 179+10 179+35
Station (ft)
The field nuclear density tests indicated that some of the subgrades in the geotextile
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
sections had an increase in density at 5 and 12 years after construction, but tests in the
soil-only sections had the same or lower results compared to the tests during
construction.
The base course was very dense, and steel pry bars were required to loosen it during
both the 1996 and 2003 test pit excavations. Less than 13 mm of base
course/subgrade intermixing was observed in the soil-only sections. Grain size
distribution tests conducted on the base course material indicated none to a trace of
fines migration (<5%) between the subgrade and the aggregate located immediately
above the zone of intermixing.
These observations indicate that the pavement section may be too thick to realize the
separation benefits of the geotextiles in the 12 years since construction. This is
evidence that when geotextile separators are used, it is probably not necessary to
subexcavate to the same depth as if no geotextile was present. The presence of the
geotextiles may be contributing to an increase in the base course moduli over time.
The pavement in the test section is in good condition, thus the true “long-term”
benefits of the geotextiles are yet to be quantified.
CONCLUSIONS
1. FWD testing and interpretation was successfully used as a means of
evaluating the long-term performance of pavement sections with geotextile
separators.
2. The most significant improvement in pavement section moduli, as determined
by FWD tests, generally occurred in the first several months following
construction.
3. In situations where the subgrade has modest shear strength; subexcavation (or
digout) depths may be decreased if a geotextile separator is placed between
the base course aggregate and the subgrade.
4. Geotextile separators can provide reinforcement of the base course that may
contribute to an increase in base course moduli over time, but for relatively
thick pavement sections, incorporation of a geotextile into the section may not
provide a significant contribution to the overall performance of the pavement
section over the design life.
ACKNOWLEDGEMENTS
The research presented in this paper was funded by WSDOT. Their financial support
is greatly appreciated. Additional thanks are given to all of the personnel who were
involved in planning and executing the field investigation and also those who assisted
in interpretation of the FWD data.
REFERENCES
Black, P.J. (1997) “Performance of Geotextile Separators: Bucoda Test Site – Phase
II,” MSCE Thesis, University of Washington, Seattle, 210 pp.
Black, P.J. and Holtz, R.D. (1997) “Performance of Geotextile Separators, Bucoda
Downloaded from ascelibrary.org by MOHAMED AMINE on 12/31/13. Copyright ASCE. For personal use only; all rights reserved.
Test Site – Phase II,” Final Summary Report, Washington State Department of
Transportation, Report No. WA-RD 440.1, 210 pp.
Black, P.J. and Holtz, R.D. (1999) “Performance of Geotextile Separators Five Years
after Installation,” Journal of Geotechnical and Geoenvironmental Engineering,
ASCE, Vol. 125, No. 5, pp. 404-412.
Savage, B.M. (1991) “Field Activities Report,” Bucoda, Washington, Field Research
Project, June 25, 1991, unpublished, 29 pp.
Tsai, W.S., Savage, B.M., Holtz, R.D., Christopher, B.R., and Allen, T.M. (1993)
“Evaluation of Geotextiles and Separators in Full-Scale Road Test,” Geosynthetics
’93 Conference Proceedings, Vancouver, B.C., Vol. 1, pp. 35-48.
WSDOT Pavement Guide, Pavement Analysis Computer Software and Case Studies
(1999) Washington State Department of Transportation, Vol. 3, 148 pp.