Professional Documents
Culture Documents
SPECIFICATION FOR
FIRE PROTECTION SYSTEM
PACKAGE FOR STORAGE TANKS
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL All rights reserved
SPECIFICATION FOR FIRE DOCUMENT NO.
PROTECTION SYSTEM 6698-6-66-0072, Rev A
PACKAGE FOR STORAGE Page 2 of 10
TANKS
INDEX
1.0 SCOPE
2.0 CODES AND STANDARDS
3.0 SYSTEM DESCRIPTION
4.0 SCOPE OF WORK AND SPECIFIC REQUIREMENTS
5.0 DESIGN AND CONSTRUCTION
6.0 ERECTION
7.0 TESTING AND COMMISSIONING
8.0 PAINTING
9.0 CIVIL WORKS
10.0 VENDOR DATA REQUIREMENT
ANNEXURE-ß
TABLE SPECIFIC REQUIREMENTS FOR DESIGN OF FIRE PROTECTION SYSTEM
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL All rights reserved
SPECIFICATION FOR FIRE DOCUMENT NO.
PROTECTION SYSTEM 6698-6-66-0072, Rev A
PACKAGE FOR STORAGE Page 3 of 10
TANKS
1.0 SCOPE
This specification covers the requirements of Íupply, fabrication, erection, testingô °¿·²¬·²¹
and commissioning of Cooling, Semi Fixed Foam systems and Rim Seal Fire Protection
and Detection system for the protection of storage tanks containing inflammable
hydrocarbon liquids.
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL All rights reserved
SPECIFICATION FOR FIRE DOCUMENT NO.
PROTECTION SYSTEM 6698-6-66-0072, Rev A
PACKAGE FOR STORAGE Page 4 of 10
TANKS
d) Coating of pipes passing through dykes as per ×ÑÝÔ Ípecification No. ÐÎñ×ÐñÐÎñ
×ÒÍÐÛÝÌ×ÑÒ ÓßÒËßÔñïîòïì including encasing at dyke locations with PCC M20.
e) Taking approval from TAC accredited agencies.
The cost of all such º¿¾®·½¿¬·±² drawings °®»°¿®¿¬·±² to be ·²½´«¼»¼ ·² ¬¸» °®·½» ¯«±¬»¼ ¾§
½±²¬®¿½¿¬±® for the work. The term "drawing" in the detailed specifications ¸¿´´ ·³°´§ ¬¸»
drawings prepared by the contractor and approved by ×ÑÝÔñ×ÑÝÔ Ý±²«´¬¿²¬.
Advance certified final drawings/calculations submitted by the contractors shall be reviewed
by EIL/Owner. During such review, the Engineer-in-Charge may suggest certain comments
necessitating some modifications in these documents. The contractor shall incorporate all
such modifications.
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL All rights reserved
SPECIFICATION FOR FIRE DOCUMENT NO.
PROTECTION SYSTEM 6698-6-66-0072, Rev A
PACKAGE FOR STORAGE Page 5 of 10
TANKS
works is not delayed for want of inspection by the concerned authorities. The bidder shall
give assistance and cooperation to the inspection authorities for inspection works at various
stages.
Any change/addition required to be made to meet the requirements of the statutory
authorities shall be carried out by the Contractor. The Inspection and acceptance of the
work by statutory authorities shall, however, not absolve the Contractor from any of his
responsibilities under this contract.
5.1.2 In case of floating roof tanks the cooling ring shall be located about 1.0M below the top
wind girder. Where more than one wind girders are envisaged, the location of the cooling
ring shall be decided as per table in clause no. 5.3.1. All wind girders except the top one
shall be provided with deflector plate to channelise the water along the shell.
In case of cone and floating-cum-cone roof tanks the cooling ring shall be provided at the
highest possible location on tank shell to provide maximum coverage to the tank shell.
Where more than one wind girders are envisaged, the location of cooler ring shall be
decided as per table in clause no. 5.3.1. All wind girders shall be provided with deflector
plates to channelise the water along the shell.
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL All rights reserved
SPECIFICATION FOR FIRE DOCUMENT NO.
PROTECTION SYSTEM 6698-6-66-0072, Rev A
PACKAGE FOR STORAGE Page 6 of 10
TANKS
5.2.2 Foam makers for cone and floating cum cone roof tanks shall be provided with vapour seal
chambers to prevent escape of hydrocarbon vapours through dry foam piping to the
roadside.
5.2.3 Suitable foam deflectors shall be provided inside tank shell on foam outlets to guide the
foam smoothly along the tank shell. Platform and approach ladder from rooftop shall be
provided for each foam maker for maintenance and testing work.
TABLE NO-1
(FOR FLOW OF WATER AND NO. OF RINGS)
Detail of Tanks No. of Rings %Flow Ring Position on Tank
of
water
Floating Roof Tanks
Height > 10.0M < 2nd Ring 70% 4M from top of tank (in case this
Two location is fouling with 2nd wind
15.0M
girder, the ring shall be placed
below the 2nd wind girder.)
Ist Ring 25% Below top wind Girder
2nd Ring 25% 4M from top of tank (in case this
location is fouling with 2nd wind
Height > 15.0M girder, the ring shall be placed
Three below the 2nd wind girder.)
< 20.0M
3rd Ring 50% At mid height of the tank (in case
this location is fouling with 3rd
wind girder, the ring shall be placed
below the 3rd wind girder.
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL All rights reserved
SPECIFICATION FOR FIRE DOCUMENT NO.
PROTECTION SYSTEM 6698-6-66-0072, Rev A
PACKAGE FOR STORAGE Page 7 of 10
TANKS
Cone & Cone cum Floating Roof Tanks
One
Revolving 2nd Ring 20% 4M from top of tank (in case this
Height> 15.0M location is fouling with 2nd wind
Head + 3
< 20.0M girder, the ring shall be placed
Rings
below the 2nd wind girder.)
3rd Ring 35% At mid height of the tank (in case
this location is fouling with 3rd
wind girders, the ring shall be
placed below the 3rd wind girder.
The spray nozzles shall be so selected that their individual spray pattern shall at least meet
each other without leaving any portion of tank shell unwet and shall provide uniform cooling.
A minimum overlap of 400mm between two nozzles shall be provided.
For floating roof tanks the foam application shall be restricted to foam seal area by
providing a foam dam. The foam dam shall be located about 800mm away from tank shell.
The height of foam dam shall be sufficient to retain foam upto the top of the weather shield.
Suitable drain spouts shall be provided to drain the degenerated foam liquid from the foam
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL All rights reserved
SPECIFICATION FOR FIRE DOCUMENT NO.
PROTECTION SYSTEM 6698-6-66-0072, Rev A
PACKAGE FOR STORAGE Page 8 of 10
TANKS
dam area. The rate of application of foam shall be 12 lpm/m2 of foam dam area for floating
roof tank.
6.0 ERECTION:
Fabrication and erection of piping shall be done as per the approved detailed drawings and
enclosed specifications with following specifications with following specific requirements:
6.1 Foam Piping at grade level shall be sloped towards the drain valves at all the lowest
elevations.
6.2 Drain valve assembly shall be provided at low points in the dry piping system. Suitable
strainers shall be provided in cooling water headers.
6.3 Suitable guides shall be provided on the piping wherever required to keep the pipes in
position.
6.4 Vendor shall design, fabricate and provide all pipe supports on tankages. Pipe sleepers for
grade level piping (sleeper height upto 500mm above finished grade level) shall be as per
EIL standard drg. enclosed. In case where the sleeper height is more than 500, special
structural supports shall be designed and provided by the Contractor.
6.5 The portion of piping passing through dykes shall be coated as per ×ÑÝÔ specification No.
ÐÎñ×ÐñÐÎñ×ÒÍÐÛÝÌ×ÑÒóÓßÒËßÔñïîòïì and encased in M20 ½±²½®»¿¬»100mm thick all around.
з°» shall be embedded in the dyke to make it watertight. The dyke shall be cut to lay the pipes
and dyke made good after laying the pipes.
6.6 10% of all the welded joints shall be radiographically tested and half the joints radiographed
shall be field joints.
7.2 Commissioning
The complete cooling and foam system shall be tested for satisfactory performance as per
design requirements by the contractor. Any modification required for achieving such
performance shall be done by the contractor without any extra cost. (Owner shall arrange
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL All rights reserved
SPECIFICATION FOR FIRE DOCUMENT NO.
PROTECTION SYSTEM 6698-6-66-0072, Rev A
PACKAGE FOR STORAGE Page 9 of 10
TANKS
for necessary water and foam solution required for performance testing of the system). The
system shall be deemed to be complete after the above tests are conducted by the bidder
to the satisfaction of the owner.
8.0 PAINTING
8.1 After hydraulic testing of the system all exposed steel piping, equipment, fixtures and
supports shall be painted as per Job Specification No. 6698-0642-PT-I-05
8.2 All other components shall be suitably painted and identified.
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL All rights reserved