Professional Documents
Culture Documents
भारत सरकार
उ�र क्षे� िव�ुत सिमित
18-ए, श.जीत �सह मागर, कटवा�रया सराय,
नई �दल्ल- 110016
Government of India
Northern Regional Power Committee
18-A, S. Jeet Singh Marg, Katwaria Sarai,
New Delhi-110016
सव
े ा म� : �चालन समन्व उपसिमित के सदस् ।
To: Members of OCC
�चालन समन्व उप-सिमित क� 128 व� बैठक 14 एवं 17 अक्ट ूब, 2016 (सोमवार) को आयोिजत
क� गयी थी। उ� बैठक का कायर्व� उ�र क्षे� िव�ुत सिमित क� वब
े साइट http://www.nrpc.gov.in
पर उपलब् है ।
128th meeting of the Operation Co-ordination sub-committee was held on 14th and
17th September, 2016. The Minutes of this meeting have been up-loaded on the
NRPC web-site http://www.nrpc.gov.in.
Sd/-
(हम
े त े )
ं कु मार पांडय
अधीक् अिभयंता
1
Minutes of 128th OCC meeting, held on 14th & 17th October, 2016 at New Delhi
128th meeting of the Operation Coordination Sub Committee (OCC) of NRPC was
held on 14th and 17th October, 2016 at New Delhi. The list of participants is enclosed
at Annex - IA.
1. Confirmation of Minutes:
The Minutes of the 127th meeting of the OCC held on 23.9.2016 at New Delhi were
issued vide letter dated 10.10.2016.
THDC vide letter dated 13.10.2016 requested NRPC Secretariat to included
following text under item 15 (SPS for Tehri Complex) in the Minutes of 127th OCC
meeting:
"ln order to implement SPS at Tehri, it has been decided that PGCIL shall formulate
necessary logic at KPS end for sending a signal when
(i) One of the KPS-MEERUT lines trips AND
(ii) The Power flow on line prior to tripping was more than the margin
available in second line for stable operation.
The logic shall be extended by PGGIL up to interface area of Tehri plant by providing
a 220V DC potential free contact which shall subsequently be configured by THDC
into its protection system. Till SPS is placed in position, NRLDC shall consider
staggering of peaking schedule of Tehri and Koteshwar. PGCIL shall expedite the
restoration of FSC at the earliest."
The amendment proposed by THDC was discussed in detail. It was noted that point
(ii) mentioned by THDC had not been discussed and as per discussion in last OCC
meeting, THDC had to implement SPS in coordination with POWERGRID. It was
also noted that in the minutes of 127th OCC meeting it is already recorded that
POWERGRID and THDC will work out the necessary details to implement the scheme;
therefore, OCC opined that there was no need of amendment in the minute.
The variation in anticipated and actual energy requirement and peak demand
was discussed and the reason, as explained by Rajasthan & U.P. was good
rainfall in the states during the month of September, 2016. However, Punjab has
cited less rainfall in the state. SE, NRPC emphasized the need to improve the
demand estimation taking into account weather conditions/ monsoon records for
previous years and IMD forecast.
SE, NRPC stated that monthly power supply position for NCR till the month of
August, 16 was placed on NRPC website. Members were requested to submit
the updated information on regular basis.
4. Information about variable charges of all the generating units in the Region.
SE, NRPC stated that as per decision taken in 103rd OCC meeting, all generating
entities were required to furnish the variable charges of their generating units on
monthly basis to NRPC secretariat. It was also decided that SLDCs would submit the
variable charges of the generating units located in their control area. The details of
variable charges submitted by utilities from April to September, 2016 were available
on NRPC website.
SE, NRPC informed that data of state Gencos was not being received regularly at
NRPC secretariat.
All SLDCs and regional generating entities were requested to furnish the variable
charges on regular basis.
Representative of NTPC stated that government had reduced the prices of domestic
gas by 14.6%. This had resulted into reduction in ECR of gas stations in the range of
3
Rs. 1.80 to Rs. 2.10. He requested the beneficiaries to avail the opportunity and
maximize the schedule on gas based stations.
4
Discussions on implementation of recommendations: Recommendations
pertaining to operational aspects made by the Enquiry committee for grid
disturbances on 30th July, 2012 & 31st July, 2012 are as under:-
8.1 Third party protection audit.
(i) Progress of rectification of deficiencies observed/improvements
suggested in Basic Protection Audit (BPA) .
A. SE (O), NRPC stated that in the 27th NRPC meeting held on 30th November,
2012, it was decided that all efforts should be made to squeeze the time for
procurement of relays etc so as to rectify deficiencies observed in the Basic
Protection Audit within a year i.e. before November, 2013. Later, in 28th
NRPC meeting the target date was deferred to March 2014. However, utilities
have not been able to meet the timeline given by NRPC. Utilities, which have
yet not completed the rectification, were requested to expedite the rectification
of deficiencies.
Representative of UPRVUNL informed that their work of rectification of
deficiencies would be completed by 30.11.2016. Representative of NTPC
intimated their work related to commissioning of relay panel would be
completed by 30.11.2016. The status of rectification of the deficiencies as
updated in the 128th OCC meeting is enclosed as Annex - I.
B. PLCC defects:
The defects were observed during BPA pertaining to operation of PLCC at
many sub-stations/ switchyards. It was observed that mainly work pertaining
to UPPTCL, UPRVUNL and PTCUL were pending. Status as updated in 128th
OCC meeting is as Annex - II.
C. Bus Bar Protection
SE(O), NRPC stated that a sizable no. of Bus Bar Protection (BPP) schemes
at 400 kV or 220 kV sub-stations of UPPTCL were found either not installed or
not in working condition during Basic Protection Audit. UPPTCL was
requested to expedite the commissioning of the bus bar protection at these
sub-stations. The updated status is enclosed as Annex - III.
The issue was discussed in 32nd TCC/36th NRPC meeting. PSTCL had
informed that CPRI would submit the final report by 31.12.2015 and they have
intimated action based on the interim report. Utilities had agreed in the NRPC
meeting to submit by 15.01.2016, the action plan with time schedule for
rectification of deficiencies observed in TPPA.
5
In 127th OCC meeting, representative of UPPTCL had informed that CPRI had
submitted the draft report of the TPPA and action plan for the rectification of
the deficiencies was underway. Representative of PSTCL had intimated that
action plan would be submitted by 31.10.2016.
B.HVPNL
6
a) At the Sub stations at Hissar, Fatehbad, Bhiwani, Sirsa, Rania ,Jind,Narwana
Static Relays are installed.
b) At all the Substations under M&P Division Gurgaon, type of relay has not
been mentioned.
c) At the Palwal substation the UFR relays are not working though the substation
is being fed from 220KV substation Rangla-Rajpur.
C.RVPNL
a) At some substations under SE (MPT&S) Ajmer Electromagnetic or Static
Relays are installed. The same be looked into and the Numeric Relays be
installed there
b) At all the substations under SE (MPT&S) in the report the type of Relay ie.
Static OR Numeric has not been stated.
D.HPSEBL
Static Relays have been installed at :
1. M/S GACL 132 KV S/S Darlaghat
2.132KV/33kv S/S Kala
Representative of HPSEBL assured to look into these issues and reveryt
back before next OCC meeting.
E. PTCUL
The static type UFRs are still installed on Transformers/feeders emanating from
132KV Majra and Jwalapur Substations and 220KV Ramnagar,Rorkee and
Rishikesh Subsations.
Representative of PTCUL reiterated assurance given in 123rd OCC meeting
that replacement of these relays with Numeric Relays would be completed
by 31.12.2016.
(iv) SE, NRPC pointed out that recently it has been observed during the testing
at 220 KV Subsation Banur that PSTCL did not have the testing kit for
generating the df/dt slope. Also, a separate register to maintain record of
actual operation was not maintained separately by PSTCL. He requested
STUs to keep Relay testing kits in sufficient numbers for testing and provide
the same to NRPC officers as and when required. Separate register with
record of UFR operation should be maintained at all stations wherever UFR
installed.
7
PSTCL representative ensured that they would procure proper testing kit.
Also a separate register be maintained for record of UFR operation.
8
2016.
Sonepat:-30.11.2016
Kanpur:-31.12.2016
9 MERTA 125 RVPNL Same as S.No. 1
B. In the 33rd NRPC meeting held on 11.11.2014, RRVPNL had intimated that they
had finalised 15 nos. of reactors at 220 kV level in pockets of renewable energy.
In the 111th OCC meeting, RRVPNL had intimated that the study to assess the
requirement of reactors at 220 kV level was being taken up afresh keeping in
view the likely addition of 32,000 MW Solar and 5,500 MW wind generation
capacity in Rajasthan.
In 125th OCC meeting representative of RRVPNL had informed that the
requirement of 25 MVAR reactors at 13 Nos. 220 kV GSS has been assessed
and the same would be finalized in the meeting of whole time directors (WTD) of
RVPNL, after which procurement action would be initiated.
In 126th OCC meeting RRVPNL had informed that reactors at 220 kV were still
under consideration of Directors.
In this OCC meeting representative of RRVPNL informed that based on the
observation of the management, the proposal has been resubmitted for
approval.
C. Study by POWERGRID for reactive compensation at 220 kV level:
SE(O), NRPC stated that the proposal for installation of bus reactors at 12 nos. 400
kV and 17 nos. 220 kV sub-stations was discussed in the 29th meeting of NRPC held
on 13th September 2013. After deliberations, NRPC had approved installation of
reactors at 400 kV sub-stations of POWERGRID and RVPNL. As regards 220kV bus
reactors, POWERGRID had stated that the requirement would be firmed up in
consultation with the States in separate meetings. Thereafter, the issue of validation
of the data and submission of report of the study for determination of requirement of
reactive compensation at 220 kV level has been under discussion at NRPC forum.
CTU, vide email dated 30.09.2016 had submitted report of the study, which was
enclosed at Annex—AA of the Agenda for the 128th OCC meeting. In this report,
following reactors are proposed:
At 220 kV level:
Reactors Proposed
S.No. Bus Name State
(MVAR)
1 Jind (PG) Haryana 25
2 Fatehbad (PG Haryana 25
3 Chamera Pooling Stn. Himachal Pradesh 2x25
4 Kishenpur J&K 25
9
5 Jalandhar Punjab 2x25
6 Nakodar Punjab 2x25
7 Amritsar Punjab 25
8 Makhu Punjab 25
9 Dhuri Punjab 25
10 Akal Rajasthan 25
11 Suratgarh Rajasthan 2x25
12 Bikaner Rajasthan 2x25
13 Barmer Rajasthan 25
At 400 kV level:
Reactors Proposed
S.No. Bus Name State
(MVAR)
1 Mandola(PG) DELHI 125
2 Hissar(PG) HARYANA 125
3 Kala Amb HIMACHAL 125
4 Chamera Pooling Stn. (PG) HIMACHAL 125
5 Kishenpur(PG) J&K 125
6 Nakodar PUNJAB 125
7 Jullandhar(PG) PUNJAB 125
8 Moga(PG) PUNJAB 125
9 Dhuri PUNJAB 125
10 Patiala(PG) PUNJAB 125
11 Ludhiana(PG) PUNJAB 125
12 Ajmer(PG) RAJASTHAN 125
13 Merta RAJASTHAN 125
14 Ratangarh RAJASTHAN 125
15 Chittorgarh(PG) RAJASTHAN 125
16 Suratgarh(PG) RAJASTHAN 125
17 Parichha UP 125
18 Allahabad(PG) UP 125
19 Mainpuri UP 125
20 Unnao UP 125
21 Gonda UP 125
22 Meerut(PG) UP 125
23 Kashipur UTTRAKHAND 125
24 Srinagar UTTRAKHAND 125
The report was discussed in the meeting. It was pointed out in the meeting
that there were some discrepancies in the name and associated organization
of the sub-stations where reactors were proposed to be installed.
POWERGRID was requested to check the same and modify the same, if
necessary. OCC recommended the proposal of reactors for approval of
TCC/NRPC.
10
8.5 Strengthening of Intra-State transmission system
11
iv. Units for which step test/PSS tuning has been carried out after July, 2013,
results of the tests should be submitted to NRLDC and NRPC Secretariat, if
not submitted earlier.
v. Generating companies should plan for retrofitting of units having analog AVR
with Digital AVR and indicate timeframe for the same.
Members were requested to update the status.
B. Analysis of Step Response Test
In the 34th NRPC meeting, it was decided to constitute a group for analysing
the results of PSS tuning. Issues arising out of recommendations of the Group
were deliberated in the TCC/NRPC meetings held in March 2016 and it was
decided that the Group should meet again to fine tune the recommendations.
Meanwhile, members are requested as under:
(i) As far as possible, Generating companies to submit values of power
output vs time to establish settling time observed during Step Response
Test with and without PSS. If it is not possible, the curve should be on a
bigger scale so that values of initial peaks or settling time can be clearly
measured/ interpreted.
(ii) If possible, such values should be submitted for even those units, for
which curves had been submitted earlier.
Members were requested to update the status.
12
of information problem may be resolved by POWERGRID with one to one
discussion with the concerned utilities. Members agreed had for the same.
In this OCC meeting, it was intimated that load grouping has been
finalized. It was also informed that the scheme would be installed at about
30 odd sub-stations of the Punjab, Haryana. U.P., Rajasthan and Delhi.
Utilities were requested not to change the sub-stations where the scheme
is already functional. Representative of POWERGRID stated that scheme
would be commissioned by 31.03.2017.
b. Mock testing of 765 kV Agra-Gwalior held on 12.05.2015
As agreed in 122nd OCC meeting mock test of SPS for 765 kV Agra-Gwalior was
held on 12.05.2016.
Further, POWERGRID vide e-mail dated 10.05.2016 had informed that during
visit of POWERGRID's Engineer at Jamsher Sub Station, it was reported that
tripping wire was found removed from DTPC installed for Agra-Gwalior SPS.
PSTCL was requested vide e-mail dated 13.05.2016 to look into the issue and
submit a report.
In 126th OCC meeting POWERGRID had informed that DTPC for 220 kV
Jamsher has arrived and the problem will be resolved in one week.
In the 127th OCC meeting POWERGRID informed that problem has been
rectified at 220 kV Jamsher S/s. OCC had desired to know the reason for
replacement of DTPC. Representative of POWERGRID had agreed to
submit this information before next OCC meeting.
In this OCC meeting, representative of POWERGIRD informed that there
was a problem in the converter card of DTCP which was replaced with the
spare one.
9.2 The latest revised target dates for implementation of SPS in Northern Region are
given in Annex - V.
9.3 In respect of finalization of backing down of generation at Dadri TPS and Dadri
CCGT for implementation of SPS for tripping of multiple lines from 400 kV Dadri,
in the 105th OCC meeting, NTPC had informed that SPS was likely to be
implemented by Feb, 2015. Thereafter the issue was under discussion regularly
in OCC meetings, a target date was getting deferred.
In 125th OCC meeting representative of NTPC had informed that SPS would be
made operational by 31st July, 2016.
In Last OCC meeting NTPC informed that the SPS has been commissioned.
OCC had decided that modalities for mock testing of this SPS need to be
finalized.
In this meeting representative of NTPC informed the mock testing could
be planned for 18.10.2016. NRLDC would coordinate for the same with
Dadri TPS.
9.4 Rosa SPS had been commissioned on 18.06.2016.
13
In the 127th OCC meeting, representative from Rosa Power briefed the OCC
about the different contingencies considered along with the logic implemented
to make the SPS operational.
Representative of NRLDC had stated that the logic for contingencies and
consequent backing down of the generation are based on the overloading of the
transmission lines or the ICTs. However, decision on the basis of comparison of
Analog Values may take longer time for the SPS to operate. Instead of taking
decisions on the basis of overloading, logic could be on the basis of the tripping
of the lines as the power flow considered for decision making would be almost
similar to the case of tripping of circuits. Representative of Rosa Power had
agreed to consider the suggestion and review the SPS implemented in the light
of these suggestions.
Status could not be updated as no representative from Rosa Power
attended the meeting.
9.5 SPS for ICTs at 765 kV Unnao sub-station:
A discussion was held on 06.05.2015 in NRPC secretariat with the officers from
UPPRVUNL in the presence of officers from NRLDC, POWERGRID and NRPC
sect. UPRVUNL was briefed about the basic philosophy along with the hardware
requirement of the System Protection Scheme (SPS) for evacuation of Anpara-D
generation. It was agreed that UPRVUNL along with UP SLDC would prepare the
SPS for safe power evacuation of Anpara-D. Further the scheme would be
submitted to the OCC for approval. Thereafter, the matter was under discussion in
various OCC meetings without much progress.
In 121st OCC meeting, it was decided that in line with the document on roles and
responsibilities on SPS, it would be appropriate that the scheme be implemented
by UPPTCL. Further, this scheme was under discussion for long time and various
issues were still unresolved, it was decided to hold a meeting on 11.04.2016 at
NRPC Sectt. to deliberate and the expeditious implementation of the same.
In 126th OCC meeting, representative of UPPTCL informed that the scheme would
be commissioned by 31.12.2016.
In the 128th OCC meeting, UPPTCL informed that status is same as that of
last meeting.
Based on the above, Letter of Award was issued to CPRI for carrying out the studies
with consultancy charges of Rs 20 Lakh plus Service tax after due approval from
Chairperson, NRPC. To carry out capacitor studies, CPRI had submitted format for
submission of data which were circulated to the SLDCs vide letter dated 13.07.2016.
The formats were also circulated in 125th OCC meeting held on 22nd July, 2016.
Further a separate letter dated 19.08.2016 was written by Member Secretary, NRPC
to TCC members of STUs with a request for submission of data. The issue of non
submission of data was discussed in the 127th OCC meeting held on 22nd
September, 2016 wherein it was highlighted that without the availability of the data,
capacitor requirement studies cannot be carried out. OCC was concerned about the
non- submission of data even though some of the state has submitted the proposal
for installation of capacitor in their states through PSDF. It was decided that all
utilities would submit the data for capacitor studies by 30.09.2016. It was also
decided that in case data is not submitted, it would be informed to PSDF nodal
agency that capacitor requirement could not be finalised due to non- availability of
the data. However, only HPSEB Ltd and PSTCL have submitted that data whereas
partial data has also been received from HVPNL.
He mentioned that under Section 2.4.2(g) of Indian Electricity Grid Code, one of the
functions of RPC is to review the reactive power compensation requirement and
monitor installation of capacitors. Therefore, non-submission of data for carrying out
the aforesaid study constitutes non-compliance to IEGC.
• To Inform Hon’ble CERC and PSDF nodal agency that capacitor requirement
could not be finalized due to non- availability of the data.
• To cancel the Letter of Award issued to CPRI for carrying out capacitor studies
for 2016-17 and 2017-18.
In this OCC meeting representative of DTL, PTCUL stated that they have submitted
the data. Representative of UPPTCL and Haryana stated that they would submit the
data within a week time. OCC recommended that the matter may be taken up in
TCC/NRPC meeting.
15
SE, NRPC stated that in the 13th NRPC meeting held on 27th June 2009, scheme of
Automatic Meter Reading from Interface Meters in Northern Region was approved.
He added that in last OCC meeting, it was decided that NRLDC and POWERGRID
would submit the joint status report of AMR at the end of every month.
It was informed that joint report for the week 26.09.2016 to 02.10.2016 had been
received by NRPC secretariat.
NRLDC and POWERGRID were requested to submit the joint status report of AMR
at the end of every month regularly.
15. SPS for the Tehri complex for the contingency of any of the circuit of 400
kV Koteshwar-Merrut line
In the 127th OCC meeting, the scheme with following logic was approved:
16
“When all the four machines (i.e. Tehri HPS (4 × 250 MW) and Koteshwar HPS
(4×100 MW)) are running and any one of the 400 kV Koteshwar-Merrut circuit trips,
one unit of 250 MW of Tehri HPS should be tripped instantaneously”.
1. THDC would commission the SPS for the Tehri complex for the contingency of
any of the circuit of 400 kV Koteshwar-Merrut line by 30.11.2016.
3. POWERGRID and THDC will work out the necessary details to implement the
scheme.
In this OCC meeting it was decided that THDC will finalize the scheme. Further
THDC would hold a meeting with POWERGIRD to decide the modalities of the
scheme. Representative of POWERGRID assured to extend full cooperation in
implementation of SPS.
17
However, it was clarified that the above framework was only a suggestion.
SLDC/DISCOM may decide its own course of action.
NRLDC had requested all SLDCs to submit the report of day-ahead load forecasting
to NRLDC on regular basis as per provisions of IEGC.
Members had agreed that procurement of software for load forecasting should not be
delayed. It was decided that SLDCs/DISCOMs will consider the above mentioned
broad framework and submit their comments to NRPC secretariat before next OCC
meeting.
In the 127th OCC meeting, SE, NRPC had informed that UP SLDC had given its
consent to participate in the above mentioned scheme provided three months
demand forecast on trial basis is free of cost.
In the meeting, it was decided that all the SLDCs would submit present status of load
forecasting and details about the tool being used for this task by 30.09.2016. This
would also include an analysis of load forecasted vis-à-vis actual load on hourly
basis for a reasonable period of say one month. It was also decided that the
willingness to participate in the above mentioned process of procurement of tools
may be submitted by the SLDCs /Discoms by 30.09.2016.
Representative of Uttarakhand SLDC stated that they were already using scientific
tools for demand forecast. It was decided that Uttarakhand SLDC would make a
presentation in next OCC meeting regarding their forecast model.
In this meeting, SLDCs were requested to send 15-minute wise day ahead demand
forecast and actual demand on that day, to NRPC secretariat and NRLDC for the
period 25th to 31st October 2016.
Representative of NRLDC stated that SLDCs may directly upload the forecast
figures to NRLDC’s ftp server.
17. Compilation of data regarding failure of CTs and replacement plan of older
CTs
Sometime back NRPC Sectt. had requested utilities to provide data of CT failure
for the last 5 years. All the utilities had meticulously submitted and compiled the
data; however the format sought date of commissioning of switchyard however
intention was to get the date of commissioning of CT. Hence, all the utilities
were requested to supply the data and any other updated/missing data so that
further necessary action can be taken.
Information for RVPNL, Adani Power Limited, POWERGRID (NR1), DTL,
THDCIL had been received.
PSTCL, NTPC, NHPC & NPCIL submitted the data in the meeting/just after
meeting. All other utilities assured to submit the data on priority. As
discussed in the meeting, the email to the utilities who have not supplied
the data was resend for due compliance at their end.
18
18. Targets fixed for Load Relief from operation of df/dt & UFR relays in Punjab
– Review thereof
SE, NRPC recalled that this agenda item was brought in the 127th OCC meeting by
PSTCL. In short, PSTCL had contended that variation in their load from summer to
winter was such that they were not in a position to meet targets of automatic load
shedding under UFR, df/dt and SPS.
In the 127th OCC meeting, it was informed that the issue was deliberated in 5th NPC
meeting held on 05.04.2016 wherein it was decided that it would suffice if NR as a
whole is able to meet the desired load relief. It was decided that to work out the
same, a format would be circulated to submit the load data of the feeders where
UFR based load shedding scheme have been installed. For submission of data two
typical scenarios of July and January were to be taken. Accordingly, the format was
finalized and SLDCs were requested to furnish the information regarding automatic
load shedding under UFR scheme in the prescribed. The format was enclosed at
Annex – XIII of the minutes of 127th OCC meeting and Annex- VII to the agenda of this
OCC meeting. .
It was noted that none of the SLDCs had submitted the information. Members
agreed to submit the information within 15 days.
19
Net Average Inter-Regional import was decreased by 6.42 MU/day during
September, 2016 as compared to corresponding month in previous year.
Net Average Import from WR decreased by approx. 11 MU/day during
September, 2016 as compared to corresponding month in previous year.
Net Average Import from ER increased by approx. 3.36 MU/day during
September, 2016 as compared to corresponding month in previous year.
Net Average Import from NER increased by approx. 1.22 MU/day during
September, 2016 as compared to corresponding month in previous year.
Members were requested to forecast generation & load and plan for generation
including keeping reserves to avoid such overdrawal/deviations.
It was decided that apart from forecasting of demand, the ramp forecasting is
essential to maintain grid discipline & grid safety during such high ramp periods.
All the SLDCs agreed to put more efforts on forecasting. It was also agreed that in
line with IEGC and Ancillary Services procedure, all SLDCs would send their
states forecast to RLDC.
20
“Each region should maintain secondary reserves corresponding to the largest
unit size in the region and tertiary reserves should be maintained in a de-
centralized fashion by each state control area for at least 50% of the largest
generating unit available in the state control area“
He added that the need for maintaining reserves Primary, Secondary and tertiary
have been felt since long. However, with the improvement in frequency profile
through concerted efforts of all the stakeholders and tightening of frequency band,
deviations etc., it is extremely important to have the reserves in the system all
time. Reserves are important to cater the error in load forecasting, continuous
deviations, inclement weather related deviations and forced generation outage.
Members were requested to update the status of spinning reserves and expedite
the same.
23. Outage Planning for Rihand III STPS (Generating Unit #5)
Representative of NRLDC stated that NTPC had earlier submitted their plan to
taking Rihand Generating Unit#5 for planned maintenance work from 15.09.2016
to 09.10.2016. NTPC had informed during the 127th OCC Meeting held on
16.09.2016, that due to non-availability of “GRP component”,they were not taking
the s/d as planned and they would take the m/c shut down only in the month of
November 2016. Accordingly, the transmission line outage were finalised and
approved by the OCC. During last week of September 2016, due to poor quality of
coal and other reasons, generation availability in Singrauli, Rihand, Anpara
complex was approximately 3000 MW less than normal condition. NTPC on 29th
September 2016 informed NRLDC that they were planning to take Rihand #5
under S/D for planned mtc work. NRLDC advised them to defer the planned
maintenance activity (citing reference to low generation availability in the complex
and OCC discussions) till generation availability in the complex improves.
However, it was observed that NTPC took out Rihand U#5 (500MW) for planned
mtc work on 30/09/2016. He expressed concern over non-compliance to the
outage schedule finalized by OCC and non-compliance to advice of NRLDC.
Representative of NTPC stated that Coal India had informed them that the coal
mines had been flooded and coal production would be affected for about 15 days.
Further, due to massive fire last year, cable was to be replaced by armored cable
and this work was pending. Therefore, their management had decided to
shutdown the machine.
SE, NRPC stated that not following decisions of NRPC forum and instruction from
RLDC, comes under non-compliance of IEGC and could have led to serious
consequence.
Representative of NTPC assured that this type of instances will not be repeated in
future.
21
24. Winter Preparation
In 127th OCC meeting NRLDC representative stated that during summer/monsoon
month, daily voltage variation is in the range of 10 kV while the same is in the
range of 15-20 kV due to demand variations over the day while the base itself
would increase by 10 kV. Thus, very high voltages are expected specially during
off peak hours. It was also stated that due to load group change by Rajasthan,
approx. 500-800 MW load of Rajasthan drops at 0400 hrs, causing very high
voltages and at times tripping of lines on over voltage.
Representative of NRLDC stated that for smooth operation of system in ensuing
winters, measures are to be taken by the utilities. Following measures were
suggested by NRLDC:
In 127th OCC meeting OCC advised HP and Punjab states also to give
feedback on the synchronous condenser operation of units in their
state control area so that same may be used in condenser mode
during this winter.
23
Representative of NRLDC stated that this year, gas units have been
commissioned in the state of Uttarakhand. SLDC Uttarakhand was
requested to inform about their capability in respect of synchronous
condenser operation.
NRLDC representative stated that the formats had been shared in the 127th OCC
meeting but information was not received in proper format.
All the utilities were requested to send the data in proper format at the earliest.
It was also decided that in case of part ownership of a transmission line, the owner
of major part of transmission line would submit the data for the whole line.
C. Weather data: Following information w.r.t weather data shall be checked and
updated
a. Correct Temperature and Humidity data from all the locations.
b. SCADA displays for better visualization of this data in the control
centers
c. IMD website (Link on NRLDC website too and also available on SLDC
website)
d. Other weather monitoring websites
It was highlighted that some of the states were continuously violating the
regulations. Members were requested to take action to avoid such violations.
24
It was emphasized that in the absence Area Control Error (ACE) of respective
control areas should be monitored and corrected expeditiously.
26. Multiple element tripping events in Northern region since last OCC meeting:
NRLDC representative stated that despite persistent discussions/follow-up in
various OCC/PCC meetings, the compliance of the regulations was still much
below to the desired level.
He requested members to impress upon all concerned for providing the
Preliminary Report, DR/EL & Detailed Report of the events in line with the
regulations and also take expeditious actions to avoid such tripping in future
Members were asked to submit Detailed Analysis Report to NRLDC with a
copy to NRPC sectt., of these incidents suggesting the remedial measures
to avoid the recurrences of these types of incidents.
Representative of NRLDC stated that one FRC based event had occurred
since last OCC meeting. It was added that NRLDC had computed the FRC
and request was sent to state control areas along with other regional entities
to compute the same at their end.
FRC observed for each state control area for the event was also presented in
the meeting. The response from states as well generators was poor.
Utilities were requested to submit the FRC of their control areas. Members
agreed for the same.
NRLDC representative stated that 400kV Delhi Ring was open since last 2 years.
He informed that 400kV Bawana-Mundka, Jhatikara-Bamnauli ckt and
Ballabgarh-Bamnauli ckt of Delhi Ring were open. Due to opening of Delhi Ring,
26
multiple incidents of load loss/generation loss were observed at 400kV Bamnauli
station. During Sep,16 there were 4 trippings at Bamnauli/BTPS , where lod loss
up to 650 MW was observed. Apart from these tripping, load of South Delhi area
also affected due to limited connectivity. It was clearly observed during multiple
element tripping in BTPS, Ballabgarh(BBMB), Samaypur(BBMB).
While expressing concern on opening of Delhi ring since a long time, OCC
advised concerned utilities to submit reports for the incident so that the
event could be analysed for taking necessary remedial measures to avoid
such incidences.
30. Prolonged Fault feeding during failure of R-phase CB at 400kV Mau station:
27
~20 second during the incident which is very high in comparison to 100 ms
prescribed in CEA Grid standard.
31. System Operation and constraints in J&K Valley during Winter months:
NRLDC representative stated that during winter months, Kashmir valley needs to
import most of its demand in view of low hydro power availability. Connectivity
from rest of the grid play vital role during power import. Kashmir valley power
system is connected through rest of the grid through following 4 transmission lines
Therefore, during winter season and high import requirement, any contingency of
lines especially 400 kV ones would create severe bottleneck for power supply to
valley area. These contingencies had also resulted in collapse of valley power
system at times
He further stated that the valley power system also witnesses following points of
concern during winter months:
1. Low voltage in valley area due to high reactive drawal
2. Outage of transmission lines due to bad weather/heavy snowfall
3. Split bus operation at Baghlihar HEP
4. Limited connectivity with rest of the grid.
While expressing concern on several past trippings in the valley he mentioned that
After January,2012 incident, Central Electricity Authority (CEA) had approved a
System Protection Scheme (SPS) to avoid such tripping of power system in
valley. However, status of implementation of the scheme was not known.
28
2. Expeditious commissioning of SPS scheme for valley (As approved by
CEA)
3. Alertness and quick action in case of any contingency.
4. Deployment of capacitor banks, under frequency schemes etc.
5. Operation of GTs at Pampore at the time any contingency.
6. Readiness for black start capability at all black-start capable generating
stations. A mock exercise for the same could be done at a convenient
date.
No representative from PDD, J&K was present in the meeting. OCC expressed
concern about the issues. It was decided that NRPC Sectt. would take up the
issue with PDD, J&K.
“(c) UFRs and df/dt relays also be mapped on the SCADA system of each state so
that they can be monitored from SLDC/NRLDC.
(d) All STUs and SLDCs to map/network the UFR and df/dt on their SCADA
system.”
The issue has also been discussed in various OCC meeting , wherein it was
decided that both digital and analog values, of the feeders where such relays had
been installed, should be monitored.
In 120th OCC meeting, a uniform formats for mapping of UFR & df/dt in
SCADA systems for all the states for visualizing the feeders was suggested by
NRLDC. These formats have to be compiled by respective state/SLDC by co-
coordinating with respective SCADA team of SLDCs.
Considering that communication from all UFR and df/dt relays was yet not
available, it was decided in 124th OCC meeting that wherever, such issues are
arising, the transformers at 220kV or 132 kV substations be monitored and
mapped in the SCADA as alternate monitoring point.
The issue was again discussed in 125th, 126th and 127th OCC meeting of NRPC.
The status of UFR and df/dt SCADA displays of different states/UTs as received
at NRLDC was discussed in detail.
Representative from Punjab stated that mapping would be completed within week.
HP representative informed that all the activities had been completed.
29
33. Revision of document for Reactive Power Management for Northern
Region:
34. Revision of document for System Restoration Procedure (SRP) for Northern
Region:
NRLDC representative informed that system restoration procedure for Northern
region was due for revision. The last updated document link had already been
shared with the constituents.
Utilities were requested to give their feedback, suggestion & updated information
latest by 30th November 2016 in order to revise the System Restoration procedure.
It was also informed that NRLDC had planned to organize one day workshop for
system restoration in Northern Region on 29th Nov 2016.
Representatives from all power stations were requested to be present in the work
shop & share details regarding the following:
• Healthiness of Diesel Generator(DG) sets at black start sources
• Capability curve of the black start generator
• Governing system at generating stations for frequency control
• Experience of black start exercise conducted recently
He informed that Railways would also be requested to be present & share latest
details regarding traction feeding points, traction load, provision for phase balancing
(Scott Connection) & contact details of nodal persons etc.
30
NRLDC representative suggested that one or two state representative may prepare
presentation for restoration procedure of their state and share the details during the
workshop. He requested all the constituents to depute the concerned officer for the
workshop.
Quote :
Unquote :
He stated that similar to WR, NTPC ISGS stations in NR also face scheduling
issues. With respect to coal stations, the scheduling problem is more aggravated in
Gas Based Stations, namely Anta, Auraiya and Dadri-Gas. Due to limited availability
of domestic gas and non-availability of schedules from beneficiaries on alternate
fuel, Gas Stations are either run part on capacity or taken under complete Reserve
Shut Down (RSD). During part module operation, DC on GF gets restricted to ON-
BAR capacity and entitlements of beneficiaries also get curtailed.
31
NTPC representative further stated that in line with WRPC decision, allowing such
beneficiary(s) states to requisition surplus ON-BAR power available at a particular
station (restricted upto its overall share based on ON-BAR capacity) would not only
ensure effective utilization of surplus power availability within the region, but also
help in curtailing ATC/TTC violations. This arrangement would also enhance the
probability of getting the domestic gas fully consumed which otherwise always
remain a matter of great concern due to Take or Pay obligations with supplier.
The issue was deliberated. Members felt that in view of complexity involved
further deliberation is needed. It was also opined that help of WRPC/WRLDC
may be taken to understand the mechanism implemented in WR. It was
decided that the matter would again be discussed in next OCC meeting.
Briefing the members, SE, NRPC stated that in accordance with the (IEGC) (Fourth
Amendment) Regulations, 2016, NRPC Sectt had prepared draft mechanism for
compensation to Generating Stations for degradation of Heat Rate, Auxiliary
Consumption and Secondary Fuel Oil consumption due to part load operation and
multiple start-ups of units.
The said draft was brought in the 31st Commercial Sub-Committee (CSC) meeting
held on 04th July, 2016 and 125th OCC meeting held on 22nd July, 2016 for detailed
discussion and deliberation among the stakeholders. Accordingly, the draft was
modified by incorporating the views of stakeholders. Subsequently, a meeting was
held among the officials of CERC and NRPC Sectt. on 01.09.2016 at NRPC Sectt.,
New Delhi and based on these deliberations, the modified was enclosed as Annex -
VII of the agenda for 127th OCC.
In the 127th OCC meeting, NTPC representative sought time for submitting comment
on revised draft. Other members had no comment to offer on revised draft. It was
decided that all the members including NTPC may submit comment to NRPC
secretariat within a week. After receiving the comment, if required, a separate
meeting may be called to discuss this issue; otherwise the matter would be put up
before TCC/NRPC for ratification.
Comments were received from NTPC which were placed in Agenda.
In the meeting, NTPC proposed for calculation of the compensation on time block
wise instead of on monthly basis. It was also mentioned that the total compensation
by any beneficiary during a calculation period shuld not be negative.
32
SE, NRPC stated that Staff of CERC had indicated that a meeting would be called by
them to bring uniformity in the compensation mechanism among all RPCs. OCC
recommended thatproposal in the present form along with comments of NTPC can
serve as starting point for meeting with staff of CERC. The same may also be taken
to TCC/NRPC .
SE, NRPC stated that BBMB had submitted a proposal for funding from Power
System Development Fund (PSDF) for Renovation and up-gradation of Protection
System of various Sub-tations and Power Houses. Appraisal committee of the PSDF
has requested BBMB to get the proposal appraised from NRPC. Accordingly, the
proposal was submitted by BBMB to NRPC for appraisal. The salient points of the
proposal are:
• In line with the observations of protection audit , it is proposed to provide Bus
Bar Protection at two 220 kV sub-stations namely Delhi & Kurukshetra.
• At 220 kV Ganguwal s/s, 220 kV Switchyard of Bhakra Right Bank, Dehar
Power House & Pong Power House, existing old Electromechanical realys are being
proposed to be replaced with Numerical ones to comply with Protection audit
observations.
• The old electromechanical Unit Protections provided at Bhakra right & Pong
Power Houses are also being proposed to be replaced.
• Redundant DC sources are required to be provided at 220KV substations of
BBMB to ensure reliable grid operation.
• At some of the substations, existing CTs are required to be replaced because of
High Tan Delta. Also some of the CTs, which are quiet old and have oil leakage,
are also proposed to be replaced.
• PTs/CVTs at some of the substations are required to be replaced in view of
providing synchronizing facility and ageing.
• Synchronizing trolleys at 220kV GSS, Dhulkote and Sangrur are to be provided
to ensure trouble free operation during restoration of the Grid.
• Replacement of existing old and obsolete PLC terminals along with protection
couplers have been proposed for smooth operation of PLCC equipment.
NPCIL representative stated that islanding scheme for RAPS-A and RAPS-B was
not functional. After the failure of RAPS-A & RAPS-B islanding scheme during
grid event of 30/07/2012, a new scheme was proposed by RRVPNL in year 2013
33
which was under discussion in PCC. This scheme was with inclusion of Mahi HEP.
NRPC after reviewing RRVPNL proposed islanding scheme, raised the concern on
the success of this scheme in PCC meeting He mentioned that as per 30th PCC
MOM, this islanding scheme implementation was awaited, as the results of
dynamic simulation studies with or without inclusion of Mahi HEP had not been
received from CPRI. He requested for speedy implementation of islanding
scheme for RAPS-A & RAPS-B.
SE, NRPC stated that the matter was deliberated in the 31st meeting of the
Protection sub-committee and representative of RVPNL had informed that the
procurement process for this islanding scheme was underway and the scheme,
without considering Mahi, was expected to be functional by December, 2016.
Members noted the above.
39. Certification of Non-ISTS line for inclusion in PoC Charges
SE, NRPC informed about that the Central Electricity Regulatory Commission (Sharing of
Inter State Transmission Charges and Losses) (Third Amendment) Regulations, 2015,
which requires certification by the RPCs regarding Non-ISTS lines for inclusion in PoC
charges.
He recalled that according top aforesaid provision, it was decided in 31st TCC/35th NRPC
meeting held on 08th /09th July, 2015 to constitute a group to recommend a methodology
for the study to be conducted by NRPC Secretariat, in consultation with RLDC. Based on
the methodology suggested by the group, the study was carried out for certification of the
non-ISTS lines submitted by UP, Punjab and Rajasthan.
He informed that the following transmission lines, fulfill the criteria recommended by the
group and were to be recommended for certification as ISTS for the current Financial
Year by NRPC Secretariat:
It was explained that the complete list of transmission lines submitted by STU sub-divided
in following categories was available as Annex to the agenda:
34
(i) Transmission lines, which fulfill the criteria recommended by the Group and
hence are recommended to be certified as ISTS
(ii) Transmission lines, which do not fulfill the criteria recommended by the
Group and hence may not be certified as ISTS
(iii) The lines, which were claimed to be used for inter-state transmission by
STUs but were not modelled in the PoC transmission charge calculation and
hence exercise to see whether or not these lines carry inter-state power
could not be carried out. It may be mentioned that the responsibility to
submit the requisite details for modelling the lines in PoC transmission
charge study rests with STU concerned.
(iv) The transmission lines which are natural inter-state lines and hence need not
be certified as ISTS.
It was further informed that fresh claims for certification of non-ISTS lines being used for
inter-state power will have to be submitted by end of December 2016.
OCC recommend the proposal to certify the transmission lines as mentioned above, for
approval of NRPC. Members were apprised that for the certified lines all the CERC norms
for ISTS lines including certification of availability would be applicable.
T1. Power Supply Position Data
SE, NRPC stated that SLDCs were furnishing monthly data in format 28 and 29
for provisional and final for Power Supply Position (PSP) , respectively. The
supply of data as per format 28 and 29 is a statutory obligation under the
provisions of CEA (Furnishing of Statistics, Returns and Information) Regulations,
2007.
In the data received from SLDCs, it has been observed that some of the states
are showing restricted demand data, while in the format it is clearly mentioned
that unrestricted requirement ( in MU) and unrestricted peak demand ( in MW)
data is to be furnished. Furnishing restricted requirement /demand data is
violation of statutory provisions of CEA Regulations.
It had also been observed that many of the states are showing NIL shortages in
the data being furnished to NRPC secretariat in above mentioned formats,
whereas in the data available from other sources, it is evident that power cuts
has been imposed .
Matter was discussed and all the SLDCS were requested to furnish correct
data in the prescribed format.
T2. Issue arising out of Three and Half Hour KWHEP Plant Shutdown Since
01.10.2016
35
Representative of SJVN stated that from 1st October 2016, daily generation
schedule of KWHEP had been revised in such a way that there was a
complete plant shutdown of three and half hour duration starting at 06:00 hrs
till 09:30 hrs. This lean season, NJHPS and RHEP are totally dependent on
KWHEP, for water requirement. As per NRLDC instructions, machines need
to generate near peak load during these morning hours. He added that
NJHPS is an RoR plant and do not have a huge pondage, therefore, it was
not possible to generate and sustain peak generation when upstream power
plant was not releasing water.
SJVN representative requested that at least 300MW schedule be given to
KWHEP in these hours, so that NJHPS can generate as per NRLDC
instructions.
It was decided that Rajasthan and Haryana will schedule power from KWHEP
in peak hours as per NRLDC notification for peak hours.
36
Annexure - IA
List of Participants in the 128th OCC meeting held on 17.10.2016 in NRPC Conference Hall,New Delhi
37
K.Pandey AEN(RUVNL) RVPNL 9413391556 ceruvn@gmail.com
A.K.Saxena AEE(PPMC&IT) RVPNL 9413385957 CEPPMCIT@rrvun.com
C.L.Koli SE(PP) RVPNL 9413385340 se.pp@rrvun.com
Atul Sharma XEN(SOLD) RVPNL 9413382632 sharma.atul1@rvpn.co.in
A.J.Siddiqui UP-SLDC UPPTCL 9415609363 ajsiddiqui1962@gmail.com
Pankaj Saxena EE-STU UPPTCL 9415902780 smart.saxena@gmail.com
Kavindra Singh UP-STU UPPTCL 9412749803 skavindra@yahoo.co.in
Pankaj Malviya SE UPPTCL 9450909474 setnclko@gmail.com
se.omc_3.parichha@uprvunl.or
Sheikh Salim SE UPPTCL 9415900086
g
Amin Aziz SE UPPTCL 9412749817 setncmrt@gmail.com
Vinayak Shaily EE UPPTCL 7088117954 vinayadl_shaily@ptcul.org
P.Mediratta AGM(NTPC) APCPL 9416212411 pmediratta@ntpc.co.in
Shashi Saini DM-elect.CLP LANCO APTL 8198900924 shashi.saini@clpindia.in
Sumit Sinha DM-elect.CLP LANCO APTL 8198900928 sumit.sinha@clpindia.in
P.S.Mhaske MS NRPC
Ajay Talegaonkar SE(O) NRPC
Hemant Pandey SE(S) NRPC
Naresh Kumar EE(O) NRPC
Gourav Jasuja AEE(S) NRPC
Sonia Chauhan ASE NRPC
38
Annex - I
Harduaganj– Completed.
39
Annex - II
Status of pending rectification of Defects observed during BPA pertaining to
operation of PLCC
S. Utility Sub-Stns/Switchyards
No.
1 UPPTCL 400 kV Sultanpur S/s: 220 kV Panki S/s: 220 kV Moradabad S/s:
(i)Bithoor-Unnao–service LILO of Moradabad-C.B.
i) 220kv Sultanpur- New Tanda - engineer awaited. Ganj at 220 kV Rampur
Completed S/s- Data Channel
commissioned. Protection
ii) PLCC system for 220 kV
panel by November 2016
Phoolpur– Sultanpur line liloed at
Pratapgarh. The PLCC System
shall be commissioned at 220 kV
Pratapgarh-Sulanpur and 220 kV
Pratapgarh - Phoolpur lines by
October 2016;
iii) 220 kV Sohwal line- ETL
Panel is defective, replacement
by November 2016;
400 kV Murzaffarnagar S/s: 220 kV Fatehpur:
220 kV Allahabad S/s:
220 kV MZN-Shamli line – Fatehpur-PGCIL-I/II, Service
Material partly received at MZN Engineer is awaited. Expected (i) 220 kV Jhasi-Phoolpur-;
and HF cable, LMU & Wave Trap by November 2016
(ii) 220 kV Allahabad-
at Shamli to be received.
Rewa-Road I/II-.
Expected commissioning by
October 2016. UPPTCL informed the
revised date as October,
2016
400 kV Bareilly S/s: 220 kV Nara S/s:
(i) PLCC for 220 kV Dohana-C.B.
Ganj and Bareilly by November, i) LILO of Nara-Rishikesh at
2016 Roorkee pertains to PTCUL
(ii) Protection coupler for 220 kV th
PTCUL informed in 124 OCC
line at Sahjahanpur – expected
meeting that that LMU of the
by Sept. 2016
PLCC is to be replaced and
(iii) BPL Panel on 220 kV line to PLCC has been functional
Pantnagar is defective and PLCC from 30.06.2016.
system of 220KV lines pertains to
PTCUL. Revised target Dec UPPTCL informed that PLCC
2016 not working.
40
Annex - III
Status of pending work regarding Bus Bar Protection found non-
operational/defective/non-installed in BPA
S.No. Utility Sub-stns/Switchyards
400 kV Azamgarh S/s – 400 kV Kasara(Mau) 400 kV Sultanpur S/s- 400
expected completion by S/s expected kV BBP-
October’16 completion by expected completion by
UPPTCL 220 kV Azamgarh S/s – October’16 November’16
1
Commissioned
400 kV Panki-November,
2016
Harduaganj TPS S/Y – Siemen’s Service Engineer is awaited. Expected completion
2 UPRVUNL
by November 2016
41
Annex - IV
42
Annex - V
43
Annexure – VI
A. Generating units which are out for a long period and have not been revived
are listed as under:-
Gen. Stn./ Unit No. Date from Reason of Outage Expected date of
S.
which under revival
No.
outage.
09.10.2004 Regulatory clearance Not available
1. RAPP A unit -1
01.07.2010 R & M Work 31.10.2016
2. Obra # 7
10.07.2011 R & M Work 30..11.2016
3. Obra # 11&10
21.03.2014 R & M Work 31.05.2017
4. Dehar # 6
11.07.2014 Bed Material Leakage Disinvestment has been
5. Giral # 1 &2
27.1.2016 proposed by the
Government
16.07.2015 GT Compressor Rotor 31.12.2016
6. Bawana GPS # 1
fault
2.7.2016 Under R&M 31.12.2017
7. Paricha #1
19.8.2016 DC not offered by Not Known
8. GVK #1
generator
10.8.2016 DC not offered by Not Known
9. GVK #2
generator
12.4.2016 Annual Maintenance Not Known
10. Bhakra –L HPS
12.5.2016 Less Gas Availability Not Known
11. Dadri GPS #6
20.6.2016 Less Gas Availability Not Known
12. Auraiya GPS #6
6.8.2016 Less Gas Availability Not Known
13. Dadri GPS #4
17. 2.2016 Less Demand in Not Known
14. Suratgarh #1
Rajasthan
8.1.2016 Less Demand in Delhi Not Known
15. Bawana GPS #4
24.3.2016
#2
21.8.2016 Due to Electrical Fault Not Known
16. Anpara TPS#3
1.4.2016 Less Demand in UP Not Known
17. Lalitpur TPS #3
4.6.2016 Annual Maintenance Not Known
18. Kalisandh TPS #2
20.8.2016 Less Demand in Punjab Not Known
19. GHSTPS#2
21.8.2016 Less Demand in Punjab Not Known
20. GNDTPS#2
B. System elements that had been out of service for a long time and not revived are
as under:
50 MVAR, 400 kV, Bus • Out Since 16.02.2009
1.
Reactor at SARNATH.
• Rector would be replaced by 125 MVAR reactor
• Tender opened on 07.06.2013.
• LoI placed in December, 2013.
• Expected commissioning by 31.10.2016.
2. 63 MVAR, Bus reactor at • Reactor burnt.
Dadri
• 125 MVAR Reactor is to be installed.
44
• Process for procurement of new reactor underway.
• Re-tendering being done.
• Financial bid opened
• LoA placed on 02.05.2016 with completion target of
18 months.
• Expected commissioning by Nov’17
3. FSC at Kishanpur on • Became redundant (Spare).
Kishanpur-Pampore line I &
• Due to shortened line length on account of LILO of the
II
line at Mirbazar and Ramban.
• Relocation planning being done.
4. FSC of Meerut-Koteshwar -II • Out since 16.07.2015
• Fire in FSC
• Expected by March 2017
5. FSC of Unnao-Bareilly -I • Out since 19.04.2015
• Fire in FSC
• Expected by 31.3.2017
6. FSC of Panki-Aligarh -I • Out since LILO of Panki-Muradnager line.
(10.09.2015)
• Matter reported to CTU
• Relocation planning being done
7. 400 kV Bamnauli - • Out since 22.05.2016
JattikalaCkt-I
• Tower damaged.
• Expected by Nov, 2016.
• Ckt-2 is charged on ERS tower.
8. 315 MVA ICT at Kalisindh • Out since 04.06.2016
• Buchholz relay operated
• Expected by 31.03.2017
9. ICT at Muradnagar • Out since 16.9.2016
• Due to fire
• Expected by 31.10.2016
10. Reactor at Greater Noida • Out since 6.8.2016
765 KV
• Due to Buchholz relay operation
11. 315MVA ICT 2 at Jodhpur II • Out since 10.8.2016
• Due to Buchholz relay operation
12. ICT-1 at Anta RS 765KV • Out since 17.8.2016
1500 MVA
• Manually operated due to fire in control panel
• Expected by 31.10.2016
13. Kishenpur 80MVAR B/R • Out since 2.2.2016
• For voltage regulation
14. Bawana-Mundka1&2 • Out since 27.9.2016
• To raise the height of towers of 400KV Bawana-
Mundka line which are infringing in the Metro Corridor
15. Bareilly 50MVAR B/R • Out since 5.8.2007
• Failure of Reactor
16. Wagoora 50MVAR B/R • Out since 22.4.2015
• Take out due to low voltage
17. TCSC of MUZPR-I at GRKP • Out since 17.9.2016
• Block problem of Y&B phase
45
18. Anta RS –Chabra -1 • Out since 19.8.2016
• Keep open on over voltage
46