Professional Documents
Culture Documents
Problem-01:
Fred Jacobs, assistant manager of Home and Hearth, is reviewing the cost associated with the store’s best-selling frying pan. The
data available to Mr. Jacobs concerning this frying pan follow.
Demand = 20units/week
Order cost = $75/ order
Holding cost = $15/ unit/yr.
Home and Hearth operates 50 weeks per year.
a) The current order quantity is 125 units per order. What is the annual ordering Cost, holding cost and total cost?
b) Jacobs has recently learned of the economic order quantity in his Operations management class. If Home and Hearth
implemented the EOQ, what are the changes Jacob found in ordering cost, holding cost and total cost?
c) It is time for periodic review. How much kitty litter should be re-ordered?
a) Calculate the item’s EOQ. What is the average time between orders in weeks?
b) Find the safety stock and re-order point that provides a 95% cycle service level.
c) For these policies, what are the annual cost of (i) holding the cycle inventory and (ii) placing orders.
d) A withdrawal of 15 units just occurred, is it time to re-order?
S = $54
Price = $11.70
H = (27%)($11.70) = $3.16
2 DS 2(4,680)($ 54)
EOQ 159,949.37
H $3.16 = 399.93, or 400 bags.
Q 400
0.08547 years 4.44 weeks
D 4680
b. Reorder point, R
R = demand during protection interval + safety stock
dLT d L = 15 3 = 25.98 or 26
R 270 22 292
When the EOQ is used these two costs are equal. When Q 500 , the
annual holding cost is larger than the ordering cost, therefore Q is too
large. Total costs are $789.75 + $505.44 = $1,295.19.
Total cost using EOQ is $1,263.60, which is $31.59 less than when the
order quantity is 500 bags.
z = 0.84
P L d P L
P L (6.124) 27 18 = 41.08
T = (15*45) + 35 = 710
z d L
Safety stock: = (1.65)(100) 2 = 233.34, or 233 units
c. cost
P is rounded to 2 weeks.
P L d P L
EOQ 179
P 0.0895 years 4.475
D 2000 or 4.0 weeks
L = 4 weeks
Safety stock:
The westerville Auto parts company produces rocker-arm assemblies for use in the steering and suspension system
of four wheel drive trucks. A typical container of parts spends 0.02 day in processing and 0.08 day in material
handling and waiting during its manufacturing cycle. The daily demand for the part is 2000 units. Management
believes that demand for the rocker-arm assembly is uncertain enough to warrant a safety stock equivalent of 10
percent of its authorized inventory.
(a) If there are 22 parts in each container, how many Kanban cards sets (production order and withdrawal cards)
should be authorized?
(b) Suppose that a proposal to revise the plant layout would cut materials handling and waiting time per container to
0.06 day. Hoe many card sets would be needed
A company using a kanban system has an inefficient machine group.. For example, the daily demand for part L105A
is 3000 units. The average waiting time for a container of parts is 0.8 day. The processing time for a container of
L105A is 0.2 day and a container holds 270 units. Currently 20 containers are used for this item.
c) Suppose that the policy variable, α was 0. How many containers would be needed now? What is the effect
of the policy variable in this example?
Problem-03: (Exercise problem 2 page 317 krajjewski)
A fabrication cell at Spradley’s Sprockets uses the pull method to supply gears to an assembly lines. George Jitson is
in charge of the assembly line which requires 500 gears per day. Containers typically waits 0.2o day in the
fabrication cell. Each container holds 20 gears and one container requires 1.8 days in machine time. Setup times are
negligible. If the policy variable for unforeseen contingencies is set at 5 percent, how many containers should Jitson
authorize for the gear replenishment system?
You are asked to analyse the kanban system of LeWin, a French manufacturer of gaming devices. One of the
workstations feeding the assembly line produces part M670N. The daily demand for M670N is 1,800 units. The
average processing time per unit is 0.003 day. LeWin’s record show that the average container spends 1.03 days
waiting at the feeder workstation. The container for M670N can hold 300 units. Twelve containers are authorized for
the part.
a) Find the policy variable, α, that expresses the amount of implied safety stock in this system
b) Use the implied value of α from part (a) to determine the required reduction in waiting time if one container
was removed. Assume that all other parameters remain constant.
An assembly line requires two components: gadjits and witjits. Gadjits are produced by center 1 and widjits by
center 2. Each unit of end item called a jit-together, requires 3 gadjits and 2 widjits. The daily production quota on
the assembly line is 800 jit-togethers.
The container of gadjit s holds 80 units. The policy variable for center is set at 0.09. The average waiting time for a
container of gadjits is 0.09 day and 0.06 day is needed to produce a container. The container for widjits holds 50
units and the policy variable for center 2 is 0.08. The average waiting time for container of widjits is 0.14 day, and
the time required to process a container is 0.20 day.
Problem-06:
A toy company uses a Kanban system to make a metal fastener of several toys. The waiting
time for a container of the fasteners during production is 0.25 day; average processing time
is 0.15 day per container. Each container holds 200 fasteners. The daily demand of the
fastener is 2000 units. Using an efficiency factor of 5%, calculate the number of Kanban card
sets needed for the fasteners.
Problem: 03
Spradleys’ Sprockets
d ( w )(1 )
k= c
k = 52.5
Problem: 04
LeWin
a. Solving for implied policy variable,
d ( w )(1 )
k= c
12 300
1 a 1.0256
1,800 1.05 0.003 300
1.0256 1 0.0256
w 0.888 days
105 .
. 0888
1543%
.
105
.
Problem: 05
k=5
k = 12
PROBLEM: SUPPLY CHAIN MANAGEMENT / DESIGN (Chapter 9)
Jack Jones, the materials manager at Precision Enterprises… is beginning to look for ways
to reduce inventories. A recent accounting statement shows the following inventory investment
by category: raw materials $3,129,500; work-in-process $6,237,000; and finished goods
$2,686,500. This year’s cost of goods sold will be about $32.5 million. Assuming 52 business
weeks per year, express total inventory as:
a) Weeks of supply
b) Inventory turns
3. Sterling Inc. operates 52 weeks per year and its cost of goods sold last year was $
6,500,000. The firm carries eight items in inventory: four raw materials, two work-in-
process items and two finished goods. Following table shows last year’s average
inventory levels for these items along with their unit values.
a. What is the average aggregate inventory value?
b. How many weeks of supply does the firm have?
c. What was the inventory turnover last year?
RM-2 5,000 $5
RM-3 3,000 $6
RM-4 1,000 $8
A firms cost of goods sold last year was $3,410,000 and the firm operates 52 weeks per year. It
carries seven items in inventory: three raw materials, two work in process and two finished
goods. The following table contains last year’s average inventory level for each item, along with
its value.
RM-2 2,500 $5
RM-3 3,000 $1
= $3,129,500 + $6,237,000 +
$2,686,500
= $12,053,000
= $625,000
Weekly sales
= $12,053,000/$625,000
= 19.28 wk
= $32,500,000/$12,053,000
= 2.6964 turns/year
Problem- 02: (Advanced problem 9 page 347 krajewski):
Sterling Inc.
a. Average
= 2.688 weeks.
= 19.34 turns.
PROBLEM: RESOURCE PLANNING (CHAPTER 15)
Problem-01: Exercise Problem 1 page 568 Krajewski
a. Item I has only one parent (E). However, item E has two parents (B and
C).
a. FOQ of 50 units
Item: Drive shaft Lot Size: 50 units
Week 1 2 3 4 5 6 7 8
Gross requirements 35 25 15 20 40 40 50 50
Scheduled receipts 80
Projected on hand10 55 30 15 45 5 15 15 15
Planned receipts 50 50 50 50
Planned order 50 50 50 50
releases
b. L4L
Week 1 2 3 4 5 6 7 8
Gross requirements 35 25 15 20 40 40 50 50
Scheduled receipts 80
Projected on hand10 55 30 15 0 0 0 0 0
Planned receipts 5 40 40 50 50
Planned order 5 40 40 50 50
releases
c. POQ with P = 4
Week 1 2 3 4 5 6 7 8
Gross requirements 35 25 15 20 40 40 50 50
Scheduled receipts 80
Week 1 2 3 4 5 6 7 8
Week 1 2 3 4 5 6 7 8
Planned receipts 20 70 60 95
Planned order 20 70 60 95
releases
Week 1 2 3 4 5 6 7 8
A B
F(1) F(1)
C D E F
Week 1 2 3 4 5 6 7 8
Projected on hand 305 305 135 135 135 155 155 155
25
Week 1 2 3 4 5 6 7 8
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0
Week 1 2 3 4 5 6 7 8
Week 1 2 3 4 5 6 7 8
Scheduled receipts
Two notices are identified: order 85 units of D and 430 units of F. Please
note that action notices were not asked for in the problem.