Typical Project Sequence
Typical Project Sequence
Notes:
The Process Plant Project Sequence "Chart" is a broad generalization of the major project
activities by the different groups and is not intended to be an absolutely detailed match for every
project. It was prepared specifically for use as a guide in this Training Program for Piping Leads.
To use the Chart on screen go to the first page of the Chart, Place the courser in "Cell" C-1 and
then go to "Windows (in the tool bar above) and click on "Split" This will freeze the left-hand "B"
column. Then you can scroll right to any page and you will still see the discipline designations in
the "B" column. On print-Out Column "B" will be repeted on each page.
The major Engineering and Design disciplines stretch across the pages horizontally. Their
individual activities and tasks remain in their individual horizontal bar. Joint activities are shown
grouped vertically.
The vertical fields are not intended nor should they be interpretive as implying any unit of time
such as Hours, Days, Weeks, Months or Years. They are only there for the presentation of the
data.
Instructions:
These "Notes and Instructions" along with the attached "Chart" are "Locked" and Password
protected. To make any changes you must "Unlock" the individual document first. After the
changes have been completed you should relock the document. The "password" for both
documents is located in "Cell" CO-1 of the Chart file.
Page 1 of 10
493096593.xls
PROJECT KICKOFF 1
CLIENT
Client and Company PM
jointly set time, place and
Project agenda for Kickoff meeting Arrange for
Mngmt. project
number and
Eng. Mngr space, office
En'g Mngmt & computers Establish commu
selected
Civil Lead
Civil Group Joint Kickoff meeting with
Assigned
all Leads in attendance.
Agenda includes such key
issues as Project Purpose,
Goals and Target
Structural Struct. Lead Completion Date. Other
Group Assigned items should include:
-Project Execution plan
(EPC , EPCM or other.) -
Design Execution Plan -
Manual, 2D or 3D -
Mech. Mech. Eqp. Procurement plan,
Equip. Lead Construction Plan: Stick
Group Assigned Build or Module, Direct
Hire or Sub-Contract.
Client provides all
relative documents such as
process Block Flow
Vessels
Vessels Diagram, information on
Lead
Group feed stock, and end
Assigned
products.
Notes:
Page 2 of 10
493096593.xls
Preliminary
PROJECT
Engineering
KICKOFF 2 Prelimina
Approves
CLIENT
PFDs
Project
Mngmt.
Work with
Piping on
Civil Group Civil & Structural start Plot Plan
Property Survey and developm't
Geotechnical study to Completes and issue the issues
determine issues such as results of the Site Survey
Soil conditions to Storm to all project disciplines. Work with
water drainage and Piping on
Structural disposal Plot Plan
Group
developm't
issues
Pumps
Work with
Mech. Mechanical Equip. starts Exchangers Piping on
Equip. Project Equipment list with Heaters Plot Plan
Group data on type and size Compressors developm't
issues
Other
Work with
Vessels initiates
Piping on
Vessels preliminary Vessel and
Plot Plan
Group Tank drawings with sizes
developm't
and Nozzle schedule
issues
Work with
Electrical starts Motor List,
Piping on
Electrical and other activities relating
Plot Plan
Group to Power, Lighting &
developm't
Communications
issues
Notes:
Page 3 of 10
493096593.xls
Preliminary Engineering
PROJECT KICKOFF 3 Scope, Estimate & S
Approves Approves Review and
CLIENT
P&IDs Plot Plan App. SOW
Project
Mngmt.
With input form the Client & all disciplined determine the project execution Plan (2D, 3D, or Manual)
En'g MngmtEstablish Document control System and Group to handle Project Documents.
Resolve all
P&IDS Issue P&IDs Review Plot Issue P&IDs Develop all
Company (in-house) P&ID Client
Process updated for to Client For Plan Return Approved for Utility
Reviews attended by all comments,
Group In-house Approval Comments Design distribution
disciplines update
comments (IFA) to Piping (AFD) Diagrams
P&IDs
Work with
Review Plot Perform
Piping on
Instrument Plan Return Develop Spec & Data Sht MTO of all
Plot Plan
Group Comments for all known Instru. Bulk Instru.
developm't
to Piping Items
issues
Notes:
Page 4 of 10
493096593.xls
Process
Develop Operating Instruction: Start-up, Shut-Down a
Group
Input Req'd
Electrical Data for Develop underground cable routing/Duct Banks. Coordinate all undergr
Group Computer and Instruments. Coordinate all work with the
Design
Input Req'd
Instrument Data for Develop individual Instrument connection Details, Loop Detail Drawi
Group Computer Coordinate all work with Piping and the De
Design
Notes:
Page 5 of 10
493096593.xls
Process
p Operating Instruction: Start-up, Shut-Down and Upset Conditions
Group
Civil Group
Engineering and Design Development as required. Engineering and Design Development as required.
Structural
Engineering and Design Development as required. Engineering and Design Development as required.
Group
Joint Vess.
Initiate detailed design of all piping areas
Orient. Continue detailed design of all piping areas complete
Piping complete with Structures, Pumps,
Review w/ with Structures, Pumps, Exchangers, Compressors,
Group Exchangers, Compressors, Heaters, Pipe
Process & Heaters, Pipe Racks and Piping.
Racks and Piping.
Vessels
trument connectionInstrument
Details, Loop Detail Drawings & Cable Tray sizes and routing.
Engineering and Design Development as required.
Coordinate all work
Group
with Piping and the Design Model
Notes:
Page 6 of 10
493096593.xls
es for Progress, Budget, Schedule Continue reporting by Disciplines for Progress, Budget, Schedule
Project
agement for Progress, Budget, Schedule Continue reporting to Company Management for Progress, Budget, Schedule
Mngmt.
for Progress, Budget, Schedule Continue reporting to Client for Progress, Budget, Schedule
En'g Mngmt
Process
Prepare all Discipline Final Drawings for Issue.
Group
Structural
Prepare all Discipline Final Drawings for Issue.
Group
Vessels
Insure that All In-house and All Vendor Drawings and Data have been Issued.
Group
Electrical
Prepare all Discipline Final Drawings for Issue.
Group
Instrument
Prepare all Discipline Final Drawings for Issue.
Group
Notes:
Page 7 of 10
493096593.xls
es for Progress, Budget, Schedule Continue reporting by Disciplines for Progress, Budget, Schedule
Project Produce
agement for Progress, Budget, Schedule Continue reporting to Company Management for Progress, Budget, Schedule Project Final
Mngmt.
for Progress, Budget, Schedule Continue reporting to Client for Progress, Budget, Schedule Eng. Job
Report for
En'g Mngmt Company &
Client
Process
Final Drawings for Issue.
Group
Structural
Final Drawings for Issue.
Group All groups
prepare
Follow Discipline De-Staffing Plan Final Job
Report
covering
Mech.
Scope,
or Drawings and Data
Equip.
have been Issued.
Budget,
Group
Schedule,
Follow Discipline De-Staffing Plan Lessons
learned &
other
Vessels important
or Drawings and Data have been Issued. issues.
Group
Review with
Follow Discipline De-Staffing Plan Dep't Head
and turn in
After all Isometrics are issued download Final MTO and check for to Eng.
shortages and overages. Take action to buy the Shortages. In Mngr.
Piping conversation with Construction & the Client determine what action to
Group Model update prior to Issue.
Control Check, Corrections, take on Overages.
d in accordance with Project Procedures.
Develop & follow Discipline De-Staffing Plan
Electrical
Final Drawings for Issue.
Group
Instrument
Final Drawings for Issue.
Group
Notes:
Page 8 of 10
493096593.xls
8 PROJECT KICKOFF
Fabrication & Delivery 9
CLIENT As work progresses, conduct periodic reviews as required
En'g Mngmt
Prepare Home Office (H. O.) Job Report
Process
When appropriate de-staff last personnel
Group
Structural
When appropriate de-staff last personnel
Group
All personnel
Mech.
released.
Equip. When appropriate de-staff last personnel
Discipline
Group
Leads
should be
available on
an 'As
Vessels Needed"
basis for When appropriate de-staff last personnel
Group
questions.
Prepare Discipline Final H. O. Job Report
The Project may elect to assign a Piper to the Pipe Fabrication Shop(s) to monitor progress and resolve
Piping questions. The hours and costs should be included in the Project management budget.
Group
When appropriate de-staff last personnel
Prepare Discipline Final H. O. Job Report
Electrical
When appropriate de-staff last personnel
Group
Instrument
When appropriate de-staff last personnel
Group
Notes:
Page 9 of 10
493096593.xls
PROJECT
Construction
KICKOFF 10
Finalize Start-up and
CLIENT As work progresses, conduct periodic reviews as required
Operator training
Weekly Construction Status, Progress, Budget, Schedule
Project Prepare for Care, Custody
Report Construction Status to Company Management
Mngmt. and Control turn-over
Report Construction Status to Client
Process
When appropriate de-staff supervision
Group
Structural
When appropriate de-staff supervision
Group
Mech.
Equip. When appropriate de-staff Supervision
Group
Vessels
When appropriate de-staff supervision
Group
Electrical
When appropriate de-staff supervision
Group
Instrument
When appropriate de-staff Supervision
Group