Guidelines For
Warehouse
Construction
As of 20 January 2004
Department of the Army
Surface Deployment and Distribution Command
200 Stovall Street
Alexandria Va. 22332-5000
Unclassified
INTRODUCTION
They have been asked to approve plans and blueprints prior to construction,
which they cannot do.
The purpose of these high standards is to ensure that DoD Personal Property is
stored only in facilities that will provide the highest level of protection our service
members desire and deserve.
A. SITE LOCATION.
2
3. SIZE: As a General Guideline a rate of 3 to 1 in land to building is
recommended. This allows for a truck yard, off-street parking and 100% building
Expansion. Local building codes should be checked for possible violations.
4. ACCESS: Is the Site close to ON/OFF ramps to main highway? Check for
overhead obstructions and rail crossings or access streets, which could block trucks.
Check for highway weight and height restrictions on trucks.
B. BUILDING LAYOUT
3
DIRECTION. Dust and rain will blow in when doors are open.
e. Traffic flow should allow trucks to back to the LEFT into the Dock
or/and Loading Doors. This is easier and safer for Drivers.
C. LOADING DOORS; .
D. OFFICE:
E. BUILDING EXPANSION:
3. CAR PARKING: Employee and visitor car parking is best located outside
of fenced truck yard for security reasons. Check local building codes for minimum size
requirements.
4
G. DOCK:
H. FLOORS:
Recommend floors be sealed for dust and coated with polyurethane or equivalent
for easier housekeeping and good appearances.
I. EXTERIOR WALLS:
J. ROOF:
Special attention should be paid to quality in this area. Leaking roofs are a
constant problem. Also load capacity must be considered in regions with heavy
snow fall.
5
K. ENVIRONMENTAL PROTECTION:
NOTE: The following are some of the areas that must be addressed in detail by
the engineer when providing an environmental report:
b. The temperatures inside the warehouse (especially near roof and walls) at
different times of the day in relation to outside temperatures during the same period of
time. For Example: if the temperature and conditions on a given day at 2 p.m. are 90
degrees Fahrenheit, 85% humidity with a cloudless sky, what is the temperature and
humidity extremes at various points in the warehouse, especially the wall facing the sun
and the peak of the roof.
6
L. FIRE PROTECTION:
7
g. Source of water supply __________________
h. Is water supply sufficient to sustain a fire
fighting effort at the warehouse __________________
i. Does warehouse conform to all fire safety
regulations. __________________
j. Fire Department ISO rating City/County __________________
j. Certification that Fire Division Walls within
the facility is unbroken without openings,
Page 7, Guidelines for Warehouse Construction, doors or windows
and meet a minimum fire resistance of not less that one-hour. __________________
M. SECURITY:
1. Consideration should be given to fencing all but the visitor and employee
parking areas. Security lights, private patrols and even watchdogs are further deterrents
to crime. Visit the servicing police department for patrol information and possible
security checks.
8
4. Burglar alarms that are tied into Central Reporting Stations may be
substituted for the second lock on doors and additional security on windows. Alarms
range from contact points, raise of heat, motion and sound or light beams. Discussion
with local alarm companies can determine the best system for your facility.
The RSMO does not recommend any specific type of building construction. Each
building whether concrete, metal or heavy mill construction, is considered on its own
merits.
The Western RSMO will forward a package to you containing the requirements
for approving your facility. This checklist is designed for your general information and
does not supercede specific requirements in the DTR Regulation 4500 9-R Part 4. We
suggest that you do not commit money to meet approval requirements until you and the
Western RSMO are certain that it is absolutely required for approval and that you have
Page 8, Guidelines for Warehouse Construction, successfully met all other prerequisites.
Refer to your pre-award correspondence to see which items listed below apply to the
Storage-In-Transit (SIT), Non-Temporary Storage (NTS) programs or both.
APPLICABLE REGULATON/STANDARDS:
9
SUMMARY:
Standards for facilities storing DOD Personal Property are constantly being
reviewed. It must be remembered that these guidelines are just that, guidelines, not hard,