net/publication/338146830
CITATIONS READS
0 135
1 author:
Zainal Arifin
PLN Indonesia
59 PUBLICATIONS 27 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Increasing Renewable Energy penetration on micro grid through optimization Hybrid Diesel and PV with Battery Storage system View project
Penurunan Biaya Pokok Produksi Tenaga Listrik melalui Inovasi Teknologi dan Skema Bisnis di Bidang Pembangkitan View project
All content following this page was uploaded by Zainal Arifin on 24 December 2019.
http://www.iea.org/publications/freepublications/publication/TrackingCleanEnergyProgress2017.pdf
www.pln.co.id |1
EV Global Countries
http://www.iea.org/publications/freepublications/publication/TrackingCleanEnergyProgress2017.pdf
www.pln.co.id |2
EV Global Cities
http://www.iea.org/publications/freepublications/publication/TrackingCleanEnergyProgress2017.pdf
www.pln.co.id |3
Indonesia EV Main Driven?
http://www.iea.org/Sankey/#?c=Indonesia&s=Balance
www.pln.co.id |4
EV Outlets
Level 1
Level 2
SPLU
Level 3
www.pln.co.id |5
EV Outlets
www.pln.co.id |6
EV Outlets
http://www.iea.org/publications/freepublications/publication/TrackingCleanEnergyProgress2017.pdf
www.pln.co.id |7
EV Charging Habits
www.pln.co.id |8
Impact EV to Electricity Demand
www.pln.co.id |9
Load Impact
www.pln.co.id | 10
Load Impact
www.pln.co.id | 11
Standard Issue
www.pln.co.id | 12
www.pln.co.id | 13
SPESIFIKASI PERALATAN PENGISIAN (CHARGING)
BATERAI UNTUK KENDARAAN LISTRIK
Susunan Kelompok Kerja Standardisasi Charging Mobil Listrik
Keputusan General Manager PT PLN (Persero) PUSLITBANG Ketenagalistrikan
(Research Insitute) No. 0029.K/GM/2017
Zainal Arifin : Ketua merangkap Anggota (Divisi EPP – PLN Pusat)
Muhammad Firmansyah : Sekretaris merangkap Anggota (Kantor Distribusi – PLN DJB)
Nugroho Adi : Anggota (Divisi EPP – PLN Pusat)
Tri Wahyudi : Anggota (BMPS – PLN Puslitbang)
Inu Suprianto : Anggota (Divisi Niaga – PLN Pusat)
Dody Suhendra : Anggota (Kantor Distrbusi – PLN Distribusi Banten)
Dimas Kaharudin : Anggota (Divisi EBT – PT PJB)
I Kadek Krisna Adi : Anggota (Kantor Distribusi – PLN Distribusi Bali)
14
Customers: Utility industry:
1. Charging cepat 1. Grid stability
2. Charging mudah 2. Less impact to Peak Load
3. Charging praktis (banyak pilihan) 3. Low investment
4. Safety factors 4. Communication to grid
5. Tarif ekonomis 5. Safety factors
6. Pembayaran praktis 6. Asset security
7. Flexibility
8. International support
15
Acuan Normatif
IEC 61851-1: 2017, Electric vehicle conductive charging system - Part 1: General Requirements;
IEC 60364-7-722: 2015, Low-voltage electrical installations - Part 7-722: Requirements for special installations or locations - Supplies for electric vehicles
IEC 62196-1: 2014, Plugs, socket-outlets, vehicle connectors and vehicle inlets – Conductive charging
IEC 61851-24: 2014, Electric vehicle conductive charging system –Part 24: Digital communication between a.d.c. EV charging station and an electric vehicle for
control of d.c. charging;
IEC 61851-23: 2014, electric vehicle conductive charging system-part 23: DC electric vehicle charging station
IEC 61439-5: 2014, Low-voltage switchgear & control gear assemblies-Part 5: Assemblies for power distribution in public networks;
IEC 62196-3: 2014, plug, socket outlets, vehicle connector and vehicle inlets-conductive charging of electric vehicles-Part 3: dimentional compatibility and
interchangeability, requirements for d.c .and a.c./d.c. and contact tube vehicle couplers;
16
Level 1 Level 2 Level 3
Fase Tunggal Tunggal atau tiga Tiga
Tegangan (V) 230 230-400 250-500
Tipe arus AC AC DC
Arus (A) Maks. 16 Maks. 32 Maks. 100
Tipe 2+DC (IEC 62916-2
Tipe plug-in konektor Tipe 1 (IEC 62916-2) Tipe 3 (IEC 62916-3)
dan IEC 62916-3)
17
Type 1 + CHAdeMo
No. Parameter Type 1 CCS Type 2 CCS GB/T Tesla
L1 max 3.7kW, L2 L1 max 3.7kW, L2 L1 max 1.6kW, L2
L1 max 1.6kW, L2 max max 43.5 kW, L3 L1 max 3.7kW, L2 max 43.5 kW, L3 max 19.2 kW, L3
1 High Power 19.2 kW, L3 max max max 12.8 kW, L3 max max max
90 kW 350 kW 200 kW 120 kW 50 kW
1 High Power 3 5 4 5 4
2 Convenience 4 4 1 5 3
3 Communication 5 5 1 1 1
4 Flexibility 2 5 2 2 3
5 Support 3 3 3 3 3
Total Score 19 22 11 15 14
19
20
Sejak tahun 2011 PLN sudah melakukan riset tentang dukungan terhadap pengembangan
kendaraan listrik di Indonesia
www.pln.co.id | 21
PLN sudah terlibat dalam penyediaan “SPLU” kendaraan Listrik pada Forum APEC
tahun 2013 di Bali
www.pln.co.id | 22
Saat ini “SPLU” PLN sudah siap dikembangkan untuk produksi massal, dan beberapa
sudah tersedia di Lingkungan PT PLN (Persero)
www.pln.co.id | 23
Selain untuk mobil Listrik, PLN juga sudah menyiapkan “SPLU untuk Sepeda Motor Listrik”,
yang saat ini jumlahnya sudah lebih dari 540 unit dan tersebar di Jakarta Raya
www.pln.co.id | 24
Kita dapat menemukan lokasi “SPLU” PLN di Jakarta melalui aplikasi google map
www.pln.co.id | 25
Kunjungan Presiden RI ke Stand PLN tanggal 27-08-2017
Presiden RI mendapatkan penjelasan tentang SPLU dan contoh kendaraan Listrik milik PLN
www.pln.co.id | 26
Media News
www.pln.co.id | 27
Next Agenda
1. Road map EV charger station (SPLU):
Mapping EV charger for public
Estimate of units needed
National grid network
2. Commercial aspect approval:
Payment system
Tariff scheme
Business model proposal
www.pln.co.id | 28
PLN Solution
www.pln.co.id | 29
Terima Kasih