You are on page 1of 11

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/278679758

Design and construction of mined tunnels in


challenging site condition

Conference Paper · January 2008

CITATION READS
1 456

9 authors, including:

Massimo Marotta
Singapore Land Transport Authority
21 PUBLICATIONS   30 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Singapore Downtown Line View project

Thomson East Coast line View project

All content following this page was uploaded by Massimo Marotta on 19 June 2015.

The user has requested enhancement of the downloaded file.


World Tunnel Congress 2008 - Underground Facilities for Better Environment and Safety - India

Design and construction of mined tunnels in challenging site condition

S.Y. Tong, R. Stadelmann, C.R. Mann & S.K. Tang


Amberg & TTI Engineering Ltd.

M. Marotta, M.C. Joshi, & V. Singhal


WH STEC AM JV Contract 855, Singapore

C.N. Ow
Land Transport Authority, Singapore

SYNOPSIS: Mined tunnel construction is considered a special tunnelling technique in Singapore. Most
tunnels in Singapore are constructed either by cut and cover method or tunnel boring machine (TBM). In
the construction of the Circle Line Stage 4 and 5 Contract 855, mined tunnels were proposed for a section
of about 70 m where cut and cover section was not feasible due to the close proximity of the critical
utilities such as high voltage electrical cables, gas pipes and telecommunication cables. The mined tunnel
section consisting of two tunnels also underpasses a four-lane two-way roadway (Ayer Rajah Avenue) and
is named as AYA tunnels after the road name. The tunnels, with an overburden of 10 m and span a
maximum width of 12 m with height of about 10m, pass through residual soil and highly weathered
sandstone and siltstone with distinct discontinuities at certain locations. Due to the challenging ground
conditions and constraints, the design and construction of the mined tunnels have to be carried out in a
manner that will not cause excessive movement to the utilities and the roadway.
This paper addresses the key design principles and construction techniques of the mined tunnel adopting
different construction methodologies. Various engineering challenges such as ground water control, face
stability, as well as engineering solutions implemented in overcoming the difficult ground condition are
also discussed in the paper.

1. INTRODUCTION only minimal deformation during construction


is allowed.
As part of the Circle Line Mass Rapid Transit
(MRT) Project, Contract 855 comprises 4 stations Shallow cover of around 1 to 1.2 tunnel
and 5.2 km of tunnels, of which are mostly diameters (10 m to 13 m cover).
constructed by cut and cover method or bored Application of different construction
tunnelling method. The AYA tunnels are located techniques, such as multi drift method, heading
between the already completed Cut and Cover bench invert method, use of soil and rock
tunnel and also an underground station (One North profiles, and mixed application of the
Station). Refer to Figure 1 for the location plan. mentioned systems.
At present, the construction of the Inner Bound Challenging geological conditions, with
tunnel is completed, including the permanent lining, excavation from rock to residual soil under a
and the construction of the Outer Bound Top layer of artificial fill and soft clay and below
heading has also been completed. the water table.
The construction of the AYA twin tunnels has Close proximity of the two tunnels, with a soil
been challenged by the following factors: pillar width of 1 m to 4 m.
Location, as the tunnel is situated in urban area, The construction of the Inner Bound tunnel
under passing a four-lane two-way roadway started in December 2006, and it was almost
and a number of utility service lines, therefore immediately interrupted by shotcreting quality due
Ayer Rajah
Avenue
SCL Mined
Tunnels

Inner Tunnel
One North
Station Cut and Cover Section
Outer Tunnel

Figure 1. Site location plan

to the unavailability of fine sand. The situation layer of thickness between 0.5 m to 2.5 m beneath
regularized only in the beginning of March 2007 the fill. The estuarine layer consists of very soft to
where alternative sources of quality sand was made soft dark grey to black peaty clay. The longitudinal
available in Singapore. profile is shown in Figure 2.
2. GEOLOGICAL CONDITION The Jurong Formation is composed of a series
of sedimentary rocks such as sandstone, mudstone,
The site is situated in Jurong Formation (JF) with and siltstone. This formation has been severely
overlying Fill. The thickness of the fill varies from folded and faulted in the past as a result of tectonic
0.7m to 7m. The backfill generally consists of movements. The formation is believed to be formed
heterogeneous soils frequently mixed with gravels, in Upper Triassic to Early Jurassic period (about
rock fragments, bricks, wood pieces and organic 100 to 200 million years ago). The tunnel is located
materials. There is also a localized estuarine clay

Re duce d Le ve l
(m )

Fill 115m
JF Re s idual Soil Pe aty Clay
N<20 110m
105m
JF Re s idual Soil JF Re s idual Soil
20?N<50 100m
N?50
95m
JF Rock 90m
85m
80m
75m
CH77300 CH77320 CH77340 CH77360 CH77380 CH77400
Chainage (m )
Figure 2. Geological longitudinal profile
in one of the facies of Jurong Formation, known as modules were constructed in similar way, also
Tengah Facies which comprises muddy marine adopting multi-drift methodology with the
sandstone with occasional grit beds and excavation of the tunnel face carried out in four
conglomerate. The member is usually deeply successive excavations in order to provide better
weathered but appears not to have been strongly control over ground deformation. Partition
lithified at any stage. Also, the degree of excavation will also allow a smaller face to be
weathering generally decreases with depth. exposed, thus reducing pre-deformation.
The top portion is the residual soil of Jurong The remaining modules were smaller but
Formation, which is generally stiff to hard or typical in size with maximum width of about 11m
medium dense to very dense in consistency with and height of 9 m. Conventional top heading, bench
SPT-N values ranging from 12 to over 100. The and invert construction methodology was thus
thickness of the residual soil is about 10 m to 20 m. adopted for these modules. The geometry of the
Underlying the residual soil is the sedimentary design modules is shown in Figures 5 and 6.
rocks, which comprises mainly of siltstone and The tunnels were constructed module by
sandstone of various weathering grades. Localized module. Due to the close proximity of the tunnels
discontinuities of close spacing and slickensides to each other, it was decided that the inner tunnel
were observed along the tunnel alignment, as shown being larger in size, was to commence excavation
in Figure 3. first. It is envisage that the influence of the outer
smaller tunnel excavation on the completed bigger

Quartz with Highly weathered


Slickenside observed sandstone

Figure 3. Face observations during heading excavation at CH77368 (Left) & CH77376 (Right)

3. DESIGN MODULES AND CONSTRUC- inner tunnel would be smaller than if the outer
TION METHODOLOGY tunnel was to commence excavation first. It is also
important that the excavation of the bigger tunnel
The entire 70 m of both inner and outer bound was carried out in relatively undisturbed ground.
tunnels were divided into four modules each. The Prior to the commencement of each module,
length of each module varies from 14 m to 21 m, as pipe roof of length varying from 21 m to 27 m were
presented in Figure 4. installed depending on the length of each module,
In order to accommodate an additional keeping a design overlapping of at least 7m to the
branching railway track, two of the modules in the next pipe roof array. The pipe roof consisting of
inner bound tunnel (Module 1 and 2) were larger in 114 mm diameter steel pipes of thickness 6.3mm,
dimension of which the largest module spans about and were installed at 300 mm centre to centre
12 m in width with a height of about 10 m. Based spacing at a vertical inclination of 2 to 4 degrees.
on experience from Uetliberg Tunnels in Zurich, The pipes were packer grouted after installation.
Switzerland in similar ground condition but larger For the multi-drift construction approach in
in size (147 m2 excavation face, spanning a width of Module 1, 1A excavation was carried out meter by
14.7 m and height of 12.7 m) which adopted multi- meter, supported with spray concrete lining (SCL)
drift approach, it was decided that these two larger all the way to the end of the module. In order to
I4 I3 I2 I1 INNER
BOUND

ONH
station OUTER
O8 O7 O6 O5 BOUND

Figure 4. Design modules for inner and outer tunnel

Heading:
1A: 27-32 m ² 3a: 2A 37-57 m ²
9.3-10.0 m

8.4 - 9.0 m
1B: 25-28 m ² 3b: 2B
Bench/Invert:
19-22 m ²

10.5-11.8 m 8.5-10.9 m
TOTAL: 76-93 m ² TOTAL: 56-79 m ²

Figures 5 and 6. Geometry of design modules

have a good bearing for the 1A profile, elephant distance depends on the ground condition and the
footings were provided at the invert of 1A, with deformation of the tunnel. In the initial design, the
additional H-beams to provide lateral restraint to the distance is about 8m behind the heading. Module 3
lateral earth pressure. After which, 1B excavation was constructed adopting this 8m distance between
was carried out beneath the H-beams all the way to the heading and the invert. However, the
the end of the module. 2A/2B excavation was construction sequence for the Outer Tunnel was
carried out in staggered fashion with 2B lagging at adapted with the top heading and temporary invert
2m behind 2A. excavation proceeding all the way 70m before
For the conventional top heading, bench and followed on with bench and invert excavation.
invert construction approach, the excavation was Micropiles were installed at certain locations to
carried out first with top heading and temporary improve stability and reduce settlement.
invert and elephant footings. The temporary invert In both types of construction approach, the
was required due to the low strength of the residual design support consists of 300mm thick shotcrete of
soil, of which the SPT N-value ranges from 20 to 50 Grade 30 and 2 layers of T8-100 meshes. Lattice
at certain locations which results in lower bearing girders were adopted as non-structural member to
capacity. It was subsequently followed on with provide the profiling for the final shape of the
bench and invert excavation, of which the lagging tunnel geometry. Dumplings (or soil berms) and
systematic face nails were provided to improve the becomes paramount especially where there are
face stability during each advance especially at several major utilities above the tunnels.
locations where distinct discontinuities and With this emphasis, extensive instrumentation
slickenside were observed. and monitoring were proposed both at the ground
surface and in the tunnels. The layout is presented
in Figure 7.
4. INSTRUMENTATION AND MONITORING
For the surface monitoring, 5 lateral
In the construction of the mined tunnels, our monitoring arrays across the tunnels were installed.
approach emphasize strongly on observational The instruments comprised of ground and building
methodology. CIRIA Report 185 defines the settlement markers, utility settlement markers, rod
observational method in ground engineering as a extensometers, vibrating wire piezometers, water
continuous, managed, integrated, process of design, standpipes and inclinometers.
construction control, monitoring and review that For the in-tunnel monitoring, two types of
enables previously defined modifications to be monitoring array, Array P and Q (in Figures 8 and
incorporated during or after construction as 9), which consist of optical prisms, were installed
appropriate. Also, all these aspects have to be generally at 7m spacing along the tunnels alignment.
demonstrably robust. Thus, monitoring of how the Readings for the instruments were taken daily
tunnel and ground reacts during the excavation during excavation. The frequency of the monitoring

Array 5 ArrayW4 Array 3 Array 2 Array 1

W
P
I
I I
W
E

E
E

E I E I W

E E

W
I

P W
W

Figure 7. Layout of surface monitoring instrumentations

2A Heading
1A

Tem p Invert
1B
2B
Bench/Invert

Figures 8 and 9. Layout of in tunnel monitoring for multi-drift (Array P, Left) and heading profile (Array Q, Right)
was increased whenever there was significant 5.1.2 Multi-drift (I.B. tunnel, Module 1, TM 10 to
change in the rate of settlement. TM 21)
The use of multi-drift has been designed and
5. CONSTRUCTION OF THE AYA TUNNELS implemented in order to reduce the excavation area
at each stage, thus reducing the deformation.
5.1 Different excavation methodologies
The excavation sequence was the subsequent
The following sections will describe the adopted completion of every drift (1A, 1B, 2A & 2B) for
methods, with reference to the location where the every tunnel module in order to install the pipe roof
methods have been applied (I.B. Inner bound tunnel, canopy for the subsequent module.
O.B. Outer bound tunnel, Module, Tunnel Meter
TM with 0 as starting chainage).

5.1.1 Multi-drift, horse-shoe profile (I.B. tunnel,


Module 1, TM 0 to TM 10) 1: 1A 3a: 2A

During the excavation of the inner tunnel module 1


drift 1B, rock was found at spring line level dipping 3b: 2B
2: 1B
down towards excavation direction.
The presence of rock and the limitation of
using heavier equipment caused a cycle time of 36h
for the first round of 1m in 1B.
To improve the efficiency and also ensure a safer Figure 11. Multi drift
working condition by reducing a vertical slope during
The application of this method (Fig.11) has
excavation and hacking in a confined space condition,
resulted in challenges during construction in terms
horse-shoe tunnel profile (Fig.10) socketing in rock was
of:
then used during construction of the first 10m of the
inner tunnel module 1. This particular area has also Reduced excavation area, with consequent
been characterized by the installation of an "A" frame limitations in the use of certain equipment
on the first 5m of tunnel in order to allow clearance for
equipment access, yet still provide a good control of the Difficult joint construction between side drift
deformations, as the original horizontal H beam (at and enlargement sections (1A/2A and 1B/2B)
tunnel spring line level), was just 1.8m above the tunnel Accessibility problems, especially during the
access level (cut and cover permanent slab level). 1B stage, mining under the horizontal H beams
The maximum tunnel settlement recorded installed during 1A excavation.
using this method is 18mm, of which 83% (15mm)
has occurred during 1A & 1B excavation stages. In order to minimize possible disruptions due
to the construction of the difficult joints, a 1 to 1
scale mock up of the joint was constructed for
training purpose while a second one was used to
verify the shotcreting quality which would have
1: 1A been affected by the congestion of reinforcements
A frame 3a: 2A (lattice girder, mesh, lapping bars). However,
during construction, back grouting has been done at
crown joint location in order to avoid any possible
3b: 2B settlement due to eventual gaps behind the shotcrete.
2: 1B The maximum tunnel settlement recorded
using this method is about 34mm, of which 53%
(18mm) has occurred during 1A & 1B excavation
stages.(Fig.12)
Figure 10. Multi-drift horseshoe profile
Figure 12. Excavation of drifts 2A/2B

5.1.3 Multi-drift plus bench & invert & micro- In order to assure a proper load transfer
piles (I.B. tunnel, Module 2, TM 21 to TM mechanism, and to reduce face instability problems,
38) micropiles were installed ahead of the bench face
along the 1A temporary drift supports.
The accessibility during 1B excavation for this The maximum tunnel settlement recorded
approach was a main problem especially the area of using this method is about 26mm, of which 65%
1B is smaller as compared to that in Module 1. (17mm) has occurred during 1A excavation stage,
Using multi-drift (Fig.13) method, the full profile showing the advantage of having a rapid ring
ring closure is achieved only upon completion of closure.
the full section. Therefore the deformations during
1A and 1B stage, are time dependent. A longer
period of construction to close the full profile is 5.1.4 Top heading, bench & invert (I.B. tunnel,
likely to cause additional settlement. Module 3, 4 TM 38 to TM 68 & O.B. tunnel
Module 8 TM 56 to TM 68)
This method (Fig.14) was adopted for the rest of the
1: 1A mining, and entirely for the outer bound tunnel,
2: 2A
although at the present stage of construction we can
1a: Micropiles predict the use of horse-shoe tunnel profile socketing
in rock at certain locations of the outer tunnel.
The excavation using this more traditional
3: Bench
system has been less challenging then using the
multi-drift method, although controlling the
4: Invert deformation (both pre-deformations and shotcrete
deformations) has required particular attention.
Figure 13. Side drift + bench/invert The face was mainly supported by use of
systematic face nailing and face wedge. Temporary
The problem was solved by modifying the invert was kept as close as possible to the face,
original method to a different one, consisting in the however during the excavation of the outer bound,
excavation of drift 1A for the entire module length micropiles have been extensively used in order to
(max 17m), followed by the excavation of the drift minimize the settlement.
2A and a rapid ring closure with bench and invert The maximum tunnel settlement recorded
excavation. using this method is about 12mm, of which 83%
(10mm) has occurred during top heading with 5.2 Face stability
temporary invert stage.
One of the challenges during construction is
carrying out the excavation in relatively difficult
geological conditions, especially in terms of
localized instability problems due to the presence of
narrow spaced discontinuities.
1: Heading The measures adopted in order to control the
stability of the face were:
2: Temp Invert Face nailing

Staged excavation & face wedge


3: Bench/Invert

Figure 14. Heading, bench, invert

5.1.5 Top Heading, bench & invert, with


Micropiles (O.B. Bound tunnel Modules 5, 6,
7 TM 0 to TM 50)
This method (Fig.15) was adopted in the outer
bound tunnel, in order to minimize the settlements
during top heading excavation and prior to the
bench/invert excavation. Figure 16. Face nailing
Face nailing, together with staged excavation
and face wedge was also adopted. Face nailing was included in the design for the
Micropiles were installed as contingency drifts 2A/2B, for the top heading excavation and at
measure from TM 0 to TM 38 in order to alleviate the end of each tunnel section where a full face is
ongoing settlements, of which a maximum value of formed.
21mm was recorded in the tunnel. From TM 38 to During construction face nailing has been
TM 50, micropiles were installed systematically extensively used during all the stages of excavation
during heading and the maximum recorded (1A, 1B, bench invert). The execution of face
settlement is about 14mm. nailing (Fig.16) solved the localized instability
problems and also acted as a confinement at the
working face to reduce pre-excavation deformation.
Despite a systematic use of face nailing,
problem of local instability still occurred, mainly
1: Heading due to the narrow spacing of discontinuities and
separation planes, as shown in Figure 17, which
indicates the surface from where a block was
2: Temp Invert detached from the face, as the separation planes
were located in-between the installed face nails.
This problem was addressed by increasing the
3: Bench/Invert number of face nails on the face.
During the excavation of the Inner Tunnel
using multi-drift method, additional forepoling on
Figure 15. Heading, bench, invert with micropiles the temporary side drift have also been installed to
address potential extension of face failure over the
temporary drift.
using the pipe roof pipes as casing (pull drilling),
Detached block with a system that allows retrieval of the drill string
upon completion but sacrificing the pilot bit.
A survey was executed after each pipe
installation. The absolute deviation of the pipe
deflection from the intended design inclination or
drilling accuracy was measured to be a maximum
value of 0.5%. The deflection of pipes during
drilling, which usually occurred due to the self
weight and change in ground conditions, was also
Face Nails measured and found as low as 0.2% for the longest
27m length canopy.
Based on this execution/monitoring process,
continuous adjustments were made to the drilling
methodology in order to achieve the desired results.
Although in the design, arching effect of pipe
Figure 17. Localized face failure roofing was not considered, double packer grouting
has been performed in almost every canopy in order
Although the original design addressed the to improve the portion of soil between adjacent
face stability in term of wedge failure, the spacing pipes, generally spaced at 300mm center to center.
and the orientation of discontinuities created
Double packer grouting was completed in steps of
challenges even after the extensive implementation
1m.
of face nailing.
A total of 6,066 m length of pipe roofing has
For this reason, during excavation, each face
was subdivided into smaller portions, as indicated in been completed with a total grout intake of 140 m3.
Figure 18, excavate and immediately seal with Average grout intake was estimated to be 11.5 litre
shotcrete on all exposed ground prior to advance of per metre length for the packer grout and of 11.7
the next meter. litre per metre length for the fill grout. Attention
was also given to the sequence of drilling and
grouting, with grouting being executed after the
1a: Heading drilling of a maximum of 2 to 4 pipes.

1b 1c 5.4 Pillar stability


Wedge
The stability of the pillar was a concern when
2: Temp Invert
excavating the outer tunnel. The owner Land
Transport Authority (LTA) routinely appointed a
3: Bench/Invert
board of international renowned consultants to
review the construction risk. The Board of Advisors
advised that the permanent lining in the inner tunnel
Figure 18. Staged excavation to be cast first to increase the tunnel stiffness so as
improve the pillar stability, prior to commencement
of the outer tunnel excavation (Fig.19).
5.3 Pipe roofing canopy execution
The measures implemented comprises the
It was important during pipe roofing execution to casting of the side walls and base slab in the inner
achieve the best possible drilling accuracy in order tunnel, the stitching of the 2 tunnels with tie rods,
to reduce over-excavation or pipe intrusions during continuous face nailing ahead of the face, extended
construction, which would result in delay of support pipe roofing at Outer Tunnel Module 5 and
installations and causing higher deformations. In controlled excavation to minimize over-excavation
order to do so, drilling has been executed directly at the pillar side.
Extended
pipe roofing
1

2 3 Perm anent
4
lining
5: Tem p Invert

pillar stitching

Figure 19. Pillar stability control measure at Inner tunnel module 1

6. CONCLUSIONS of major infrastructure projects involving deep


The implementation of different construction excavation, tunneling, deep foundation and slope
methodologies in the 70m long twin tunnels stabilization, both in Singapore and overseas. He is also
undercrossing several major utilities and road (AYA) a qualified Professional Engineer registered with the
shows how design and construction are strongly linked Singapore Professional Engineer Board.”
in terms of performance monitoring, observation, and
modification to the actual ground conditions. This is a “Rolf Stadelmann obtained his M. Sc in
good example of cooperation among client, contractor Civil Engineering from the ETH Zurich,
and designer to successfully construct the tunnels in Switzerland in 1992. He specializes in
challenging ground conditions. general stability analyses, temporary &
permanent excavation support systems,
REFERENCES as well as in structural design of all
1. CIRIA Report 185 (1999), The Observational types of tunnel lining. His core
Method in Ground Engineering : Principles and competence is also in the quality
Applications. management for geotechnical analyses as well as in the
development of Contractor’s alternatives. He has in-depth
2. ICE Design and Practice Guide (1996), Sprayed
experiences in underground space design for all kinds of
Concrete Linings (NATM) for tunnels in soft ground,
rock conditions. Since 2003 he is Head of Geotechnical
The Institution of Civil Engineers, Thomas Telford,
Department of Amberg Engineering Ltd in Switzerland.”
London.
3. Schnelli .O, Marti .D, Maurhofer .S, Bolliger .J and "Massimo Marotta obtained a Survey
Voerkel .M (2003), Uetliberg Motorway Tunnel Engineering diploma in 1992. He
(Switzerland). Proceedings of the ITA World served the National Service as officer
Tunnelling 2003, (Re)claiming the Underground in the corps of engineers. In 1996 he
Space, pp.419-426. joined the Italian company I.N.C.-
BIOGRAPHICAL DETAILS OF THE AUTHORS General-Contractor in Israel for a
hydraulic tunnel project first and, in
“Tong Swei Yeh Marcus graduated
1997 in Taiwan for a rail tunnel in
in Civil Engineering from Nanyang
D&B, with position as Branch Manager. In 1998 he joined
Technological University in
ITAI as Technical manager for freeway, railway and
Singapore in 2000 with a first class
hydraulic tunnels using D&B and in difficult ground
honours degree and obtained a
conditions, as the Hukou tunnel, part of the Taiwan High
Master of Science in Civil
Speed Railway. In 2006 he moved to Singapore with
Engineering from National
WSA-JV as NATM Manager for Circle Line contract
University of Singapore in 2003. He
C855"
has been extensively involved in the consultancy design

View publication stats

You might also like