You are on page 1of 7

All India Seminar on “Slope Stability Issues in Opencast Mining and Civil Engineering(SSIOMCE-15)

National Institute of Technology-Rourkela : July 25-26, 2015

Stability of Spilway Cutslope at Dhauliganga H.E Project


Dr. Gopal Dhawan* B.D.Patni**

ABSTRACT
The understanding of hill slope stability in the construction of hydro project depends upon the realistic approach of
Geological investigation and cautious construction procedure. The careful appraisal and analysis of geotechnical data
helps to chalk out the strategies for coping with various slope failures. Excavation of 150 m high spillway cut slope of
Dhauliganga project experienced various geotechnical problems due to complex geological setup and adverse
topographical conditions. With successful application of state of the art technology, the problems were conquered with
success. The high angle spillway cut slope necessitated with progressive change in the design of spillway by reducing
its width and utilization of diversion tunnel as spillway tunnel. For the first time in Himalayan terrain, a reinforced
anchored drift was constructed to stabilize the vulnerable spillway cutslope. The present paper deals with the several
geological problems faced during the excavation of 150m high spillway cut slope of 280 MW Dhauliganga Project, St-I
(Uttarakhand) and its remedial measures.
Keywords: Cutslope, Hydroelectric project, geotechnical investigations
INTRODUCTION i. A massive rock slope above the dam axis, spillway,
intake structure and chute channel consisting of
The 280MW Dhauliganga HE Project Stage-1, a run of the jointed biotite gneiss rock mass.
river scheme on river Dhauliganga is located in Dharchula, ii. The overburden slope (less steep) above the spillway
Distt.- Pithoragarh, Uttarakhand (Fig-1). Despite many approach channel was composed of large
odds, the project was successfully completed with disintegrated rocky blocks mixed with soil resulting
scheduled time of 5 years. The project has been from sliding activities in the geological past.
characterized by difficult access condition, unfavorable
topography, very active monsoon and many technological
hurdles. Construction of spillway cutslope and handling
70m deep overburden in the river bed were two major
challenges. In the DPR, 111m high rockfill dam above
foundation with conventional clay core was proposed.
Keeping in view the difficulty in removing deep overburden
in river bed and non-availability of clay borrow areas in
proximity, project design was reviewed in association with
Electro watt Engineering, Switzerland. Subsequently, type
of dam was changed to Concrete Faced Rockfill Dam
(CFRD) of 51m height.
Fig-1. Location and General Layout of Dhauliganga H.E.
Provision of low level chute spillway on the right bank Project
necessitated the excavation of large rock slopes. The GEOLOGICAL INVESTIGATION
natural slope of the existing right bank was grouped into Geological Description
two regions from downstream to upstream.
The project area is located in Chiplakot Formation belonging
*CMD, MECL to Precambrian age. All the structural components of the
**Chief (Geology), NHPC
1
SSIOMCE 2015
project are housed in single formation comprising mainly
of biotite gneiss with subordinate schist & patches of augen
gneiss. The project is bounded by North Chiplakot thrust
in upstream and South Chiplakot thrust in downstream
side which has given rise to intense jointing in the area.
The Chiplakot rock accordingly exhibits prominent jointing
rendering the rock blocky at most of the places. The joint
systems are continuous wherein one joint can be traced
for several hundred meters. An extensive survey had been
carried out during investigation stage (Dhauliganga, 2011).

During investigation stage, the right bank of the dam site


was explored by means of detailed geological mapping (in
1:1000 & 1:500 scale), two nos. (L-10A & L-11) exploratory Fig 2. Geological Elevation Plan of Spillway Cutslope
drifts at El. 1311.70M & 1327.90M respectively An analysis Below EL 1351M, the low dipping S-2 joint plane were
of 3-D geological log indicate wide opening along valley daylighted in the slope face having high dip amount as
dipping joints with an average dip of 600. Significant compared to angle of friction of the rock surface which
shearing was also noticed along S-4 (hill side dipping joint). caused no. of planar failures before installation of support.
In addition, one drill hole (BH-19), 41.8m deep was drilled
at right abut at El. 1305.2M. The bedrock was encountered The area above spillway approach channel was occupied
at 16m depth. The initial 35m rock mass (measured by debris slump accumulated due to landslide. The
horizontally from ground surface) was affected by steep, overburden consists of mainly large slided blocks and rock
valley dipping stress relief joints having opening up to fragments of biotite gneiss embedded in a silty clay matrix.
300mm. A preliminary kinematic slope stability analysis At few places, the overburden mass consists of silty clay
based on drift data indicated potential planer failure along material.
stress relief joints.

The area above dam axis and spillway chute channel was
occupied by moderately jointed biotite-gneiss rock mass
with occasional bands of talc mica schist. The rock slopes
on the right bank were clearly influenced by four families
of joints, viz S-1(040-75/40-55), S-2(315-355/50-75), S-
3(120-170/40-70) and S-4(180-220/40-70) (Fig.-2). Among
these, S-2 joint was most vulnerable due to its parallelism
with the cut slope direction i.e. towards valley side. Many
wedge failures have also been experienced at different
levels. The deep seated rock mass in the area exhibited
tightening of joints with lesser frequency. Two major Shear
Zones (20cm-150cm) having attitude 180-210/70-75 & 220/
65 respectively have been recorded in the right bank. During
progressive excavation of cut slope both wedge failure and
planar failure occurred with the combination of foliation &
valley dipping joints (Fig-3). Kinematic analysis of slope
revealed the plunge of the line of intersection of S1 & S2
joint plane was more than the angle of friction of the surface.
The plunge of the line of intersection of the S-1 & S-2
plane was less than that of dip of slope face. The direction
of line of intersection of two planes was also parallel to cut
surface (Fig.4 &5).

Fig 3. Wedge Failure above Road Level in Spillway


Cutslope
2
SSIOMCE 2015
to be governing failure mechanism above El.1351M. The
analysis confirmed that the wedges formed require
untensioned passive rock anchors of 15, 12, 8 length &
36mm diameter alongwith Fe415 fully grouted steel bars
at approximately 2m c/c forstabilization

Overburden Slope

The overburden (debris slump) was comprising of large


boulders & rock fragments of biotite gneiss embedded in
clayey matrix. The overall angle of stability of the overburden
in the approach channel area was assessed about 35
degree. It was reasonable to assume that steeper
excavation could mobilise mass movement during rains,
although sudden failure of entire slope was ruled out. It
was estimated that permanent stabilization of entire
excavation in overburden area would be very extensive &
costly. Therefore excavated slope in the overburden was
Fig 4. Geological Section of Spillway Cutslope at Ch.0 specified as 1H:1.25V with 3m wide benches at 15m
(Dam Axis) vertical intervals. The average excavated inclination of the
slope was 45° (Fig.-8).

Fig-6. Tender Stage Layout of Dam Complex

Fig 5. Geological Section of Spillway Cutslope at Ch.63


CUTSLOPE GEOMETRY AND SUPPORT
Rock slope

As per the tender drawing, a 10 m wide road was proposed


at El. 1351M. Two number berms each 5m wide were
specified at El. 1324M and at El. 1376M respectively (Fig.-
6). The slope between the berms was specified as 1H: 8V
and 1H: 10V above El. 1351M and below El.1351M
respectively. The overall slope was 1H: 3V and extended
upto El.1400M and at some locations upto EL.1420 M
(Fig.-7). Thus the total height of the slope in the area
between dam axis and power intake was 120m and in area
downstream, less than 100m. Based on the analysis of
discontinuity data, planar & wedge failure was considered Fig 7. Tender Stage Cut Slope Design
3
SSIOMCE 2015
INCIDENCE OF SLOPE FAILURE

The inherent geological and topographical environment of


the area was the causative factors for instability of the
slope. The main problem experienced was due to adverse
orientation of rock discontinuities and mobilization of
unconsolidated overburden (debris slump) mass during
rainy season. Initially, the slope excavation started from
El. 1460M in overburden in the approach channel. The
excavated slope was provided at 1H: 1.25V with 3m wide
benches at 15m intervals (Fig.-9). Excavation was then
extended towards the downstream between chainage 30
and chainage 90. At the toe below El 1400M the rock was
Fig 9. The Development of benches at EL 1459.0 m and
exposed in spillway channel area.
disposition of the natural slopes in upstream side

Fig 10. Slope Failure in Spillway occurred in March and


April, 2001
Fig -8. Excavation of Slope in Overburden Additional Safeguards
Initially in March, 2001, a small rock slide occurred at El ±
1420M. Thereafter, on April 24, 2001 in the bedrock area, The cutting of high angle hill slope required an understanding
a massive rock slide took place which extended upto of nature of major change in the behaviour of shear strength
El.1480M (Fig.-10). The rock mass measuring about 45 x parameters of discontinuities that took place during
50 x 25m slided down by about 25m. It was resting partly progressive excavation. By considering the high angle of
on the 1411M bench. The quantity of the failed rock mass slope cut, opening along discontinuities and existence of
was about 25000 m3. The phenomenon was so deep that unstable large wedges the design was reviewed as follows:
the existing provision of support could not save the failure. 1. The global slope was modified from 1H: 3V to 1H: 2V
The mechanism of the slide involved two wedges formed to reduce the quantum of rock support needed (Fig.-
by the joint combination of 335/60 and 015/60 & 335/60 13a &b). In addition to that, number of bays was also
and 100/70 (Fig.-11). In the month of June 2001, due to reduced from 3 to 2 bays and the existing diversion
incessant rains, the excavated slope in overburden mass tunnel was converted into spillway tunnel by providing
got saturated and resulted in failure of 15m high benches inclined connecting tunnel.
(Fig.-12). Before commencing further work, it was 2. The numbers of intermediate branches were kept
considered necessary to reanalyze the existence & minimum to avoid the need for additional support for
behavior of the valley dipping joints and probable unstable berm stability.
wedges in the higher elevations (Gupta, R.K. and Kumar 3. As primary support provision was kept to install rock
Rajeeva., 2006). The detailed geological mapping was anchors and to depend minimum on installation of
carried out and updated sections were prepared for further tendons as it was time consuming.
analysis.
4
SSIOMCE 2015
4. To treat the open joints and to enhance the reliability EXCAVATION & SUPPORT OF SPILLWAY CUTSLOPE
of passive rock anchors, extensive grouting was AS PER MODIFIED DESIGN
carried out.
5. To ensure the stability of the slope between El.1480 To accommodate low level chute spillway structure,
M and El.1411M in approach round area anchor drift excavation of right bank area commenced in Nov’2000.
were suggested at El.1450 M and El.1411M. The right bank cut slope was divided into 3 zones:
— Spillway cut slope from Ch. 173 to Ch. 48.3m.
— Approach round cut slope from Ch.0 to Ch. 68m at
El. 1411M.
— Approach channel cut slope from Ch. (AR 60 to 200)m.

The surface area of excavation slope was 30,000 m2 in


rock and 30,000 m2 in overburden. Maximum height of slope
in rock and overburden was 120m and 150m respectively.
The spillway cut slope between EL 1410M to EL 1295M
was excavated by providing berms at EL 1410M (5m wide),
EL 1375M (5m wide), EL 1351M (8m wide) and EL 1310M
(5m wide) respectively. Excavation of 5m has been carried
out at one cycle and supported properly before lowering
down to next level. Spillway cut slope was supported by
untensioned rock anchors of 36mm dia and fully grouted
steel bars at approx. 2m c/c. The length of the rock anchors
(level wise) ranges from 15m, 12m, 8m & 6m respectively.

Excavation slope between the El. 1351 M and El. 1310 M


was kept as 1H:3V. A berm of width 8-10 meters was
provided at El.1310 M. The slope between El. 1310 M up
to the foundation level was provided as vertical. For the
Fig -11. Kinematic Analysis of Joints in Spillway Cutslope
bucket and the deflector wall in the downstream end of
spillway, rock anchors 15 m long and three rows of tendon
were also specified. All these anchors were to be extended
into concrete cladding, while 50% of tendons were to be
extended into the concrete to give a positive force to
concrete cladding. For the power intake area vertical
excavation was required to be carried out between El.1335
M and El.1310 M. The slope between El.1335 M and
El.1324 M was provided with two rows of tendons and
spacing of 15m/12m long rock anchors were also reduced
to 1.4X1.4m. The excavation for tunnel spillway intake was
carried out very carefully due to presence of opening along
S-2 joints (5mm-15mm) and reduced side cover. Extensive
Fig-12. Failure of Overburden in Spillway consolidation grouting was carried out once some
movement was noticed during excavation of tunnel spillway
intake. During excavation large cavities were also noticed
in the approach channel area at EL 1410M. Approx. 400
m3 concrete was poured to till the cavities.

EXECUTION OF DRIFT ANCHORS

Two numbers of longitudinal exploratory drifts were made


for the purpose of exploration which were later reinforced
and concreted to serve as high capacity passive drift
anchors for providing additional support for the rock mass
at EL.1450M and at EL. 1411M (Fig.-14). The 3-D geological
Fig 13 (a). Originally Proposed Spillway Cutslope Section log of the drifts were influenced by 4 sets of discontinuities
Fig-13 (b).Modified Spillway Cutslope Section having large opening up to 500mm along S-1 & S-2, 0570-
5
SSIOMCE 2015
075 0/50 0-700 , 3000-340 0/51 0-75 0 joint at places. The Concrete and reinforcement work of the drift at El.1450M
intersection of these two joint plan were forming large was completed in about three month’s time (Fig.15a&b).
unstable wedges. Three cross drifts along with a longitudinal Another set of drifts had also been constructed at EL 1411M
drift (45 m long) at El.1450M was constructed. One cross in a similar fashion (Gautam. P.C. and Tripathi. L.K., 2006).
drift (Limb A) was 40m long and the other two (Limb B & Reasons for heavy grout intake are as follows:
Limb C) were each of 30 m length. The force requirement i. Geologically the spillway slope is segmented by open
against possible wedge failure and the resisting force discontinuities of varying depth.
provided by drifts were compared. ii. Presence of wide open joints/cavities is big consumer
of grout mix.
CONSOLIDATION GROUTING ON THE RIGHT BANK iii. As indicated by geological section high persistence
OF SPILLWAY of open joints are causative and contributing factor for
free transmissivity of grout mix.
i. After evaluation of the geological discontinuities of the
spillway slope and analyzing the design aspect of the RESTORATION OF OVERBURDEN SLOPE (DEBRIS
various geological problems, extensive consolidation SLIDE)
grouting with cement and sand was undertaken from
the open joints and drill holes, which covers the spillway The slided overburden mass (boulder) above spillway
slope over a length of ± 100 mts. and extended down channel was restored by providing catch water drain at EL
to the level of El. 1318M. 1425M to arrest the storm water and channelized it towards
ii. The basic concept of doing consolidation grouting in the rock slope. The slope between EL 1380 & EL 1351M
the spillway slope was to seal the open joints and was excavated at 1H/1V and supported with reinforced
strengthen the rock mass to the large extent before concrete gabion grid. Extensive plantation was also carried
further excavation. out in the debris slide area (Fig. 16).
iii. The grouting was carried out by drilling 89mm dia hole,
15m deep in to the rock at 6m spacing c/c in staggered STABILIZATION OF SPILLWAY SLOPE
pattern. The holes were drilled normal to the surface.
iv. In the beginning, the grouting was carried out in single By adopting innovative design modifications and state of
stage at higher elevation. Lateron it was conducted in the art construction management techniques, the spillway
three stages by using mechanical packers. slope was stabilized and the project was commissioned
v. About 6000 tonnes of cement and 200 tones of sand in Mach, 2005 without delay (Fig.-17).
were consumed in the spillway slope grouting.
vi. Maximum grout intake of 114.05 tones in terms of
cement was consumed in hole no. 27 at El. 1403M
vii. An analysis of drilling data indicated presence of wide-
open joints beyond 8 to 10 mts from the surface,
encountered during the drilling of holes above El.
1435m. Sudden loss of pressure and fast penetration
of drill rod also exhibits the presence of cavities
between Ch.+30 to +65 above El. 1403M.

Fig 15 (a). Open joint shown in the side wall at RD 17M in


the exploratory drift at EL 1450M, Spillway Cutslope area

Fig 15 (b). A frontal view of Exploratory Drift at EL 1450M


on the Spillway Cutslope showing reinforcement before
Fig-14. Layout of Anchor Drift
concreting
6
SSIOMCE 2015
for cutting of such a large slope. It needs a thorough
recording of geotechnical data, careful construction
management and innovative ideas to deal with slope
hazards. Moreover, in the present scenario, hydro power
projects with difficult, inaccessible terrain & complex
geological conditions only are left for construction. In this
context, excavation of 150m high spillway cut slope of
Dhauliganga project has given the technical confidence to
deal with more & more complex geological situations. In
spite of concurrent failures in the spillway cut slope the
problems were overcome & the slope was excavated within
scheduled time and is intact & stable thereafter.

ACKNOWLEDGEMENT

The authors express their sincere gratitude to NHPC


Fig 16. Concrete Cladding & Overburden support above management for granting permission to prepare the present
approach channel area paper. Support and help rendered by Shri Arindom
Chakraborty, AM (Geology), NHPC, Shri V.K.Aggarwal,
Executive Draftsman and Shri Pardeep Kumar Jain, Sr.
Sup (IT), NHPC is highly appreciated and acknowledged.

REFERENCES

1. Dhauliganga, 2011. H.E.Project (Geology Chapter),


Patni B.D.et.al. , NHPC Limited (Unpublished Project
Completion Report)
2. Gautam. P.C. and Tripathi. L.K., 2006; Construction
Aspects of Dhauliganga Cutoff wall; Indian Journal of
Power and River Valley Development, Special Issue
on Dhauliganga Hydroelectric Project, Stage-I,
Fig 17. Overall view of Dhauliganga CFRD showing stabi- January-February, 2006.
lized Spillway slope 3. Gupta, R.K. and Kumar Rajeeva., 2006; Dhauliganga
dam complex layout optimization – influence of Geo-
CONCLUSION Technical conditions.; Indian Journal of Power and
River Valley Development, Special Issue on
In the geologically complex & tectonically active Himalayan Dhauliganga Hydroelectric Project, Stage-I, January-
region, it is difficult to get favourable geological condition February, 2006.

7
SSIOMCE 2015

You might also like