Professional Documents
Culture Documents
ABSTRACT
The understanding of hill slope stability in the construction of hydro project depends upon the realistic approach of
Geological investigation and cautious construction procedure. The careful appraisal and analysis of geotechnical data
helps to chalk out the strategies for coping with various slope failures. Excavation of 150 m high spillway cut slope of
Dhauliganga project experienced various geotechnical problems due to complex geological setup and adverse
topographical conditions. With successful application of state of the art technology, the problems were conquered with
success. The high angle spillway cut slope necessitated with progressive change in the design of spillway by reducing
its width and utilization of diversion tunnel as spillway tunnel. For the first time in Himalayan terrain, a reinforced
anchored drift was constructed to stabilize the vulnerable spillway cutslope. The present paper deals with the several
geological problems faced during the excavation of 150m high spillway cut slope of 280 MW Dhauliganga Project, St-I
(Uttarakhand) and its remedial measures.
Keywords: Cutslope, Hydroelectric project, geotechnical investigations
INTRODUCTION i. A massive rock slope above the dam axis, spillway,
intake structure and chute channel consisting of
The 280MW Dhauliganga HE Project Stage-1, a run of the jointed biotite gneiss rock mass.
river scheme on river Dhauliganga is located in Dharchula, ii. The overburden slope (less steep) above the spillway
Distt.- Pithoragarh, Uttarakhand (Fig-1). Despite many approach channel was composed of large
odds, the project was successfully completed with disintegrated rocky blocks mixed with soil resulting
scheduled time of 5 years. The project has been from sliding activities in the geological past.
characterized by difficult access condition, unfavorable
topography, very active monsoon and many technological
hurdles. Construction of spillway cutslope and handling
70m deep overburden in the river bed were two major
challenges. In the DPR, 111m high rockfill dam above
foundation with conventional clay core was proposed.
Keeping in view the difficulty in removing deep overburden
in river bed and non-availability of clay borrow areas in
proximity, project design was reviewed in association with
Electro watt Engineering, Switzerland. Subsequently, type
of dam was changed to Concrete Faced Rockfill Dam
(CFRD) of 51m height.
Fig-1. Location and General Layout of Dhauliganga H.E.
Provision of low level chute spillway on the right bank Project
necessitated the excavation of large rock slopes. The GEOLOGICAL INVESTIGATION
natural slope of the existing right bank was grouped into Geological Description
two regions from downstream to upstream.
The project area is located in Chiplakot Formation belonging
*CMD, MECL to Precambrian age. All the structural components of the
**Chief (Geology), NHPC
1
SSIOMCE 2015
project are housed in single formation comprising mainly
of biotite gneiss with subordinate schist & patches of augen
gneiss. The project is bounded by North Chiplakot thrust
in upstream and South Chiplakot thrust in downstream
side which has given rise to intense jointing in the area.
The Chiplakot rock accordingly exhibits prominent jointing
rendering the rock blocky at most of the places. The joint
systems are continuous wherein one joint can be traced
for several hundred meters. An extensive survey had been
carried out during investigation stage (Dhauliganga, 2011).
The area above dam axis and spillway chute channel was
occupied by moderately jointed biotite-gneiss rock mass
with occasional bands of talc mica schist. The rock slopes
on the right bank were clearly influenced by four families
of joints, viz S-1(040-75/40-55), S-2(315-355/50-75), S-
3(120-170/40-70) and S-4(180-220/40-70) (Fig.-2). Among
these, S-2 joint was most vulnerable due to its parallelism
with the cut slope direction i.e. towards valley side. Many
wedge failures have also been experienced at different
levels. The deep seated rock mass in the area exhibited
tightening of joints with lesser frequency. Two major Shear
Zones (20cm-150cm) having attitude 180-210/70-75 & 220/
65 respectively have been recorded in the right bank. During
progressive excavation of cut slope both wedge failure and
planar failure occurred with the combination of foliation &
valley dipping joints (Fig-3). Kinematic analysis of slope
revealed the plunge of the line of intersection of S1 & S2
joint plane was more than the angle of friction of the surface.
The plunge of the line of intersection of the S-1 & S-2
plane was less than that of dip of slope face. The direction
of line of intersection of two planes was also parallel to cut
surface (Fig.4 &5).
Overburden Slope
ACKNOWLEDGEMENT
REFERENCES
7
SSIOMCE 2015