You are on page 1of 9

Journal of Rock Mechanics and Geotechnical Engineering.

2011, 3 (1): 64–72

Key rock mechanical problems of underground powerhouse in Shuibuya


hydropower station

Aiqing Wu1*, Qigui Yang2, Xiuli Ding1, Huoming Zhou1, Bo Lu1


1
Key Laboratory of Geotechnical Mechanics and Engineering of Ministry of Water Resources, Yangtze River Scientific Research Institute, Wuhan 430010, China
2
Changjiang Institute of Survey, Planning, Design and Research, Wuhan, 430010, China
Received 8 January 2011; received in revised form 14 February 2011; accepted 18 February 2011

Abstract: The complicated rock structures and the stability of surrounding rocks of the underground powerhouse were the key
rock mechanical problems in Shuibuya hydropower station. In order to overcome the related rock mechanical problems
encountered during its construction, a comprehensive research was carried out for the underground powerhouse in Shuibuya
hydropower station based on a detailed geological survey. It covers the investigations on the initial in-situ stress distribution
features, rock mechanical properties, engineering rock mass classifications by different methods, numerical modeling for
stability and support analysis, proper measures for rock excavation and support. The results show that the rock excavations of the
underground powerhouse under the given geological conditions can be controlled effectively. Some measures, suggested by the
designers, are proved to be rational and effective. These measures mainly consist of: (1) the soft rock replacements by concrete in
local area below the crane beam, (2) the shotcrete and reinforcement by rock bolts and anchor cables in surrounding rocks, and
(3) 2 m concrete placement on the rock bench between adjacent tailrace tubes. The engineering practice shows that the treated
surrounding rocks have a good overall stability. The deformation behaviors observed by safety equipments are within the
designing limits. The research conclusions on the related rock mechanical problems, prior to the underground powerhouse
excavations, are reliable.
Key words: Shuibuya hydropower station; underground powerhouse; stability of surrounding rocks; rock excavation and
support; soft rock replacement

wall of main powerhouse in the Three Gorges project


1 Introduction [3]; (2) siltized interlayers located nearly above the

roof of the underground powerhouse in sedimentary
The site of a proposed hydropower stations usually rocks in Xiaolangdi project [1, 4]; (3) large-scale karst
has many unfavorable geological structures, caverns near surrounding rocks in Goupitan hydro-
threatening the stability of surrounding rocks of power station [5, 6]; and (4) steeply dipped bedding
underground powerhouses. According to engineering planes in surrounding rocks with their orientations
practices in underground powerhouse at present in nearly parallel to the axis of underground powerhouse
China, four typical cases are listed as follows: (1) in Pengshui hydropower station [7]. For these
unfavorable fault intersections with the surrounding unfavorable geological conditions, some special
rocks, such as fault faults intersections of f16 and fi in engineering measures have been proven to be
the downstream wall of the main underground successful. They include (1) reinforced concrete tunnel
powerhouse in Baishan hydropower station [1, 2], and replacement combined with anchor cables used in
potential unstable rock blocks formed by fault Baishan hydropower station; (2) concrete replacement
intersections of F22, F20, f84, f10, etc., in downstream in controlled faults combined with anchor cables in the
downstream wall of underground powerhouse in the
Doi: 10.3724/SP.J.1235.2011.00064 Three Gorges project; (3) systematic anchor cables
*Corresponding author. Tel: +86-27-82820332; installed in the roof and sidewalls of main underground
E-mail: wuaiqing@vip.sina.com
Supported by the National Key Technology R&D Program of China
powerhouse in Xiaolangdi project and Penshui
(2008BAB29B01) hydropower station; and (4) treatment mainly with
Aiqing Wu et al. / J Rock Mech Geotech Eng. 2011, 3 (1): 64–72 65

concrete backfill in karst caverns in Goupitan bank of the dam. It consists of intake tunnels, main
hydropower station [1–7]. powerhouse, busbar galleries, the 500 kV translators
The underground powerhouse is the main structure installed in the ground surface, the tailrace tunnels and
in Shuibuya hydropower station. Its stability problems the related structures for its intake and outlet designs.
were concerned mainly due to the unfavorable The main powerhouse is 23 m in span, 68 m in height
geological conditions. They include the soft and hard and 150 m in length. The elevations of the main
layers of rocks alternately distributed in surrounding powerhouse are 230.47 m at its roof and 162.80 m at
rocks, especially with the soft rock in the lower part of its lowest excavation surface. Its overburden thickness
the powerhouse, and several interlayer shear zones is 170 to 220 m.
developed between the soft and hard rock layers or in The axial direction of the main powerhouse opening
the soft rocks. These shear zones behave obviously the is 296°, and the attitude of rock stratum is 245°∠
mechanical properties as those of soft rock. They have 8°–15°. The surrounding rocks of the main
lower shear strength and creep property when they are powerhouse mainly consist of limestone, bioclastic
exposed to the excavation surface or met with water. It limestone, sandstone and marly shale. The rock strata
is shown that these unfavorable geological features extending from the roof to the bottom of the opening
could have great side effects on the stability of the consist of Qixia group (P1q4 , P1q3 , P1q2 , P1q1 ) , Ma’an
underground powerhouse if no special reinforcements group (P1ma), Huanglong group (C2h), and Xiejingsi
in addition to rock bolt and shotcrete are applied. group (D3x).
In order to make a reasonable evaluation for the Joints in the underground powerhouse area are
stability of underground powerhouse, a comprehensive developed and categorized into four groups according
investigation on key rock mechanical problems of to their orientations. Joints are steeply inclined in most
underground powerhouse in Shuibuya hydropower cases, and have an average width of 0.2–2.0 cm. Figure 1
station has been carried out. It is based on a detailed shows the cross-section of the underground power-
scheme including the initial in-situ stress distribution house where rock masses in the strata P1q3 , P1q1 , P1ma,
features, rock mechanical properties, engineering rock lower C2h and D3x usually behave as moderately soft
mass classifications by different methods, numerical rocks or interlayer shear zones.
modeling for stability and support analysis, safety In addition, except for the horizontal exploratory
margin for overloading and failure features, proper adits excavated directly from river bank above water
measures for rock excavation and support [8–15]. level, a special exploratory adit named PD42, designed
Based on a general introduction to the key rock to investigate in detail the geological conditions
mechanical problems of the underground powerhouse, especially for the lower soft rocks, was excavated prior
related to the complicated rock structures and the soft to the excavation of the underground powerhouse. The
rock on the surrounding rocks, a brief summary of the special adit PD42 was 24° downward inclined and 280 m
investigation on stability and rock support for the long and extended from the elevation of 225 m nearly
underground powerhouse in Shuibuya hydropower to the roof of the main powerhouse at the elevation of
station is presented in this paper. Its practical 145 m, much lower than the bottom of the powerhouse
engineering supports and the related deformation excavation. It supplied us not only an adit for
behaviors are also analyzed and discussed. geological survey for different strata, but also a place
for in-situ rock mechanical tests directly.
2 Layout and geological conditions
3 Characteristics of in-situ stress
Shuibuya hydropower station is the third around underground powerhouse
hydropower station developed in cascade in Qingjiang
River, a sub-branch of Yangtze River. It has a concrete In-situ stress measurements were conducted using
faced rockfill dam (CFRD). Its main underground hydro-fracturing test in three crossed boreholes in adit
structures include underground powerhouse, spillway, PD42 located in the upper part of powerhouse. The
discharging tunnel and navigation structures. The three crossed boreholes consisted of a horizontal
maximum dam height is 233 m, and it is one of the borehole with a depth of 22.2 m, an inclined borehole
highest dams at present. It has 4 units of generators with 45 downward from horizontal direction and a
with a total installed capacity of 1 600 MW. depth of 26.1 m, and a vertical borehole with a depth
The underground powerhouse is located in the right of 62.5 m. The above three boreholes were located
66 Aiqing Wu et al. / J Rock Mech Geotech Eng. 2011, 3 (1): 64–72

480
460

440 el+dlQ 410.00


1
P1m el+dlQ
420 P15 13

P1q14
1q P
1q P1q124
400 P1q123
P1q12 2
380 P1q121
360 P1q11 P1q10
320.00
340 P1q9
Elevation (m)

8
P
320 1q P1q7
300 P 5 P1q6
1q

280
F50
260 Concrete P1q4 230.00
Intake tunnel 237.47
replacement
240 P1q3
200.50 P1q2 187.80
220 P1q3 P1q1
C2h
2 P1ma
P1q
200 P1q1 162.8 zkf113
D3x
180 C2h Main powerhouse
160 Tailrace tunnel
D3x
140
83.40 m 57.36 m 327.34 m 12.19 m

Fig.1 Cross-section of underground powerhouse in Shuibuya hydropower station.

in a vertical plane with its strike of N46E, normally but that in hard rock the stress is relatively high. For
perpendicular to the axis of powerhouse. By using the stratum P1q4 , the rock mass is relatively hard,
hydro-fracturing test in the three crossed boreholes, homogeneous and considerably thick, and the
two-dimensional (2D) stresses of 13 different intervals distribution of the in-situ stress is relatively uniform.
were obtained. With above measured data, three- For the stratum P1q3 , the rock mass is weaker than both
dimensional (3D) stresses of the test points could be the upper stratum P1q4 and the lower stratum P1q2 , and
calculated by using elasticity mechanics. many shear zones are developed in this soft stratum.
The 3D rock stress measurements with the So the stress magnitude is relatively low. The
over-coring stress relief method were carried out limestone stratum C2h is harder than both the upper
separately at three strata, i.e. P1q4 , P1q3 and C2h, in the stratum P1ma and the lower argillaceous sandstone
lower part of the underground powerhouse. There were stratum C2h. Its stress is relatively high. Figure 2 shows
15 points of 3D measurements that were obtained the curves of stress coefficients Kx = x/z and Ky =
successfully in the inclined adit PD42. y/z versus overburden depth obtained by regression
The maximum principal stress acquired from calculation where x, y are the normal stress
hydro-fracturing test in the three crossed boreholes is components, with the right-angle coordinates x and y
about 5.62 MPa, and its dip direction and dip angle are parallel and perpendicular to the axis of underground
253.5 and 58.9, respectively. Test data from the powerhouse, respectively.
vertical borehole indicate that the direction of the 2.0
P1q5  P1q4 P1q3  P1q
1
maximum principal stress is between N76E and 1.8 C+2h
Stress coefficient

1.6
C2h  D3x
N80ºE, parallel to the stream direction of Qingjiang 1.4
1.2 Ky
River in general. 1.0
The magnitudes of the maximum principal stress 0.8
0.6 Kx
obtained by the over-coring stress relief method 0.4 P1q3 P1ma
0.2
through boreholes in strata P1q4 , P1q3 and C2h are 4.99, 0.0
40 80 120 160 200 240 280 320
3.90 and 6.44 MPa, respectively. Their direction angles
Overburden depth (m)
vary from 197º to 221º and their dip angles are less Fig.2 Curves of stress coefficients Kx and Ky versus overburden
than 5º. depth.
The magnitude distribution of stress acquired from
the three stress relief boreholes mentioned above 4 Mechanical properties of engineering
indicates the nonuniform characteristics of stress rock mass
distribution in alternately distributed soft and hard rock
layers. The in-situ stress in soft rock is relatively low, The rock mass mechanical properties in terms of
Aiqing Wu et al. / J Rock Mech Geotech Eng. 2011, 3 (1): 64–72 67

deformation and strength characteristics were studied thin carbon-argillaceous limestone intercalated layer in
through rock mechanical tests in laboratory and field. the stratum P1q1 . Its deformation modulus, friction
By using the inclined adit PD42, the in-situ rock coefficient and cohesion are 9–14 GPa, 1.2–2.0, and
mechanical tests for different strata of surrounding 0.8–1.0 MPa, respectively.
rocks were conducted in convenience. The tests (3) Composite rock mass with soft and hard thin
included rock mass deformation test, shear strength layers is deposited alternately. It includes thin carbon-
test of rock mass and shear zones, triaxial compression argillaceous limestone rich in biogenic debris in
test with specimen’s dimensions of 50 cm  50 cm  stratum P1q3 , quartz sandstone with calcareous shale
100 cm or 30 cm  30 cm  60 cm (length  width  intercalated layer in C2h. In this case, the deformation
height). In the inclined adit, ten testing adits located modulus represents the comprehensive modulus of
respectively in different strata of surrounding rocks of different rock strata, and it is influenced mainly by the
the underground powerhouse were excavated. The tests thin carbon-argillaceous limestone rich in biogenic
for these adits could objectively reflect the mechanical debris at the lower part. Its deformation modulus is
properties of different rock strata exposed to the 1–2 GPa. Its friction coefficient and cohesion by
underground powerhouse region. In-situ tests, in-situ test are 1.19 and 0.98 MPa, respectively.
conducted in the inclined adit PD42, included 34 plate (4) Shear zones. It includes shear zones No.031,
bearing tests with the plate’s dimension of 50 cm in No.001 and F205 developed in strata P1q3 , P1ma and
diameter, and 4 groups of shear strength tests with 25
C2h, respectively. As the results of interlayer shear
specimens in total for rock mass with shear area of 2
actions, the rock mass behaves as cataclastic structure
500 cm2, and 4 groups of shear strength tests with 24
characterized with scaly or slab features. Its
specimens in total for soft interlayers, and 2 groups of
deformation modulus is 0.01–0.55 GPa.
triaxial compressive tests with 11 specimens in total
Based on the geological investigation and rock
for triaxial strength properties of rock masses.
mechanical tests in different strata, the suggested
In addition, in order to realize the rheological
parameters of surrounding rocks are listed in Table 1.
properties of the surrounding rocks, especially for soft
According to the rheological laboratory test of
rocks, unconfined compressive rheological tests were
specimens, the rheological properties in terms of
conducted in laboratory for the strata P1q4 , P1q3 , P1q1 ,
compressive strength are evaluated and listed in Table
C2h and D3x and shear zone No.031, 25 specimens in
2, where the ratios of creep strength to instantaneous
total were conducted in laboratory. Rock samples taken
strength of different rock layers are also listed. The in-
from very soft rock or shear zones were processed into
situ deformation testing curves in typical strata are
non-standard specimens. The non-standard specimen
shown in Fig.3.
had a rectangle block shape with the pressure bearing
area normally from 22 to 176 cm2. Rock samples taken
from hard rock strata were processed into standard core 5 Engineering rock mass classi-
specimens with dimensions of 50 mm × 100 mm. fication of surrounding rocks
The surrounding rocks could be classified into the
following four types according to the hardness and In order to obtain a comprehensive evaluation of
intact index: quality of the surrounding rocks quantitatively and
(1) Hard rock with good homogeneity. It includes qualitatively, the rock mass classification was
medium-thick, thick bedded and micro-crystalline conducted using three different methods, i.e. BQ
limestone with bioclastic limestone inclusions in the method, Q system and RMR system. All of the works
stratum P1q4 , cherty limestone in the stratum P1q2 , associated with field investigations were carried out in
microcrystalline limestone and fine sandstone in C2h. the inclined adit PD42.
Its deformation modulus, friction coefficient and 5.1 BQ method based on Chinese national standard
cohesion are 14–40 GPa, 1.9–2.4, and 1.0–1.5 MPa, (GB50218-94) [16]
respectively. According to Chinese national standard (GB50218-
(2) Less hard rock with medium-thick and thick 94) for engineering rock mass classification,
bedded limestone. It includes medium-thick and thick determination of rock mass basic quality is the first
carbon-argillaceous limestone rich in biogenic debris step. The rock mass basic quality is determined by two
in the stratum P1q3 , and medium-thick limestone with parameters, i.e. rock solidness and rock mass integrity.
68 Aiqing Wu et al. / J Rock Mech Geotech Eng. 2011, 3 (1): 64–72

Table 1 Suggested parameters of surrounding rocks.


Compressive Tensile Deformation Shear strength
Poisson’s
Rock type strength strength modulus Stratum
ratio f c (MPa)
(MPa) (MPa) (GPa)
Bioclastic limestone 60–65 1.0–1.5 15.0–20.0 0.25 1.1–1.2 1.1–1.2 P1q4-5
Carbon-argillaceous P1q3 , P1q
1
25–30 0.5–0.8 3.0–5.0 0.30 0.8–0.9 0.6–0.8
limestone
Microcrystalline
limestone, cherty 70–80 1.0–1.5 15–20.0 0.25 1.2–1.3 1.20–1.30 P1q2
limestone
Coal bed 15–20 0.2–0.5 0.4–0.8 0.35 0.5–0.55 0.10–0.15 P1ma
Quartz sandstone with
calcareous shale 40–45 1.0 15.0–20.0 0.25 1.2–1.3 1.00–1.20 C2h
intercalated
Argillaceous silt stone
40–45 0.2–0.5 3–4 0.30 0.8–0.9 0.6–0.8 D3x
with shale intercalated
No.001, No.031,
Shear zones 0.01–0.55 0.40–0.45 0.25–0.30 0.02–0.03
No.041
Faults 1.5–2.0 0.30 0.35–0.45 0.01–0.05 F3, F 4, F 5

Table 2 Ratios of creep strength to instantaneous strength for engineering rock mass, the necessary correction
different strata. parameters should be considered on the basis of
Stratum Ratio (%) Mean value () classification of rock mass. They include the features
P1q4 40.38–76.58 62.57
of different rock engineering types, the state of
P1q3 40.83–59.08 52.47
1
groundwater, the initial in-situ stress, and the
P1q 55.16–69.45 59.98
C2h 33.56–53.24 43.53
combination of relative orientation of the structural
D3x 30.43–69.94 47.51 axis with the occurrence of the main weak
No.031 40.53–59.94 46.81 discontinuity sets. Based on the corrective parameters,
the corrected rock mass basic quality index [BQ] is
5 Ed = 38.01 GPa calculated according to the supplied formula.
Ee = 47.06 GPa The rock mass index BQ is calculated with two
4
parameters, i.e. saturated uniaxial compression
Pressure (MPa)

3 strength Rc (MPa) and intactness index K v :


2 BQ  90  3Rc  250 K v (1)
Then the values of the corrected index [BQ] are
1
calculated for all the strata exposed in inclined adit
0
0 20 40 60 PD42, as shown in Fig.4.
Deformation (103 mm)
650 P1ma
(a) Stratum P1q4 .
550
Ed = 3.49 GPa 450
5
[BQ]

Ee = 5.60 GPa 350 P1q4 P1q2 1


P1q D3x
C2h
4 250 P1q3
150
Pressure (MPa)

3 50
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280
2 Depth of adit (m)
Fig.4 Values of [BQ] along adit PD42 passing through different
1 rock layers.
0
0 100 200 300 400 500 600 5.2 Evaluation based on Q system [17]
Deformation (103 mm)
The classification based on the Q system was carried
(b) Stratum P1q3 .
Fig.3 In-situ deformation testing curves in strata P1q4 and P1q3 .
out along the inclined adit PD42. Figure 5 shows the

25
P1ma
Rock solidness and rock mass integrity should be 20 P1q4 C2h
P1q3 P1q2 1
P1q D3x
determined by both parallel methods, namely the 15
Q

10
qualitative classification and the quantitative indices. 5
After the rock mass basic quality is evaluated, the rock 0
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280
mass class is determined by combining qualitative Depth of adit (m)
characteristics of rock mass and basic quality index Fig.5 Values of Q along adit PD42 passing through different rock
(BQ). In order to achieve a detailed classification of layers.
Aiqing Wu et al. / J Rock Mech Geotech Eng. 2011, 3 (1): 64–72 69

values of Q along the adit passing through different 2D and 3D conditions with both FEM and FLAC were
rock layers. The values of Q range from 0.4 to 23. The carried out for underground powerhouse excavation
values of Q for most strata are greater than 5 while and its reinforcements. The deformation of
those for soft layers are less than 5. surrounding rocks, stress state and the distribution of
5.3 Evaluation based on RMR system [17] plastic zone with/without reinforcement were obtained
The classification by RMR system was also carried through numerical modeling. On the basis of modeling
out in the same inclined adit. Figure 6 shows the results, the reinforcement effects of different support
results of RMR classification. Values of RMR of rock schemes were evaluated. At the same time, support
masses normally range from 40 to 60, indicating that design was optimized.
the rock could be described as a fair rock. For soft The support schemes were the combination of
layers, values of RMR are between 20 and 40, which different measures as follows: (1) Reinforced concrete
indicate poor rock. Good rock mass with a value of replacement of the soft rock in stratum P1q3 with
RMR greater than 60 occupies a low proportion. cross-section of 7 m  7 m in the upstream and
80
downstream sidewalls. (2) When the excavations of the
70 P1q4
P1q3 P1q2 1
P1q P1ma underground powerhouse reached the installation
60
RMR

50 elevation of turbine machine, the elevation of 179.0 m,


40
30
C2h D3x 2 m thick concrete placement was adopted for the
20
0 20 40 60 80 100 120 140 160 180 200 220 240 260 280
remained rock surface between adjacent turbines. (3)
Depth of adit (m) Shotcrete with a thickness of 20 cm for surrounding
Fig.6 Values of RMR along adit PD42 passing through different rocks support. (4) Systematic rock bolts are set with
rock layers. alternate dimensions of 25/32 mm, and L = 6/8 m. (5)
Seven rows of 2 000 kN grade anchor cables (L = 25 m)
5.4 Comprehensive analysis of rock mass evaluation
were installed in the roof of the main powerhouse, two
The detailed results of rock mass classification for
rows of 2 000 kN grade anchor cables (L = 20, 25 m)
individual stratum of surrounding rocks by different
methods are listed in Table 3. In order to in the upstream sidewall, and three rows of 2 000 kN
comprehensively compare the classification results grade anchor cables (L = 20, 25 m) in the downstream
obtained by above three methods, the rock mass sidewall. (6) Seven rows of 1 500 kN grade anchor
classification by Q system is categorized into five cables (L = 25 m) were installed in the roof of the main
grades. The values of Q either < 1, or 1–4, or 4–10, or powerhouse, and six rows of 1 500 kN anchor cables
10–40, or > 40 are corresponding to the grades V, IV, (L = 20, 25 m) in the upstream and downstream
III, II, I, respectively. It has been shown that there is a sidewalls. The reinforcement of surrounding rocks
good agreement for evaluating the quality of rock with schemes (5) and (6) were for comparative study.
masses by using different methods. The rock mass The following four calculation cases considering the
classification reflects comprehensively the complicated combination of excavation and supports were
characteristics of surrounding rocks of the underground conducted in numerical simulations:
powerhouse. (1) Case 1: step-by-step excavation without any
Table 3 Results of rock mass classification by different methods.
reinforcement;
(2) Case 2: step-by-step excavation with supports
[BQ] Q RMR
Stratum
Value
Rock
Value
Rock
Value
Rock formed by schemes (1) and (2);
class class class
(3) Case 3: step-by-step excavation with supports
P1q4 399–587 III–I 8–22 III–II 45–62 III
formed by schemes (1)–(5);
P1q3 287–361 IV–III 4–8 III 37–57 IV–III
P1q2 393–503 III–II 9–13 III–II 43–62 III–II (4) Case 4: step-by-step excavation with supports
1
P1q 399–510 III–II 3–23 IV–II 35–60 IV–III formed by schemes (1)–(4) and (6).
P1ma 127–150 V 1–2 IV 30–60 IV–III The results of numerical simulations showed that
C2h 163–549 IV–II 0.43–14 V–II 34–67 IV–II replacements of soft rock and systematic rock bolting
D3x 163–170 V 1–2 IV 27–31 IV
would enable the overall deformation of the
surrounding rocks to decrease effectively. Comparing
6 Numerical modeling on excavation the cases 1 and 2, the maximum horizontal
stability and its support effects displacement of the upstream sidewall decreased from
40.07 mm (case 1) to 31.12 mm (case 2), and the
During the designing stage, numerical simulations in maximum horizontal displacement of the downstream
70 Aiqing Wu et al. / J Rock Mech Geotech Eng. 2011, 3 (1): 64–72

sidewall decreased from 45.48 mm (case 1) to 35.07


mm (case 2). Meanwhile, the maximum rebounding
displacement of the excavation of bottom surface
decreased from 110.9 mm (case 1) to 50.18 mm (case
2). The displacements of the other parts of the
surrounding rocks were decreased by 3.0–10.0 mm.
With shotcrete and rock bolts installed, the
displacements decreased more. Comparing the cases 3
and 2, the displacements of the roof was and the
sidewalls of the main powerhouse decreased obviously. Fig.7 3D numerical model of underground powerhouse in
The maximum vertical displacement of the roof Shuibuya hydropower station.
decreased by about 10.09 mm, and the displacements
of the upstream and downstream sidewalls of the

Maximum displacement (mm)


70 Upstream sidewall
turbine pits were decreased by about 5.13 and 12.88 60 Downstream sidewall
Roof
mm, respectively. The displacements of sidewalls, 50
intake tunnels and the intersections of the main 40
30
powerhouse with the busbar galleries and the tailrace
20
tunnels all decreased with different scales. The average 10
deformations decreased by 3.0–6.0 mm. The support in 0
Case 1 Case 2 Case 3 Case 4
the case 4 behaved the best effect. In this case, the Calculation case
maximum reduction of displacement of the Fig.8 The maximum displacements corresponding to calculation
surrounding rocks due to excavation was 20.54 mm. cases.
With the replacement of the soft rock and
installation of systematic bolts, the surrounding rocks
had a better stress state after excavation than that
without any support. Comparing the cases 3 and 1, the
range of tensile zone in the side walls was decreased
greatly. The plastic zones developed at the intersection
of the headrace tunnels and the upstream sidewall of
the main powerhouse, the intersections of main
powerhouse with the busbar galleries and the tailrace
tunnels decreased largely, too. Comparing the cases 4
and 3, the plastic zone further decreased. This
Fig.9 Plastic zone of surrounding rocks in case 4.
indicated that the installation of anchor cables (support
scheme (6)) played an important role in improving the
stress condition of the surrounding rocks and the 7 Actual rock support and
overall stability of the underground caverns. deformation behaviors
In general, with the current support design scheme
(case 4), the maximum displacement of the key 7.1 Actual rock support
position of the surrounding rocks could be reduced by Based on the detailed survey of the distribution of
15%–30%. The displacement of the surrounding rocks the soft rock and the comprehensive researches on rock
ranged typically from 40 to 60 mm, except for the one mechanical problems, the actual excavation scheme
where soft rock layers were exposed. With the support and rock support of the underground powerhouse were
schemes (1) and (2), if shotcrete and rock bolt were proposed as follows:
installed immediately after excavation, the displace- (1) Replacement of the soft rock below elevation of
ment of the surrounding rocks would range from 20 to the crane beam. The rock bolted crane beam is a
35 mm, with the maximum value less than 60 mm. load-bearing structure and has a strict limit for the
The 3D numerical model, the maximum defor- deformation magnitude of the surrounding rocks. It is
mations at different places corresponding to related suggested to replace the stratum P1q3 with concrete
calculation case and the plastic distribution around the C25, and the replacement area is 7 m × 7 m for both
surrounding rocks in calculation of case 4 are shown in the upstream and downstream sidewalls. Replacement
Figs.7–9, respectively. of the soft rock stratum P1q3 and its contacting
Aiqing Wu et al. / J Rock Mech Geotech Eng. 2011, 3 (1): 64–72 71

consolidation grouting should be completed prior to shear zones exposed to side walls.
the main powerhouse excavation. (5) Locking support of intersections prior to
(2) Supporting with shotcrete and rock bolts. For excavation. For the intersections of the main
roof and sidewalls of the main powerhouse and the powerhouse with the intake tunnels, busbar galleries
tailrace tube excavation surface, it is suggested to and tailrace tunnels, the excavation and locking
systematically install rock bolts with length L = 6/8 m, support should be completed prior to the excavation of
combined with steel fiber shotcrete. The thickness of main powerhouse when proceeding to corresponding
the shotcrete is 15–20 cm. elevations. This will reduce the deformations of the
(3) Grouting and protection of the soft rock exposed sidewalls of the main powerhouse and the stress states
to the lower part of the main powerhouse. Except for of the intersections can be improved.
stratum P1q3 , the soft rock is mainly exposed below Figure 10 shows the practical rock support scheme.
elevation of the tailrace tube inlet. Numerical results In Fig.10, the characters in the small circle symbol
show that if the excavation is preformed from roof to represent different types of rock supports. “MS”
bottom of the main powerhouse with normal step-by- represents the anchor cables with capacity force of
step method, the deformations of the side walls of the 1 500 kN and cable length of 25 m. “MS1” represents
turbine pit will be considerably large and the maximum the anchor cables with capacity force of 1 500 kN and
displacement will reach 16 cm. This will cause a cable length of 20 m. “A” represents the rock bolts
negative effect on the stress, deformation and stability with spacing of 1.5 m and length of 8 m. “A1”
of the upper part of the surrounding rocks. Therefore, represents the rock bolts with spacing of 1.5 m and
when the full-face excavation is preceded to the length of 9.3 m. “B” represents the rock bolts with
elevation of 179 m, the anchor piles are installed in spacing of 1.5 m and length of 6 m. “C” represents the
rock masses around all the turbine pits. Then rock bolts with spacing of 1.5 m and length of 10 m.
reinforced concrete C25 with a thickness of 2 m is “F” represents the rock bolts with spacing of 1.5 m and
backfilled on the rock bench between adjacent tailrace length of 7 m.
tubes to protect the excavation surface. Thus, rock
benches with a width of 16 m and a height of 14 m will
be formed between adjacent tailrace tubes, which
contact directly the upstream and downstream
sidewalls, and a strong support between the two walls
will be supplied. After the reinforced concrete
placement is completed, the grouting of the rock
masses around tailrace tubes can be performed, and a
strictly controlled excavation along tailrace tubes is
preceded.
(4) Reinforcement of shear zones and faults by
anchor cables. The roof of the main powerhouse is
Fig.10 Practical rock support scheme (unit: m).
located at stratum P1q4 where several shear zones and
faults are fully developed. In order to prevent the 7.2 Deformation behaviors
negative effect of shear zones on the stability of the The construction of the underground powerhouse
roof, the 1 500 kN grade anchor cables, 23 rows in started in 2002. Till mid 2005, all the excavation and
longitude and 7 rows in vertical have been installed. support were completed. During the excavation of the
The length of the cable is 25 m, and the spacings are underground powerhouse, different kinds of safety
4.2 m × 4.5 m. monitoring equipments were used to monitor the
For the upstream sidewall, 6 rows of 1 500 kN grade deformation behaviors of the surrounding rocks. They
anchor cables have been installed with a length of included the convergence meters, multi-point
20–25 m and the spacing in longitude direction is 4.5 m. extensometers, cracking measurement especially focused
For the downstream sidewall, 5 rows of 1 500 kN on the crane beams, and anchor force measurement of
grade anchor cables have been installed with a length anchor cables and rock bolts.
of 25 m and the spacing in longitude direction is 4.5 m. It was shown that the reinforced surrounding rocks
The purpose of installing anchor cables on the had a good overall stability. The maximum
sidewalls is to prevent the shear deformation caused by displacements observed by multi-point extensometers
72 Aiqing Wu et al. / J Rock Mech Geotech Eng. 2011, 3 (1): 64–72

at upstream and downstream sidewalls and in the roof 1982, (1): 271–284, 292 (in Chinese).
of the main powerhouse were 6.3, 9.2 and 4.9 mm, [3] Wu Aiqing, Xu Ping, Xu Chunmin, et al. Researches on stability for
surrounding rock masses of underground power house in the Three
respectively. Figure 11 shows the monitoring results by
Gorges project. Chinese Journal of Rock Mechanics and Engineering,
multi-point extensometers installed at downstream
2001, 20 (5): 690–695 (in Chinese).
sidewall at the section of unit No.2, where the curves [4] Liu Quanpeng, Dong Dezhong. Excavation and its support in roof of
of L1, L2 and L3 represent, respectively, the anchorage the underground powerhouse. Underground Engineering Techniques,
positions with 1, 6 and 11 m from excavation surface 1996, (3): 61–68 (in Chinese).
to the downstream wall in one borehole. [5] Fu Jing, Ding Xiuli, Zhang Lian. Numerical analysis on improvement
of stability of underground grotto group surrounding rock mass with
filling in Karst region. Journal of Yangtze River Scientific Research
Institute, 2006, 23(4):47–50 (in Chinese).
[6] Li Yuji, Song Jing, Liu Gaofeng, et al. The problem and its treatment
about wall rock stability of Goupitan hydropower station’s
underground powerhouse in Wujiang River. Resources Environment
and Enineering, 2009, 23 (5): 754–757 (in Chinese).
[7] Ding Xiuli, Dong Zhihong, Lu Bo, et al. Deformation characteristics
and feedback analysis of surrounding rock of large underground
powerhouses excavated in steeply dipped sedimentary rock strata.
Fig.11 Time-history curves of the maximum displacement Chinese Journal of Rock Mechanics and Engineering, 2008, 27 (10):
observed by multi-point extensometers.
2 019–2 026 (in Chinese).
[8] Wu Aiqing, Ding Xiuli, Chen Shenghong, et al. Research on
8 Conclusions deformation and failure and characteristics of an underground
powerhouse with complicated geological conditions by DDA method.
Chinese Journal of Rock Mechanics and Engineering, 2006, 25 (1):
The key rock mechanical problems of the underground
1–8 (in Chinese).
powerhouse in Shuibuya hydropower station have been [9] Zhang Lian, Ding Xiuli, Fu Jing. Three-dimensional numerical
presented and discussed in detail. In order to resolve the analysis of stability of surrounding rocks of Shuibuya underground
related rock mechanical problems encountered prior to powerhouse. Rock and Soil Mechanics, 2003, 24 (Supp.1): 120–123
and during its construction, a detailed study in terms of (in Chinese).

rock mechanics, based on carefully issued schemes, was [10] Ding Xiuli, Sheng Qian, Wu Aiqing, et al. Numerical modeling of

carried out. It included the initial in-situ stress excavation and support of the underground powerhouse of the
Shuibuya hydropower project. Chinese Journal of Rock Mechanics
distribution features, rock mechanical properties,
and Engineering, 2002, 21 (Supp.1): 2 162–2 167 (in Chinese).
engineering rock mass classifications by different
[11] Yu Yong, Yin Jianmin, Yang Huoping. Rock mass classification for
methods, numerical modeling for stability and support underground powerhouse of Shuibuya Project. Chinese Journal of
analysis, proper measures for rock excavation and Rock Mechanics and Engineering, 2004, 23 (10): 1 706–1 709 (in
support. The results show that rock excavations of the Chinese).
underground powerhouse under the given geological [12] Hu Ying, Xie Junbing, Hu Haoran, et al. Research on the key

conditions can be handled with technically. The shotcrete technologies for the underground tunnel chambers of
Shuibuya project. Water Power, 2003, 29 (9): 27–30 (in Chinese).
measures suggested by the designers are proved to be
[13] Fu Yong. Study on the excavation and support method for the
reasonable and effective.
underground powerhouse complex of Shuibuya hydropower project
The engineering practice shows that the surrounding
and its practice. Yunnan Water Power, 2004, 20 (4): 68–71 (in
rocks have a good overall stability. The deformation Chinese).
behaviors observed by safety equipments are under the [14] Ding Xiuli, Fu Jing, Liu Jian, et al. Study on creep behavior of
designing limits. The research conclusions on the alternatively distributed soft and hard rock layers and slope stability
related rock mechanical problems, prior to analysis. Chinese Journal of Rock Mechanics and Engineering, 2005,
underground powerhouse excavations, are reliable. 24 (19): 3 410–3 418 (in Chinese).
[15] Wu Aiqing, Yang Qigui, Zhou Huoming, el at. Rock mechanical study
References of underground powerhouse in Shuibuya project. Journal of Yangtze
River Scientific Institute, 2006, 23 (4): 1–7 (in Chinese).

[1] Dong Xuecheng, Tian Ye, Wu Aiqing. Rock mechanics in hydraulic [16] The Professional Standards Compilation Group of People’s Republic
of China. GB50218-94 Standard for engineering rock masses
engineering. Beijing: China Water Power Press, 2004 (in Chinese).
classification. Beijing: China Planning Press, 1995 (in Chinese).
[2] Wang Yinhui. Excavation construction of underground powerhouse in [17] Bieniawski Z T. Engineering rock mass classification. [S.l.]: John
Baishan hydropower station. Underground Engineering Techniques, Wiley and Sons, Inc., 1989.

You might also like