Professional Documents
Culture Documents
ACTIVITY NO. 1
(ENERGY PLAN)
DEMAND
Peak Demand
The annual average growth rates of
peak demand for Luzon and are in the 4%
level. Due to its already matured and highly
industrialized economy, Luzon’s peak
demand has been recorded the highest for
the whole country from 2011-2014. Peak
demand for Luzon occurred during the
summer months of April, May and June and
is triggered by the increase in the usage of
cooling and air-conditioning units due to
high temperature.
About 25% of this increase came from the operation of the new large coal
plants. The recommissioning of 242 MW Therma Mobile Power Barges (Former
Duracom) in Navotas and the 116 MW Subic Diesel fuel-fired Power Plant were
also added to the total capacity of Luzon. Recently, Hopewell Gas Turbine was
turned over to Millennium Energy, Inc. (MEI) and the successful recommissioning
of the 100 MW Gas turbine in Navotas in May 2015 commenced. The
commercial operation of the 20 MW Maibarara geothermal plant in Batangas,
recommissioning of 130 MW Bacman geothermal plant in Sorsogon and uprating
of 132 MW Binga
Hydroelectric
plant also
increased the
capacity of
geothermal and
hydro plants from
2011-2015.
Table 1. Luzon
Additional Capacities,
2011-2015 (In MW)
Power Demand-Supply Outlook, 2016-2040
Coal fired power plants are a type of power plant that make use of the
combustion of coal in order to generate electricity. Their use provides around 40% of
the world's electricity and they are primarily used in developing countries. Countries
such as South Africa use coal for 94% of their electricity and China and India use coal
for 70-75% of their electricity needs, however the amount of coal China uses dwarfs
most other countries. The use of coal provides access to electricity to those who
previously didn't have it, which helps to increase quality of life and reduce poverty in
those regions, however it produces large quantities of different pollutants which reduces
air quality and contributes to climate change.
The building of a power station is a lengthy, costly, complicated process and a large
number of factors influence the final decision.
Any decision on new capacity is based on Eskom’s Integrated Strategic Electricity Plan
(ISEP). The plan takes numerous factors into account to estimate future growth in
electricity demand. The nature of the growth must also be taken into consideration as
an increase in either base load requirements or peaks in demand, will determine the
type of power station to be built and the priority of construction. Eskom’s planning
processes are matched by similar processes carried out by the Department of Minerals
and Energy Affairs and the National Electricity Regulator (NER).
Site Selection
When deciding on the location of a power station, factors such as the following are
taken into consideration:
- the ease with which the new station can be integrated into the national transmission
network
- environmental impacts of both the power station and its related infrastructure, such as
transmission lines
- construction period
- impact on the local area in terms of its communities and natural environment
- capital costs
- operating costs
- employment
The site selection process starts with broad, minimum criteria, resulting in the
identification of a relatively large number of potential sites. In the case of a coal-fired
power station a priority is the availability of coal and water. Once the potential sites have
been identified, more rigorous criteria are applied to narrow down the number of
possible sites still further.
Legal Processes: Licences and Approvals
An important step in the process of building a power station, is obtaining the necessary
environmental approvals from the Department of Environmental Affairs and Tourism
(DEAT). This is achieved by means of an Environmental Impact Assessment (EIA)
process, which includes a wide variety of specialist studies and a strong public
participation component. By means of the EIA process, all possible impacts of the
project on the natural and social environment are identified and mitigation measures
developed. The outcome of the EIA process is an Environmental Impact Report, which
is submitted to DEAT for approval. After due consideration, DEAT will issue a Record of
Decision (ROD).
Licences to Operate:
- The NER has to issue a licence to construct and operate the new station. Licences will
also be required to transmit and distribute the electricity.
- The Department of Water Affairs and Forestry (DWAF) has to issue a permit for the
required water use.
- The Chief Air Pollution Control Officer (CAPCO) in DEAT has to issue a licence
prescribing the emissions the station is allowed to release.
- District Councils and local municipalities issuing licence prescribing the emissions the
station is allowed to release.
Construction Phases
1. Awarding of Contracts
The civil works, boiler, turbine, auxiliary plant, electrical and control and instrumentation
contracts form part of the main contracts in terms of which the overall construction plan
is implemented. Derived from these, many smaller companies are involved as sub-
contractors.
2. Site Establishment
This phase deals with the provision of the infrastructure required for the main
contractors to begin work. Land needs to be levelled, water, sewerage and electrical
services to be provided, roads constructed and construction offices established. The
terrain needs to be fenced off and security control and first aid facilities put in place.
3. Construction
Construction starts with the setting out and excavation of foundations. If the power
station is to use a conventional wetcooling system, the trenches and pipe work for the
cooling water ductings must be in place before construction of the turbine hall
commences.
Although a number of areas are under construction at the same time, the main areas
are the foundations of the boiler house, turbine hall, cooling towers and chimneys.
The period from site establishment and commencement of civil work, to the point where
the first boiler and turbine can be commissioned, is approximately four years.
Subsequent units would be commissioned at intervals of nine to twelve months.
4. Commissioning
Auxiliary plant systems need to be commissioned first to provide logistical support for
boiler and turbine operation.These include water treatment, coal supply and ash
handling systems, electrical supplies and the transmission network.
Boiler and turbine commissioning initially involves the cleaning of all water, steam and
auxiliary pipework. Important equipment such as motors, pumps, lights and control
circuits are among the first items to be commissioned.
Safety checks and testing are carried out before any plant is commissioned.
Plant and equipment that has been commissioned is “taken over” by Eskom, although
the contractor still remains responsible for defects. A production unit (boiler, turbine and
generator) is taken over by Eskom and put into commercial operation once all the tests
have been successfully carried out.
5. Staffing
Eskom will manage all contracts in accordance its new build policy. Eskom personnel
who will be responsible for the running and maintenance of the plant are appointed and
trained during construction. By working closely with the contractors during the
commissioning and take-over phases they are readied for the moment when the power
station is finally connected to the grid for commercial production of electricity.
3. DEMOGRAPHICS
1. Bagong Bayan
2. Calero
3. Dahican
4. Dayhagan
5. Larap
6. Luklukan Norte
7. Luklukan Sur
8. Motherlode
9. Nakalaya
10. Osmeña
11. Pag-Asa
12. Parang
13. Plaridel
14. North Poblacion
15. South Poblacion
16. Salvacion
17. San Isidro
18. San Jose
19. San Martin
20. San Pedro
21. San Rafael
22. Santa Cruz
23. Santa Elena
24. Santa Milagrosa
25. Santa Rosa Norte
26. Santa Rosa Sur
27. Tamisan
5. Projected Capacity