WORK SEQUENCE

COATING APPLICATION 36 INCH CGS 5 DURI TO DUMAI AREA PACKAGE 2 - 2019

1. SITE VISIT

2. DOCUMENT
PREPARATION

3. KICK OFF
MEETING

4. MOBILIZATION &
SITE PREPARATION

6. Check 8. Coating 2.15 10. Back Fill and


5. INISIAL MSW Underground 7. Excavation Compacted
Cable & HDT

7.1. Wall Thickness 11. JOINT FINAL


(Finding Pitting WALKTHRU
Corosion)
 Quantity Survey
 Material Inventory
 Punch List

7.2. Install Pipe 12. HOUSE KEEPING


Sleeve Construction Finish

13. QAL, MAC & CLOSED


14. End of SR OUT

REV: 01