Professional Documents
Culture Documents
###
0 0 ###
29
0 0 ###
30
###
###
46
O-08-A-07 1.D5 Teak Wood Frames (As per size) 9,333,333 0 ###
55
1.B1-k Base Coat -50 mm thk IPS Flooring - Rate 0 7,687,290 ###
60
is inclusive of cement
O-08-B 1.D6 Plumbing fittings (CP, wash basin, SS 8,533,333 27,236,000 ###
61
sink, WC pan)
O-08-C 1.D12 HVAC works (Split AC units) 29,333,333 36,731,747 ###
62
###
63
O-08-G 1.D13 DG set backup for lifts & emergency 4,266,667 4,266,667 ###
68
lighting
O-08-H 1.D9 Iron & Mongery including digital lock - M/s. 10,222,222 10,287,646 ###
69
Magnum
O-08-I 1.D7 Windows (Finesta) 59,877,399 72,324,261 ###
70
###
73
###
74
###
AAAA 0 0 101
###
BBBBBB 0 0 102
###
CCCCCCC 0 0 103
###
###
O-15-B 0 0 156
###
O-15-C 0 0 157
###
O-16-B 0 0 160
###
O-16-C 0 0 161
###
Add:
E13 Attendance fees #REF!
E14 Profit #REF!
1.13 Landscaping b b b
I1070 5
Davis Langdon & Seah Consulting India Pvt Ltd
SCOPE AND ASSUMPTIONS
ORCHARD RESIDENCY
2.22 Street lights including electric pole b 43 nos @ Rs.55000 for each no including light fitting and pole b b
b Garden Spike flood light 155 nos. & 61 nos low level
2.23 Architectural Light fittings
light(650mm) is considered at podium level.
x x
2.24 UPS x Not Applicable x x
2.22 Cables
I1070 6
Davis Langdon & Seah Consulting India Pvt Ltd
SCOPE AND ASSUMPTIONS
ORCHARD RESIDENCY
5 COMMUNICATIONS
5.1 Cabling ducts from street to building x Excluded x x
5.2 Secure shaft for communications b Included x x
5.3 Main distribution frame x Excluded x x
Risers (cable from data panel(Floor DB) upto b
5.4
each flat)
Included x x
5.5 Backbone cabling x Excluded x x
5.6 Intermediate distribution frame x Excluded x x
5.7 EPABX b Included x x
5.8 Cabling at floor b Included x x
5.9 Handsets b Included x x
I1070 7
Davis Langdon & Seah Consulting India Pvt Ltd
SCOPE AND ASSUMPTIONS
ORCHARD RESIDENCY
7 OTHERS
7.1 Access control to the building b Included for Common areas b b
CCTV system at the building entry & exits and b b b
7.2 Included for Common areas
other sensitive external areas
7.3 Passenger Elevators b 1no for each building - Total 10 Nos considered b b
7.4 Service elevators b 1no for each building - Total 10 Nos considered b b
7.5 Directional signage - external & internal b Included x b
7.6 Statutory signage b Included x b
7.7 Toilet tissue dispensers x Excluded x x
7.8 Hand dryers x Excluded x x
7.9 Auto flush for urinals x Excluded x x
7.10 Paper towel dispensers x Excluded x x
7.11 MATV system x Excluded x x
I1070 8
Davis Langdon and Seah Consulting India Pvt. Ltd.,
COMPARISON OF COSTS
ORCHARD RESIDENCY
HEAD-CONTRACT PACKAGE
SN Cost Element Cost Cost per TCA % age Cost Cost per TCA % age Cost Cost per TCA
INR Per Sft of total cost REMARKS - ORCHARD INR Per Sft of total cost REMARKS DIFFERENCE IN REASON FOR INR Per Sft REMARKS DIFFERENCE IN COST REASON FOR
COST BETWEEN DIFFERENCE BETWEEN ORCHARD & INDU DIFFERENCE
ORCHARD & H1 FORTUNE FIELDS
RESIDENTIAL
B Structural Works
B1 Earth (Excavation) works 62,765,891 58 Area under consideration 16, 110,970,107 43 -16 120,322,156 74 15
670 sqmt and Avg depth of
excavation is 8.00 m.
B2 Structural works(Substructure) 236,688,842 220 810,788,351 312 Grade of concrete : M20, M30, M40 92 273,749,242 168 Grade of concrete : M10, M40 -52
B3 Structural works(Superstructure) 263,733,840 246 Grade of concrete : M20, M30, M40 -246 669,441,598 411 Grade of concrete : M10, M40 165
Antie Termite works 569,000 1 INCLUDED -1 2,435,033 1 1
Water Proofing Works 24,945,497 23 62,240,696 24 1 17,215,062 11 -13
Total B: 588,703,070 548 26.94% 983,999,154 379 21.47% -169 1,083,163,091 665 117
C Architectural Works
0
Interior Works 247,520,506 230 96,658,707 37 includes putty,plastic emulsion -193 48,211,978 30 -201
paint,OBD ,altech putty for walls &
ceiling, Duco paint, ceiling work,
French Sprit Polish for Door frames /
Shutters etc, Enamel paint on new
wood work, two or more coats of
white wash
DLS I1070 9 of 14
Davis Langdon and Seah Consulting India Pvt. Ltd.,
COMPARISON OF COSTS
ORCHARD RESIDENCY
HEAD-CONTRACT PACKAGE
SN Cost Element Cost Cost per TCA % age Cost Cost per TCA % age Cost Cost per TCA
INR Per Sft of total cost REMARKS - ORCHARD INR Per Sft of total cost REMARKS DIFFERENCE IN REASON FOR INR Per Sft REMARKS DIFFERENCE IN COST REASON FOR
COST BETWEEN DIFFERENCE BETWEEN ORCHARD & INDU DIFFERENCE
ORCHARD & H1 FORTUNE FIELDS
RESIDENTIAL
D1 External Drainage works 4,500,000 4 Main Storm Water lines & 14,888,513 6 seen annexure A for details 2 19,025,999 12 seen annexure - G for the details. 7
Sewerage line considered
D2 External Electrification 5,500,000 5 Street Light on main road & 23,433,419 9 seen annexure B for details 4 23,347,145 14 seen annexure - A for the details. 9
Podium level lighting. Excluding street lights, transformers
D3 Landscaping Works 15,000,000 14 - 0 -14 7,091,115 4 seen annexure - J for the details. -10
D4 HardScaping & Swimming Pool Works 24,150,000 22 - 0 -22 7,842,083 5 Hard scape only. Seen annexure K -18
Swimming pool equipments & services scope 4,000,000 4 Main pool -402 m3 - 01 No - 0 -4 1,012,395 1 -3
Kids pool -35 m3 - 01 No
Ladies pool - 136 m3 - 01 No
Water body features - 10 Nos
E MEP PC Sum
E1 Plumbing 123,131,020 115 5.63% 217,011,487 84 4.73% -31 94,636,785 58 -57
E1.1 Plumbing Works 95,045,020 88 1382 Nos. of 82,831,058 32 seen annexure A for details -57 34,554,515 21 seen annexure H for details -67
toilets(Bath+Toilet).Considering
Internal & shaft piping work.
Rain water & Storm water
system considered. Sanitary
fittings & material supplied by
client.
E1.2 Plumbing fittings (CP, wash basin, SS sink, WC pan) 27,236,000 25 1382 Nos. of toilets each toilet 124,800,000 48 seen annexure A for details 23 54,466,420 33 seen annexure H for details 8
consist of WC,Shower,Wash
Basin, CP Fitting. 590 nos. of
Sink & CP Fitting.
E1.3 Pumping System 850,000 1 06 Nos pumps 9,380,429 4 seen annexure A for details 3 5,615,850 3 seen annexure - G for the details. 3
0
E2 Electrical 100,013,135 93 4.58% 285,670,138 110 6.23% 24 114,466,230 63 -30
E2.1 Electrical Works 83,750,351 78 Wiring for 590 flats( Light, Fan, 115,066,566.00 44 seen annexure B for details -29 88,964,126 55 seen annexure - B & C for the details -32
Ac,Telepone , TV, Switch
sockt),Mains from meter to flat
& Basement, stilt
electrification , Tower & Non
Tower area panel DB, Stair
case & terrace lighting &
Earthing of each tower is
considered.
E2.2 Electrical works - switches 8,533,333 8 Swith & Socket , Module plate 0 supply in vendor scope
for all points is supplied by
Client.
E2.3 Lighting Arrestor 1,000,000 1 3 nos of lighting arrestor with 15,682,777.00 6 seen annexure B for details 424,124 seen annexure - I for the details
GI strip is considered
E2.4 Diesel generator sets 4,266,667 4 400 KVA 2 nos of DG Set 113,067,938 44 2000 KVA 5 nos of DG Set 40 5 2 nos - 500 KVA. Seen 1
considered with AMF panel. considered with synchronising annexure - D for further details
8,324,420.00
panel.
Supply of Transformers 15,911,335 6 5 nos - 2500 KVA, 3 nos - 6 4,644,120 3 Transformers 13 nos - 315 3
1250 KVA, 1 no -630 KVA KVA, seen annexure A
Supply & installation of HSD & LPG Works 25,867,314 10 HSD Yard -15,000 lts 10 12,109,440.00 LPG only. Seen annexure G 0
Supply & Installation of MS Fan Box 392,184 0 0 0 0 Included in internal electrical works 0
Provision of Exhaust Fan in Kitchens & Toilets. 2,070,600 2 74,208 0 Provide to service rooms and -2 0 Only Power sockets provided -2
common toilets only. Power socket
provided in flats
0
E3 HVAC Woks 41,391,304 39 1.89% 91,321,413 59 3.35% 21 0 0 -39
E3.1 HVAC Works (Split Unit) 36,731,747 34 2156 no of Split Unit (1.5TR - 79,143,384 42 1423 nos - 1.5 TR, 697 nos - 2.0 TR 8 0 0 Only power sockets proveded. -34
590 Nos, 2 TR ( 2 indoor & 1 Split AC units
outdoor) Multi Split - 584 nos.,
1 TR -590 nos, 1TR - 590 Nos,
0.75 TR - 201Nos) considered.
E3.2 HVAC Works (Basement Ventilation) 3,000,000 3 Mechanical Ventilation for 12,178,029 17 14 0 No basement ventilation -3
basement system conidered.
(55000 CFM -5 nos of fan)
DLS I1070 10 of 14
Davis Langdon and Seah Consulting India Pvt. Ltd.,
COMPARISON OF COSTS
ORCHARD RESIDENCY
HEAD-CONTRACT PACKAGE
SN Cost Element Cost Cost per TCA % age Cost Cost per TCA % age Cost Cost per TCA
INR Per Sft of total cost REMARKS - ORCHARD INR Per Sft of total cost REMARKS DIFFERENCE IN REASON FOR INR Per Sft REMARKS DIFFERENCE IN COST REASON FOR
COST BETWEEN DIFFERENCE BETWEEN ORCHARD & INDU DIFFERENCE
ORCHARD & H1 FORTUNE FIELDS
RESIDENTIAL
E3.4 Core Cutting for HVAC Works 1,659,557 1.55 Core cutting required for Piping - 0 -2 0 0 -2
work.
0 0
E6 Intercom CCTV (Security System Package) 8,000,000 7 B&W video door phones - 600 13,044,251.25 5 seen annexure -2 0 No security system works -7
Nos.EPABX system, telephone
instruments,CCTV - 10 Nos
considered.Boom barrier - 01
No.Fire alarm control panel - 10
Nos, 4 wire link module- 150
Nos, conventional detector with
base - 170 point.Response
indicator not considered.GT
2000 recorder - 08 nos
considered.
E7 Sewage treatment plant 2,500,000 2 400m3 capacity MBBR system 3,544,000.00 1 600 KLD -1 2,712,000 2 500 KLD. Seen annexure F for -1
STP considered. details for equipments only
E8 Elevator works/Lifts 32,395,160 30 20 nos(10 Service+ 10 41 10 persons, 15 stops - 39 nos ; 10 11 36,101,297 22 13 persons - 16 nos ; 6 persons - -8
Passenger) - 10 person persons, 9 stops - 6 nos (Free issue 1no.
capacity , of Schindler make is 106,942,049.00
from client)
considered.
MEP PC sum: 356,180,620 332 16.30% 784,641,338 326 18.47% 2 281,799,173 165 -166
Reinforcement Steel 334,016,348 311 578,277,700 223 -88 included in sub & super -311
structure costing
Total A: 482,510,642 449 22.08% 801,906,235 309 17.50% -141 0 0 -449
Total ( A to H): 2,135,405,441 1,988 97.71% 4,411,143,707 1,722 97.59% -259 1,828,769,763 1,115 -873
Total ( with Contingency Sum ): 2,291,934,441 2,035 100.00% 4,521,422,300 1,765 100.00% -263 1,865,345,159 1,137 -897
DLS I1070 11 of 14
REASONS FOR COST DIFFERENCE BETWEEN COST
LOMA IT PARK AND SIMILAR PROJECT ( INR / SFT )
TOTAL 525