This document provides general notes for an MSGL tank, including:
1. Specify units of pressure as kg/cm2 or bar.
2. Provide dimensions in mm unless otherwise specified.
3. Maintain all distances with respect to centerlines/baselines/equipment top lines.
4. All bolt holes must straddle the principal axis of equipment.
5. Nozzles above DN 50 must be reinforced with pads calculated by vendor.
This document provides general notes for an MSGL tank, including:
1. Specify units of pressure as kg/cm2 or bar.
2. Provide dimensions in mm unless otherwise specified.
3. Maintain all distances with respect to centerlines/baselines/equipment top lines.
4. All bolt holes must straddle the principal axis of equipment.
5. Nozzles above DN 50 must be reinforced with pads calculated by vendor.
This document provides general notes for an MSGL tank, including:
1. Specify units of pressure as kg/cm2 or bar.
2. Provide dimensions in mm unless otherwise specified.
3. Maintain all distances with respect to centerlines/baselines/equipment top lines.
4. All bolt holes must straddle the principal axis of equipment.
5. Nozzles above DN 50 must be reinforced with pads calculated by vendor.
1. Please mention unit of pressure as kg/cm2 g or in bar g.
2. All dimension are in mm. unless otherwise specified. 3. All distance to be maintained w.r.t. Center line/ base line/ t.l. of equipment 4. All bolt holes to straddle the principal axis of equipment 5. All nozzles above DN 50 to be reinforced with pads. RF pad thickness to be calculated by vendor. 6. Nozzle orientation shall be submitted along with the approval of fabrication drawing. 7. Lifting lugs and other fittings to have pad plates of equal thickness and material as base. 8. Hydro test (after lining) as per ASME sce viii div -1 code. 9. Radiography: 100% t joint & 10 % spot for all main seams of inner vessel including nozzle size dn250 (10”nb) and above or nozzle neck thickness 29mm above. 10. Insulation cleat and insulation ring 6mm thick. 11. Cleats welded on jacket. 12. Leg supports in two piece - 6” sch-80 Smls pipe , moc- sa 106 gr.b & (Bottom Leg Adjustable Standard Provided). 13. Ladder support cleat. 14. Platform support cleat 15. Lifting lug 4 Nos on top dish side 16. Tailing lug 4 Nos on bottom dish side 17. Earthling boss ( total 4 Nos . 2 Nos on lug support and 2 Nos on bottom leg support) 18. Cleaning - as per vender standard. 19. Zinc plated yellow Passivated “c “clamp & fasteners 20. For painting Surface: short blasting for cs surface. Primer: one coat of epilux 610 (Gray), dft 25-35 micron/coat. Intermediate: one coat of epilux x 155 high build mio coating (grey), dft 110-125 micron/coat. Final : two coat of eplilux 4 chemical resisting enamel, dft 25-35 micron/coat, shade :ral5002 ( blue ) 21. Provide cap on c-clamp ( Colour -Blue , MOC-Light density poly ethylene ) 22. Nozzle bolts - is 1363/1367 cl .4.6/4 23. Manhole c-clamps- ( j housing bolt -sa 307 gr. b ),( nut- sa 563 gr. b ) 24. Bottom diaphragm ring on jacket -sa240 tp 304 25. Coupling & plug - sa105 (3000 #). 26. SS tray to be provided on top head to protect insulation from dripping. 27. Welding procedure- as per vender standard. 28. Name plate should be screwed to bracket. 29. All process side nozzle covered with MSGL blind and utility side nozzle covered with wooden blank. 30. Gasket for manhole cover : PTFE enveloped caf with SS corrugated ring insert 31. All nozzles, baffles shall be provided with PTFE bushes and with PTFE enveloped gasket. 32. All Flanges as per ANSI b 16.5 150# SORF