Professional Documents
Culture Documents
Jiming Chen
Lutianhua (LTH) Co. Luzhuo, Sichuan, China
Annie Jing
KBR, Houston, USA
L
viable in the long term.
utianhua Co. (LTH) has operated an
ammonia/urea complex in Luzhuo, In June 2001, LTH contracted KBR to perform
Sichuan, China since 1976. The a revamp study so as to determine the feasibility
ammonia plant design was based on seventy’s of achieving objectives of expanding plant
vintage KBR’s conventional technology with a capacity to 1500 MTPD and reducing energy
nameplate capacity of 1000 MTPD. The plant consumption by approximately 0.5 Gcal/MT.
underwent its first revamp based on KBR design This goal of substantial increased capacity with
in 1988 and, with small modifications over the energy reduction presented quite a challenge.
years, the plant capacity was increased to
approximately 1150 MPTD and energy The KBR revamp study started with
consumption reduced to 8.32 Gcal/MT from development of a base case operation based on
9.2 Gcal/MT. the measured plant data. This provided valuable
information on the performance of exchangers,
With the arrival of the twenty-first century, as catalyst, reactors, machinery and columns, etc.
larger capacity and highly energy efficient as well as efficiencies of furnace and rotating
modern plants were built and came online, and equipment. Based on the evaluation of the base
with rising energy prices, it became clear to case operation, the inefficiencies and bottleneck
LTH that a significant step upgrade of their areas of the existing plant for further capacity
The project implementation was kicked off in The existing MEA pretreatment for bulk sulfur
July 2002 as LTH signed a contract with KBR removal downstream of the feed gas compressor
for basic engineering design (BED). In was deleted. The unit was replaced with a ZnO
November 2004, the revamped plant was desulphurization unit and moved to the
commissioned, and after a very short start-up, it upstream of the ammonia plant battery limits for
passed performance test in January 2005. Over bulk sulfur removal. The natural gas supply
the 10 years post revamp, plant operation has pressure to the plant increased 0.7bar. With
been smooth and overall performance has been these changes, the capacity of the existing feed
robust as per the revamp design. gas compressor was adequate for revamp
operation. The original compressor turbine
efficiency had deteriorated over the years, and
Description of Retrofit Feature to produce rated power as required by revamp
conditions, the turbine rotor required
Figure-1 shows the schematic of the plant replacement for capacity and efficiency.
before the revamp. The major process steps
included feed gas compression, desulfurization, Addition of Parallel Air Compressor
primary reformer, air compression, secondary
reformer, waste heat boiler, shift conversion, In the base case operation, the existing air
Benfield CO2 removal system, methanation, compressor was already operating at its upper
syngas compression, synthesis loop with four limit. Three options can be used to increase air
bed quench converter, three-stage refrigeration compression capacity: replace the existing
system, and purge gas recovery unit (PGRU) machine with a new compressor and steam
which includes two-stage Prism hydrogen turbine train to handle the revamp capacity;
recovery as well as HP purge gas ammonia retrofit both existing compressor and turbine for
recovery. All compressors, process air the revamp capacity; or add a new motor driven
compressor, feed gas compressor, syngas compressor train, operating in parallel with the
compressor and refrigerant compressor, are existing machine to handle the additional
steam turbine driven centrifugal machines. capacity of 500MTPD. Since the first two
options provide less operational flexibility and
KBR’s evaluation showed the major bottleneck require significant longer downtime to execute,
areas of the existing plant were: process air and since the first option is much more
compression, CO2 removal system, syngas expensive than the parallel compressor option,
compression, and purge gas recovery unit, while a motor driven integral-geared six-stage
the major inefficiencies lay in furnace, rotating centrifugal parallel air compressor was
equipment, synloop configuration, high pressure incorporated into the revamp scheme.
N
101‐J
AIR N PARALLEL AIR N
COMPRESSOR COMPRESSOR LTS
101C/102C HTS 103‐C
D M
LTS
SULFUR PRIMARY SECONDARY M
HTS N
REMOVAL REFORMER REFORMER
M CONVE R R
FEED GAS CTION METH
COMPRESSOR R 104‐C
114‐C M M
NG
R
1105‐C 1104‐C
M
136‐C
aMDEA CO2
SYN GAS COMPRESSOR M REMOVAL
M M
103‐J 124‐C
M
CO2 PRODUCT
121‐C 120‐C
123‐C1 N
R PRIM
AMMONIA M SEP
CONVERTER
N
MOL‐SIEVE M
PGRU REFRIG. LET
DRYER LEGEND: DOWN
PRISM SYSTEM
N
N: NEW ITEM
R: REPLACED ITEM
M: MODIFIED ITEM NH3 PRODUCT
D: DELETED ITEM