You are on page 1of 12

Sustained Operating Performance of

Lutianhua Ammonia Plant After 50%


Capacity Increase Through Revamp
Lutianhua Co. (LTH) operated a 1000 MTPD of legacy Kellogg conventional design ammonia plant
since 1976. The plant was revamped to a capacity of 1500 MTPD with energy consumption reduction
of 0.47Gcal/MT using KBR technology. The revamped plant was commissioned in 2004, and after a
very short startup, it passed the performance test, achieving design capacity and energy consumption.
In years post revamp startup, the plant has maintained performance and smooth operation, and has
helped LTH stay competitive in the fierce natural gas based ammonia industry in China. The paper
describes the revamp technology used and compares performance before and post revamp.

Jiming Chen
Lutianhua (LTH) Co. Luzhuo, Sichuan, China

Annie Jing
KBR, Houston, USA

Introduction existing plant in scale and efficiency had to be


made to stay competitive and economically

L
viable in the long term.
utianhua Co. (LTH) has operated an
ammonia/urea complex in Luzhuo, In June 2001, LTH contracted KBR to perform
Sichuan, China since 1976. The a revamp study so as to determine the feasibility
ammonia plant design was based on seventy’s of achieving objectives of expanding plant
vintage KBR’s conventional technology with a capacity to 1500 MTPD and reducing energy
nameplate capacity of 1000 MTPD. The plant consumption by approximately 0.5 Gcal/MT.
underwent its first revamp based on KBR design This goal of substantial increased capacity with
in 1988 and, with small modifications over the energy reduction presented quite a challenge.
years, the plant capacity was increased to
approximately 1150 MPTD and energy The KBR revamp study started with
consumption reduced to 8.32 Gcal/MT from development of a base case operation based on
9.2 Gcal/MT. the measured plant data. This provided valuable
information on the performance of exchangers,
With the arrival of the twenty-first century, as catalyst, reactors, machinery and columns, etc.
larger capacity and highly energy efficient as well as efficiencies of furnace and rotating
modern plants were built and came online, and equipment. Based on the evaluation of the base
with rising energy prices, it became clear to case operation, the inefficiencies and bottleneck
LTH that a significant step upgrade of their areas of the existing plant for further capacity

2014 137 AMMONIA TECHNICAL MANUAL


expansion and energy reduction were identified drops, insufficient waste heat recovery, high
and addressed in KBR’s revamp proposal inert level, and low hydrogen recovery.
submitted to LTH in October 2001, with
budgetary cost estimates for proposed revamp Figure-2 represents the revamp schematic. The
options based on USGC basis. After a detailed revamp scheme was tailor made for LTH by
risk and economic analysis based on costs in KBR for cost effectiveness as well as with due
China, and careful evaluation and survey of the consideration for reliability, operability and
Chinese market and capabilities of equipment maintainability after revamp. The major revamp
manufacturers, Chinese detailed engineering features by area are as follows:
contractors and construction companies, LTH
decided to proceed with the revamp project. Natural Gas Pretreatment & Compression

The project implementation was kicked off in The existing MEA pretreatment for bulk sulfur
July 2002 as LTH signed a contract with KBR removal downstream of the feed gas compressor
for basic engineering design (BED). In was deleted. The unit was replaced with a ZnO
November 2004, the revamped plant was desulphurization unit and moved to the
commissioned, and after a very short start-up, it upstream of the ammonia plant battery limits for
passed performance test in January 2005. Over bulk sulfur removal. The natural gas supply
the 10 years post revamp, plant operation has pressure to the plant increased 0.7bar. With
been smooth and overall performance has been these changes, the capacity of the existing feed
robust as per the revamp design. gas compressor was adequate for revamp
operation. The original compressor turbine
efficiency had deteriorated over the years, and
Description of Retrofit Feature to produce rated power as required by revamp
conditions, the turbine rotor required
Figure-1 shows the schematic of the plant replacement for capacity and efficiency.
before the revamp. The major process steps
included feed gas compression, desulfurization, Addition of Parallel Air Compressor
primary reformer, air compression, secondary
reformer, waste heat boiler, shift conversion, In the base case operation, the existing air
Benfield CO2 removal system, methanation, compressor was already operating at its upper
syngas compression, synthesis loop with four limit. Three options can be used to increase air
bed quench converter, three-stage refrigeration compression capacity: replace the existing
system, and purge gas recovery unit (PGRU) machine with a new compressor and steam
which includes two-stage Prism hydrogen turbine train to handle the revamp capacity;
recovery as well as HP purge gas ammonia retrofit both existing compressor and turbine for
recovery. All compressors, process air the revamp capacity; or add a new motor driven
compressor, feed gas compressor, syngas compressor train, operating in parallel with the
compressor and refrigerant compressor, are existing machine to handle the additional
steam turbine driven centrifugal machines. capacity of 500MTPD. Since the first two
options provide less operational flexibility and
KBR’s evaluation showed the major bottleneck require significant longer downtime to execute,
areas of the existing plant were: process air and since the first option is much more
compression, CO2 removal system, syngas expensive than the parallel compressor option,
compression, and purge gas recovery unit, while a motor driven integral-geared six-stage
the major inefficiencies lay in furnace, rotating centrifugal parallel air compressor was
equipment, synloop configuration, high pressure incorporated into the revamp scheme.

AMMONIA TECHNICAL MANUAL 138 2014


Primary Reformer Modification reactor were modified to use an axial-radial
basket.
The radiant section of the primary reformer was
The HTS effluent and methanator feed
upgraded with thinner wall HP Modified tubes
exchanger was found to be inadequate for
with an ID 89mm in 1997, and the existing
revamp operation and was required to be
catalyst tubes were in good condition. For the
replaced for capacity. Replacing this exchanger
revamp operation, the catalyst volume is
also reduces pressure drop since both sides of
sufficient and the tube design temperature
the exchanger are process gas.
margin has been maintained. Additional
modifications of the arch burners and A parallel LTS converter was added to handle
convection section were needed to increase 50% of the revamp flow and also to reduce the
overall thermal efficiency and meet revamp pressure drop. Additionally, a quench drum was
duty. installed upstream of LTS converters for inlet
temperature control.
The modifications incorporated include:
 Replacement of the existing arch burners to CO2 Removal System Modification
meet fuel heat liberation requirement
Increasing plant capacity to 1500 MTPD results
 Replacement of the convection coils which in a commensurate increase in the throughput
included mixed-feed preheat, process air for the CO2 removal system. Because the CO2
preheat, steam superheat, and feed preheat loading in the rich solution was already close to
coils for more heat transfer area and lower the upper limit, any increase in acid gas removal
pressure drop, as well as coil material must be accompanied by replacing activator and
upgrade. increasing solution circulation or solvent swap.
 Replacement of the existing combustion air After careful evaluation of three upgrade
preheater with a larger and more efficient options (replace existing Benfield activator of
plate type exchanger since the existing DEA with ACT-1; swap to two-stage aMDEA;
Ljungstrom (rotary) type preheater was not or to single stage aMDEA system), LTH elected
only limited in surface area, but also a to implement the option of swapping to BASF’s
source of leakage and inefficiency. single stage aMDEA system in consideration of
reduction in environmental impact (pollution
 Addition of pilots and flame scanner for elimination), easier control of solution
auxiliary boiler burners for safety. chemistry, startup and operation, as well as
lower Capex.
Secondary Reformer Modification
The major changes for the conversion to single
The top section of the existing secondary
stage aMDEA for revamp operation are:
reformer was replaced with a new burner
(mixer) for increased revamp throughput, and
 Replacement of Benfield solution with
the catalyst bed volume reduced or short loaded
50% aMDEA solution.
to lower pressure drop.
 The existing lean and semi-lean solution
Shift Conversion Modification pumps were reused as cold lean solution
pumps for the lean absorber, and warm
HTS catalyst volume is sufficient for revamp lean solution pumps for the bulk
operation, but to minimize frontend pressure absorber respectively, with modification
drop due to increased flow, the internals of HTS of pump seals for aMDEA. The existing
solution pumps could not provide the

2014 139 AMMONIA TECHNICAL MANUAL


head required for the revamp operation cold lean solution for the lean absorber
due to significant reduction (about 25%) section and another for warm lean
in solution density of aMDEA in solution to the bulk absorber section.
comparison with Benfield, so new
 A new plate and frame lean solution and
booster pumps were added upstream of
semi-lean solution exchanger was added
the existing pumps.
to recover the heat from lean solution
 New semi-lean solution pumps for exiting the stripper.
circulating solution from the bottom of
 For the system water balance, the
the LP flash column to the top of the
process feed temperature to the absorber
CO2 Stripper were added.
is also much colder than the Benfield
 The existing hydraulic turbine internals system. To recover the heat and cool the
were modified with new rotor and seal feed, two coolers were added - one for
plan. preheating BFW and another CW trim
cooler to control the feed temperature.
 The existing LP steam generator
(previously used for boiling stripper  The existing stripper overhead condenser
overhead condensate to generate LP was more than sufficient for revamp
steam for Benfield flash drum ejectors) operation. To reduce CW flow, a portion
was modified with a new shell to operate of the tubes were plugged.
in parallel with existing reboiler to
 All new exchangers added in the system
provide the total revamp CO2 stripper
were constructed of stainless steel (SS)
reboiling duty.
on the solution side. New solution pump
 The existing absorber and stripper internals were also SS. New semi-lean
columns were reused with minimum solution lines were SS and existing
internal modifications. For the absorber, carbon steel (CS) solution lines replaced
the existing packing was sufficient for with SS lines, if velocity exceeded 2m/s.
the revamp operation, but vortex
breaking packing was added in the Methanation Section Modification
absorber sump to reduce gas
entrainment, and the lean solution inlet Catalyst volume of the methanator is sufficient
distributer was replaced. For the stripper for revamp operation. Modifications were made
column, the flashing feed inlet device for on its feed and effluent exchangers. The
LP flash and stripper were replaced; the methanator feed/syngas exchanger and
packing for the stripper section was methanator effluent/BFW preheater were
replaced with high performance packing replaced with new ones, while the methanator
to maintain the same packing as existing; effluent/demineralized water preheater and
besides internals such as liquid water cooler were piped to operate in parallel to
distributers and partitions were added lower pressure drop.
and/or modified.
 In the aMDEA system, the absorber Synthesis Gas Compression Modification
operates with much cooler solution feeds
(solution to lean section is more than 20 As capacity increases to 1,500 MTPD, the
ºC colder and to bulk section more than make-up gas flow to the Synthesis Gas
50 ºC colder in comparison with Compressor (103-J) increases more than 30%
Benfield). To meet this requirement, two (mass) over the base case flow. In order to
new solution coolers were added, one for

AMMONIA TECHNICAL MANUAL 140 2014


minimize the front-end pressure drop increases oxides, so there is no need to pass
caused by higher flow, in the revamp scheme through an ammonia chilling cycle to
remove them. As a result, the converter
we have optimized and incorporated physical
pressure is higher; loop pressure drop
changes in piping, exchangers, and reactor to lower; power consumption of both
compensate. Still volumetric flow increased syngas and refrigerant compressors
over 40% at the compressor suction. The lower due to lower circulation rate,
existing compressor could not handle such a lower loop delta-p, and lower
large flow increment and higher-flow impellers refrigeration duty; ammonia conversion
were required, which entailed internal parts higher and catalyst life longer due to
lower ammonia concentration and very
replacement including rotors and bundles and
low level of water and CO2 (poisons to
new diaphragm couplings and coupling guards catalyst) concentration in the converter
for both LP and HP casings. The steam turbine feed.
for the compressor was upgraded in 1988,
 Retrofitted converter basket to increase
having the required capacity but efficiency was capacity and lower pressure drop. The
much lower than the original design. An basket retrofit consisted of replacing
overhaul to replace wear and tear to improve existing internals of 4 axial quench beds
turbine efficiency was required. with a design having 3 radial-flow beds
with quench and inter-coolers.
Addition of New Mol-Sieve Dryer System  Replaced the converter effluent/BFW
preheater as well as the converter exit
A new syngas drying system was added to dry
line for increased capacity and higher
the fresh makeup gas to the synloop in order to
temperature, as well as heat recovery
upgrade the existing wet loop configuration to a
enhancement. Converter effluent water
dry loop design. The dryer system consisted of
cooler was also modified for capacity,
two syngas dryers, two strainers, a regeneration
pressure drop as well as tube material
dryer as well as a regeneration heater. The
upgrade.
syngas dryer contains solid desiccant sized to
remove residual carbon dioxide and water in the
PGRU Modification
fresh makeup syngas in a 12-hour drying cycle.
Waste gas from the PGRU is used as
regeneration gas after being dried in the  To handle the increased purge gas flow,
regeneration dryer. the internals of the existing HP ammonia
scrubber were modified.
Synloop Modifications  The existing hydrogen recovery (Prism)
system which consisted of a two-stage
 Repiped synloop from existing “wet hydrogen recovery unit was retrofitted to
loop” to “dry loop” to increase synloop accommodate increased flow and to
efficiency. Refer to sketch figure-1 achieve hydrogen recovery efficiency of
showing existing wet loop and figure-2 95%, existing P0 membranes were
the dry loop configuration. In the “dry replaced with P2, and additional new
loop”, the syngas from the compressor membranes added.
discharge is directly fed to the converter
 New LP Ammonia scrubber system was
after heat exchange with the converter
added to recovered ammonia from low
effluent. After mol-sieve drying, the
fresh makeup gas is dry and free from

2014 141 AMMONIA TECHNICAL MANUAL


pressure flash gases to lower NOx in the To efficiently manage such a large and
reformer flue gas. complicated revamp project, the LTH revamp
project management team distributed
HP Process Condensate Recovery Unit
responsibility by sections. Each section had a
Modification
lead team responsible for their area engineering
and safety reviews; preparation of operation
To handle the increased load, the internals of the
procedures based on licenser, DEC and
existing condensate scrubber were replaced, and
manufacturer inputs; operator training
additional condensate pump and cooler were
(extensive class room and plant site training
added in the system.
were conducted to familiarize operators with
operation changes brought by the revamp);
Steam System and Cooling Water System
mechanical completion checkup; audits before
feed-in; as well as commissioning and startup
The high pressure steam generation from the
operations.
steam drum was increased about 10% over the
base case and HP steam superheat temperature
Table-1 Project Milestone
increased to improve plant efficiency. The
system was checked, verifying that no Date  Milestones 
modification besides a few turbine 5‐Jul‐02  Effective Date of the Contract 
modifications as mentioned above were Project Kick Off Meeting with LTH,  
required. 16‐Jul‐02 
KBR and DEC (Chengda) 
14‐Oct‐02  KBR Issued Process Design Package 
Cooling water circulation increased about 20% 18‐Dec‐02  KBR Issued BED for Client Approval 
over the base case, and a new cooling tower cell
5‐Mar‐03  KBR Issued Final BED 
and additional pumps were added in OSBL for
the increased capacity. 30‐Jul‐03  Construction Startup 
Completion of Commissioning New 
16‐Sep‐04 
Other Modifications Parallel Process Air Compressor  
Mechanical Completion of the New 
30‐Sep‐04 
A couple of new separators were added and Mol‐Sieve Dryer System  
several existing separators were modified 17‐Oct‐04  Plant Shutdown 
internally for increased throughput and Completion Inspection and 
separation efficiency. Safety relief systems, 8‐Nov‐04  Maintenance of Steam System and 
instrumentation, piping systems were checked, Start Steam Blowing 
modified, and upgraded as required.
Completion of Furnace Dry‐out  and 
19‐Nov‐04 
Start of Commissioning 
Revamp Project Milestones Plant Restart, Feed‐in Primary 
24‐Nov‐04 
Reformer 
At the beginning of the project, LTH formed a
dedicated revamp project management team Completion of Cleaning of CO2 
responsible for project execution including 24‐Nov‐04  Removal System and Start 
project cost, overall schedule, and quality Circulation of aMDEA Solution 
controls; equipment and material procurement; Completion of Synloop Repiping 
construction supervision; and safety throughout 26‐Nov‐04  Including Converter Basket 
project execution. Installation. 
27‐Nov‐04  Start of Synthesis Compressor  
2‐Dec‐04  Ammonia Product to OSBL Tank 

AMMONIA TECHNICAL MANUAL 142 2014


Date  Milestones  Operation Experience
Ammonia Production Reached 97% 
20‐Dec‐04  The success of any revamp project is measured
of Capacity 
in how the plant operates after it is startup
Completion and Pass   compared to before revamp. Tables 3 to 6 below
20‐Jan‐05 
Performance Test Run 
provide comparisons of post revamp operation
with before revamp.
With diligent planning, safety focus and efforts
of LTH revamp project team, KBR, engineering Table-3 Overall Capacity & Spec. Energy
and construction contractors, the LTH revamp
Before Post
project was executed with zero recordable safety
Revamp Revamp
incidents during construction, commissioning,
and startup. NH3 Production, MTPD 1150 1500
NG Feed & Fuel
(Gcal/MT) 8.59 8.07
The revamp project was completed within
budgeted cost; however, the 2003 severe acute Electrical Power Import-
Steam Export+CW+DW
respiratory syndrome (SARS) epidemic in
Makeup (Gcal/MT) (0.27) (0.22)
China, caused about four months delay.
Specific Energy Gcal/MT 8.32 7.85
The revamp startup was short and successful.
Table-4 Frontend Operation Comparison
The LTH revamp project achieved an ammonia-
to-ammonia period of only 45 days. In Before Post
comparison with other Chinese plant revamps of Frontend Revamp Revamp
similar revamp scope, this was the shortest span. NG Feed (Gcal/MT) 5.3 5.27
Steam to Carbon Ratio ~3.3 ~3.2
Table-2 below provides the Performance Test
130% of
Results. During Jan 17 to Jan 20 of 2005 in the
Process air rate, (mass) base base
72-hour performance test run, the average
capacity reached was 1510 MTPD. The CO2 Primary Reformer
production and energy consumption also all met ~115%
Radiant Duty base of base
the design and guarantee.
Tube outlet temp., C >800 <795
Table-2: Performace Test Run Results Anchor pres., bar(a) 32 34
Test Run Guaranteed <60% of
Day1 Day2 Day3 Avg. Value Auxiboiler Duty base base
NH3 Product Quantity
Metric Ton Per Day
1511 1509 1509 1510 1500 Stack Temp, C >170 <120
NH3 Product Quality
Furnace efficiency ~88% >92%
Ammonia wt% 99.99 99.99 99.99 99.99 ≥99.9
Water, wt% 0.01 0.01 0.01 0.01 ≤0.1 Secondary Reformer
Oil, ppmw <5 <5 <5 <5 <5
CO2 Product Quantity Outlet temp, C <990 <995
1786 1766 1766 1773 1765
Metric Ton Per Day
CO2 Product Quality
CO2 Removal
CO2 vol% dry 99.18 99.14 99.14 99.15 ≥99 CO2 production ~1360 >1766
Pressure, Mpa(A) 0.06 0.06 0.06 0.06 ≥0.06
Temp. deg. C 36.5 35.5 36.3 36.1 <40 CO2 product purity ~98.6% >99%
Energy Consumption
Frontend Pres. Drop
Natural Gas Feed&Fuel 8.062 8.074 8.071 8.069
Electrical Power Import- 102-J discharger to
Steam Export+CW+DW (0.224) (0.219) (0.203) (0.215)
Makeup
103-J suction, bar ~14 ~17
Eng. Consump., Gcal/MT 7.838 7.855 7.868 7.854 7.865

2014 143 AMMONIA TECHNICAL MANUAL


Table-5 Backend Operation Comparison conditions. Per LTH operators, post revamp
operation has been much easier and more stable
Before Post
than before the revamp.
Backend Revamp Revamp
Synthesis Section Since November 2004, the revamped plant has
103-J Suction press., maintained performance. Table-7 below lists the
bar >26 >25 ammonia production.
Make-up gas flow, ~140% of
volume base base Table-7 Plant Capacity
Loop press. drop, bar <11 <10
Recycle syngas Max Daily Annual 
Production Production 
Pressure, bar ~136 >140 (MTPD) (MTPY) 
103-J Discharge
Before Revamp 1150 350,000 
Flow rate, kNm3/hr ~660 ~600
Post Revamp   
Pressure, bar ~147 ~150
2005 1510 495,000 
Converter inlet
2006 1532 442,125 
H2 to N2 ratio ~2.85 ~3
2007 1535 444,079 
NH3 content, mol% >1.8 <1.3
2008 1513 418,515 
Inert CH4+Ar, mol% ~11 ~7
2009 1505 392,204 
Converter outlet
2010 1522 374,730 
Temperature, C <290 >370
2011 1506 313,392 
NH3 Rise, mol% ~12 ~16
2012 1458 293,241 
Temp. Rise, C ~174 > 230
2013 1550 428,171 
HP loop purge
Rate, kNm3/h 10 ~20 While the results are encouraging, the post
H2 Recovery % ~70 95 revamp plant should have been able to reach
much higher annual capacity if there were no
Table-6 Compressor Operation Comparison reduction in natural gas supply and government
Before Post as well as NG supplier mandated annual
shutdowns for saving natural gas for other
Compressors Revamp Revamp
industries or domestic uses due to natural gas
Air Compressor/Driver (MW) (MW)
curtailment in China.
Existing Comp/turbine ~8.3 ~7.2
New parallel comp. ~3.9 The revamp plant also achieved improvements
130% of in SH&E and reduced environmental impact.
Feed Gas Comp/turbine base base Before the revamp, there were hazardous
Syngas Comp/turbine ~15 ~17.5 discharges from CO2 removal due to the
Benfield system use of vanadium pentoxide for
Refri. Comp/turbine ~7.6 ~7.1
corrosion inhibitor. The aMDEA system does
As can be seen from the comparisons post not use a corrosion inhibitor, and there are
revamp, the plant capacity, energy and virtually no effluent streams with proper
efficiency improved significantly. The plant maintenance of water balance of the system.
operability and reliability also improved thanks With upgraded monitoring, controlling and
to modification and upgrades to equipment. The instrumentation systems, and replacement of
unchanged equipment were operated at lower wear and tear parts of equipment as well as
load than the base case or within their design

AMMONIA TECHNICAL MANUAL 144 2014


material upgrades, the plant operational safety the violent churning and slugging of the two-
improved. phase solution entering the column, with a large
amount of vapor release from solution that
Although the plant has successfully achieved
exerted high shear stresses and mechanical
more than revamp design capacity, the operation
forces on the internals. LTH followed KBR’s
did encounter a few problems especially during
recommendation to repair and strengthen the
the first two years of post-revamp operation:
flash gallery and inlet baffle, wash trays, and
demister pad, and add reinforcement for
Combustion Air Preheater High Pressure Drop
supporting beams.
Underperformance of the combustion air Severe corrosion was found in the CS shell of
preheater was observed during the initial phase the LP flash overhead condenser and separator.
of post revamp operation, while the air side Corrosion/erosion pits were found on the inner
pressure drop across the preheater was much wall of the absorber just below the feed gas inlet
higher than design. After several years of nozzle and at the elbow of the return line to the
operation, the pressure drop and the internal stripper from the stripper reboiler as well as the
leakage increased. When the plant operated CS shell of the reboiler (1105-C). Scale was
close to full rate or higher, vibration of the found covering the SS tubes of the stripper
existing ID and FD fans became severe due to reboilers as a dark colored layer 0.2~0.3mm in
operating near their upper capacity limit. To thickness, and similar scale was also found in
alleviate the bottleneck caused by the Preheater, the bottom bed of stripper packing. LTH lab
LTH installed a small secondhand ID fan to help analysis showed the scale contains 70% Fe2O3.
handling about 5% of the load. In 2013, LTH It was concluded that the cause of corrosion was
replaced the preheater with a new one from the due to CS in contact with very corrosive wet
same Chinese vendor as the previous one, but a CO2 in the LP flash overhead equipment.
similar high pressure drop problem was Erosion corrosion found in other areas was
encountered again. LTH is working with the likely due to flow turbulence. For the LP flash
vendor to a find solution to the problem. overhead system, LTH replaced the equipment
with new ones made of SS per the licenser
Problem with aMDEA CO2 Removal System requirement. The corrosion pits on the absorber
wall and reboiler shell were removed by
In the initial phase of post revamp operation, grinding. Per BASF, scale could have been
LTH encountered the following problems: formed due to insufficient startup cleaning, plus
foaming, damage of internals of the stripper LP insufficient filtration, as well as not operating
flashing top section, corrosion and erosion on with corrosion inhibitors. Under these
CS lines & equipment, as well as scaling. conditions, it was found possible to convert the
old corrosion protection layer into a Fe2O3 layer.
LTH experienced frequent foaming. After
The scale was removed by hydro-blasting.
inspection of the system, it was concluded that
the major cause of foaming was due to To prevent reoccurring of the corrosion
insufficient filtration. LTH replaced the filter problem, following BASF recommendation,
cartridges as per KBR design specification. LTH passivated the system to build a corrosion
protective layer before introduction of process
Severe internal damage was found on the
gas into the system. This included 72 hours of
stripper LP flash top section, the rich solution
static passivation for the absorber and 36 hours
inlet flashing gallery, top wash trays and
for the stripper, followed by more than 24 hours
demister pads were ripped off, bent and
of circulation passivation.
deformed. Analyzing the operation, it was
concluded that the damage likely was caused by

2014 145 AMMONIA TECHNICAL MANUAL


After a two- year learning curve, LTH operators less than two years. The LTH ammonia plant
said that the system is easier to operate than the has maintained consistent performance over the
previous system, as they gained more past 10 years post revamp operation. Operation
experience. With better maintenance of the has been very smooth, and overall performance
solvent, activator and other chemical was robust as per the revamp design criteria.
concentrations in the solution, and monitoring
of the solution circulation rate, and better Acknowledgments
filtration, the system operated smoothly. The
corrosion/erosion problem is also diminished to Authors acknowledge LTH and KBR
an acceptable level. management for their leadership in bringing
such a complicated revamp project to successful
reality. Further, contributions of the specialists
Conclusion and engineering team members of both LTH
Lutianhua’s decision to revamp their plant in and KBR as well as the contributions of the
2001 was very timely and prudent, as it helped operations, maintenance, construction and
them stay competitive in the harsh conditions related suppliers are highly appreciated and
prevalent in China’s natural gas based ammonia acknowledged.
industry. LTH’s revamp project has been
implemented successfully with payback period

An Elevated View of Lutianhua Overall Complex

AMMONIA TECHNICAL MANUAL 146 2014


Figure-1: Flow Sheet before Revamp

2014 147 AMMONIA TECHNICAL MANUAL


Figure-2: Flow Sheet Post Revamp

AIR REVAMP ‐ 1500MTPD 


AIR

N
101‐J
AIR  N PARALLEL AIR  N
COMPRESSOR COMPRESSOR LTS
101C/102C HTS 103‐C
D M
LTS
SULFUR  PRIMARY  SECONDARY  M
HTS N
REMOVAL REFORMER REFORMER

M CONVE R R
FEED GAS  CTION METH
COMPRESSOR R 104‐C
114‐C M M
NG
R
1105‐C 1104‐C
M
136‐C
aMDEA CO2 
SYN GAS COMPRESSOR M REMOVAL
M M
103‐J 124‐C
M
CO2 PRODUCT

121‐C 120‐C
123‐C1 N
R PRIM 
AMMONIA M SEP
CONVERTER
N

MOL‐SIEVE  M
PGRU REFRIG.  LET
DRYER LEGEND: DOWN
PRISM SYSTEM
N
N: NEW ITEM
R: REPLACED ITEM
M: MODIFIED ITEM NH3 PRODUCT
D:  DELETED ITEM

AMMONIA TECHNICAL MANUAL 148 2014

You might also like