1. Corrective actions were taken to address deficiencies found in NDT operations and radiation safety assessments, including purchasing additional examination specimens and equipment, revising training programs, and updating procedures and documentation.
2. Key updates included revising the technician certification process, question banks, and individual files, as well as designing storage rooms, updating equipment calibration schedules, and amending the bunker license.
3. Radiation safety improvements involved appointing named RSOs, updating required procedures and documentation like source inventories and logs, and ensuring compliance with regulatory reporting requirements.
1. Corrective actions were taken to address deficiencies found in NDT operations and radiation safety assessments, including purchasing additional examination specimens and equipment, revising training programs, and updating procedures and documentation.
2. Key updates included revising the technician certification process, question banks, and individual files, as well as designing storage rooms, updating equipment calibration schedules, and amending the bunker license.
3. Radiation safety improvements involved appointing named RSOs, updating required procedures and documentation like source inventories and logs, and ensuring compliance with regulatory reporting requirements.
1. Corrective actions were taken to address deficiencies found in NDT operations and radiation safety assessments, including purchasing additional examination specimens and equipment, revising training programs, and updating procedures and documentation.
2. Key updates included revising the technician certification process, question banks, and individual files, as well as designing storage rooms, updating equipment calibration schedules, and amending the bunker license.
3. Radiation safety improvements involved appointing named RSOs, updating required procedures and documentation like source inventories and logs, and ensuring compliance with regulatory reporting requirements.
NDT Operations Assessment Part Sufficient NDT (UT/RT/PT/MT ) Dedicated examination specimens shall be available with sufficient examination specimen purchased. 1 number to educate and test NDT technicians. Attachment 01 shows the Invoice and Picture of Specimen. Calibration Schedule updated. 2 NDT Equipment calibration shall be updated Attachment 02 shows the Sample of Calibration Certificates Theory Training Room & Practical Training Room designed to train the Training Room Shall be designed to accommodate a sufficient number 3 sufficient number of technicians. of technicians Attachment 03 shows the pictures of training Room All the technicians were certified using the new specimen. Attachment 04 & 05 4 All technicians shall be certified using new specimens the Technicians certification summary list and sample Practical examination paper. Bank of Questions revised for all NDT 5 Bank of questions for each NDT methods need to be revised methods. Sample of Question bank Attachment 06 for (Set 1 to Set 4) Storage room designed and maintained Storage room shall be well maintained for keeping all used and unused for all NDT used equipment’s and 6 equipment unused equipment. Attachment 07 shows the pictures of storage room Individual File for all the technicians are File for each technician shall be prepared including all the required prepared including all the necessary 7 information such as training, history, medical reports, examination documents. Attachment 08 shows the papers,… etc. sample file of technician Radiography film processing designed with drainage system and made agreement with external parties for 8 Radiography film processing room shall have suitable draining system disposal of chemicals. Attachment 09 shows the drainage disposal system photos and the agreement. Additional one Densitometer purchased and having 2 densitometer as a 9 Minimum number of densitometers shall be 2 devices minimum. Attachment 10 shows the picture & Invoice. Radiation Safety Assessment Part Bunker Location updated to Jubail in Bunker license shall be amended to indicate correct bunker location is in 1 Radiation Protection License. Jubail not in Dammam Attachment 11 shows the document. Appointment Letter of Main & Backup IQ management shall appoint the main and backup RSO by names updated through letter specifying their 2 through a letter specifying their functions and duties duties. Attachment 12 shows the document Radiation Safety procedure updated and signed by Main & Backup RSO and Radiation safety procedure signed by main and Backup RSO and 3 approved by General Manager. acknowledged by facility manager Attachment 13 shows the updated procedure. Radiation Source Inventory prepared Radiation sources inventory list shall be prepared monthly basis using 4 using KACARE Form. Attachment 14 KACARE form shows the required document. Radiation Source Log In-Out updated Radiation sources log In/out file lacking of source information such as with all the lacking information 5 source serial number, the log file shall include all information related to mentioned in the Audit findings. source, projector, destination, RT crew, issue/receiver etc.,. Attachment 15 shows the updated Radiation source Log In-Out.
TLD records maintain monthly now and
TLD Records shall be maintained monthly and reported to NRRC will report to NRRC quarterly. 6 quarterly Attachment 16 Shows the Monthly TLD report October, November & December.
Bunker Survey Report updated with
Bunker survey report does not include controlled/supervised areas and controlled & supervised areas and also 7 the dose rate limits. Survey report shall indicate all restricted areas and mentioned the dose rates in each points. dose allowed dose limits in each point Attachment 17 shows the updated Survey Report Additional 2 Crank units purchased and There are 2 projector crank units only which is not enough. Minimum now 4 crank unit available as a 8 number of crank units shall be 4 units minimum. Attachment 18 shows the Invoice & pictures of Crank Unit Emergency contact info updated inside Emergency contact info shall be updated and posted outside and inside 9 & outside bunker. Attachment 19 shows the radiation bunker. the pictures Two Area Monitor installed permanently There is no radiation area monitor installed inside the bunker. Two in the controlled & supervised areas. 10 monitors shall be installed permanently in the controlled and supervised Attachment 20 shows the pictures of areas. installed area monitor Bunker gate damage was repaired completely and in addition small gate Bunker External Gate is damaged which is critical security issue. Bunker 11 also arranged for easy access. area shall be well controlled and secured. Attachment 21 shows the pictures of Bunker gate Surveillance camera linked with RSO & Surveillance cameras inside the bunker shall be linked to external PC or GM mobile. They have live access any 12 mobiles to help in monitoring and securing the storage of the time using the application NVSEE. radioactive materials. Attachment 22 shows the sample picture of accessing Storage room maintained and arranged Storage room shall be well maintained and designated for projectors for projectors & emergency Kit. 13 accessories and emergency equipment. Attachment 23 shows the pictures of the arrangement.
Radiation source box installed with lead
Radiation sources transportation boxes installed in the vehicles shall be sheet to minimize the radiation 14 contained with lead sheets to minimize the radiation exposure during exposure. Attachment 24 shows the the public transportation. pictures of fixed lead sheet in source box
XS.NO. Assessment Findings Corrective Action Record
NDT Operations Asssessment Part Sufficient NDT (UT/RT/PT/MT Dedicated examination specimens shall be available with sufficeint examination specimen purchas 1 number to educate and test NDT technicians. Attachment 01 shows the Invoice Picture of Speciemen. Calibration Schedule updated 2 NDT Equipment calibration shall be updated Attachment 02 shows the Samp Calibration Certificates Thoery Training Room & Practi Training Room desgined to train Training Room Shall be desigined to accommodate a sufficient number 3 suffficent number of technician of techincians Attachment 03 shows the pictur training Room
All the technicians were certified
the new specimen. Attachment 04 4 All technicians shall be certified using new specimens the Technicians certification suma and sample Practical examination
Bank of Questions revised for all a
5 Bank of questions for rach NDt methods need to be revised methods. Sample of Question b Attachment 06 for (Set 1 to Se Storage room designed and maint Storage room shall be well maintained for keeping all used and unsed for all NDT used equipments and u 6 equipment equipments. Attachment 07 show pictures of storage room Individual File for all the technicia File for each technician shall be prepared including all the required prepared including all the neces 7 information such as training, history, medical reports, examination documents. Attachment 08 show papers,… etc sample file of technician Radiography film processing desi with drainage system and mad agreement with external parties 8 Radiography film processing room shall have suitable draining system disposal of chemicals. Attachmen shows the drainage disposal sys photos and the agreement. Additional one Desnitometer purc and having 2 densitometer as 9 Minimum number of densitometers shall be 2 devices minimum. Attachment 10 shows picture & Invoice. Radiation Safety Assessment Part Bunker Location updated to Juba Bunker license shall be amended to indicate correct bunker location is in 1 Radiation Protection License Jubail not in Dammam Attachment 11 shows the docum Appointment Letter of Main & Ba IQ management shall appoint the main and backup RSO by nmaes updated through letter specifying 2 through a letter specifying their functions and duties duties. Attachment 12 shows t document Radiation Safety procedure update signed by Main & Backup RSO a Radiation safety procedure signed by main and Backup RSO and 3 approved by General Manage acknowledged by facility manager Attachment 13 shows the upda procedure. Radiation Source Inventory prep Radiation sources inventory list shall be prepared monthly basis using 4 using KACARE Form. Attachmen KACARE form shows the required documen Radiation Source Log In-Out upd Radiation sources log In/out file lacking of source information such as with all the lacking informatio 5 osurce serial number, the log file shall include all information related to mentioned in the Audit finding source, projector, destination, RT crew, issue/receiver etc,. Attachement 15 shows the upda Radiation source Log In-Out. TLD records maintaing monthly no will report to NRRC quartely TLD Records shall be maintained monthly and reported to NRRC 6 Attachment 16 Shows the Month quarterly report october, November & Decemeber. Bunker Survey Report updated w Bunker survey report does not include controlled/supervised areas and controlled & supervised areas and 7 the dose rate limits. Survey report shall indicate all restricted areas and mentioned the dose rates in each p dose allowed dose limits in each point Attachment 17 shows the upda Survey Report Additional 2 Crank units purchase There are 2 projector crank units only which is not enough. Minimum now 4 crank unit available as 8 number of crank units shall be 4 units minimum. Attachment 18 shows Invoice & pictures of Crank Un Emergency contact info updated i Emergency contact info shall be updated and posted outised and inside 9 & outside bunker. Attachment 19 the radiation bunker. the pictures Two Area Monitor installedperma There is no radiation area monitor isntalled inside the bunker. Two in the controlled & supervised ar 10 monitors shall be installed permantely in the controlled and supervised Attachment 20 shows the pictur areas. installed area monitor Bunker gate damage was repai completely and in addition small Bunker External Gate is damaged which is critical security issue. Bunker 11 also arranged for easy access area shall be well controlled and secured. Attachment 21 shows the pictur Bunker gate Surveillance camera linked with R Surveillence camaeras inside the bunker shall be linked to external PC or GM mobile. They have live acces 12 mobiles to help in monitoring and securing the storage of the time using the application NVS radioactive materials. Attahcment 22 shows the sam picture of accessing Storage room maintained and arra Storage room shall be well maitained and designated for projectors for projectors & emergecny K 13 accessories and emergency equipment. Attachment 23 shows the pictures arragnement.
Radiation source box installed wit
Radiation sources transportation boxes installed in the vehicles shall be sheet to minimize the radiatio 14 contained with lead sheets to minimize the radiation exposure during exposure. Attahcment 24 shows the public transportation. pictures of fixed lead sheet in sour