A55 DAYWORKS
£ p
GENERAL BUILDING AND SPECIALIST TRADES:
* To be inserted by Tenderer
Trade/Grade Rate
per hour 0.00
MATERIALS:
Prime cost of Materials and Goods: Include the
provisional sum of £1,500.00 1,500.00
Add for percentage to cover incidental costs, overheads
and profit 0.00%
PLANT:
Prime cost of Plant: Include the provisional sum of
£750.00 750.00
Add for percentage to cover incidental costs, overheads
and profit 0.00%
£ p
COLLECTION
Page 3/1
Page 3/2
TO SUMMARY £