1 Stage payments Pre-agreed amounts are paid Provides high predictability of
at pre-set times regardless of cash flow but low accuracy of progress on site value of works done to date 2 Milestone payments Pre-agreed amounts are paid Provides high predictability of upon completion of pre-agreed payments but low predictability elements of when they may become due. 3 Payment against an activity At pre-agreed timescales Provides reasonable predictability schedule progress against an activity of cash flow forecast but only schedule is monitored and pre reasonable accuracy of value of agreed payments are made works done to date for activities which have been completed 4 Valuation of works done to date At pre-agreed periods the value Provides lowest predictability on site (3rd party certification) of work on site is assessed of cash flow forecast but high accuracy of value of works done to date