You are on page 1of 8

International Journal of Project Management Vol. 17, No. 5, pp.

301±308, 1998
# 1999 Published by Elsevier Science Ltd and IPMA. All rights reserved
Printed in Great Britain
0263-7863/99 $20.00 + 0.00

PII: S0263-7863(98)00046-5

Limitation of design liability for


contractors
H K Gaafar and J G Perry
School of Civil Engineering, The University of Birmingham, Edgbaston, Birmingham, B15 2TT, UK

This paper is based on research into the di€erent levels of design liability which contractors
might be expected to carry. There is a perception within the construction industry that there are
two distinct levels of liability: `reasonable skill and care' and `®tness for purpose'. The paper
shows that this is an oversimpli®cation, partly caused by the lack of legal de®nition of the term
`®tness for purpose'. The paper provides an introduction to the legal background of design liab-
ility and considers some of the problems raised by the diculty of obtaining insurance cover for
`®tness for purpose' liability. Some commonly used forms of contract are then compared in re-
lation to their treatment of design liability and legal analysis and case law are addressed to
demonstrate problems associated with attempts to limit liability to `reasonable skill and care'.
The paper then presents the concept of a spectrum of liability rather than two distinct levels and
considers the extent to which the novel approach adopted in the relatively new Engineering and
Construction Contract is consistent with the concept of a spectrum of liability. The main aim of
the paper, whose authors are not legal practitioners, is to provide enlightenment for project man-
agers and other construction industry professionals in an area where diculties of understanding
are caused by the interaction of legal elements with contractual provisions. A further aim is to
stimulate the industry to move towards the adoption of liability clauses in forms of contract
which are robust in the prevailing legal and insurance contexts. # 1999 Published by Elsevier
Science Ltd and IPMA. All rights reserved
Keywords: liability, design, contractor, skill and care, ®tness for purpose

Introduction The research undertaken for this paper formed part


of a broader package of research, funded by EPSRC,
The key practical issue concerning design liability for
into risk allocation in contracts, which was stimulated
contractors is the question of which level of liability is
by the involvement of one of the authors in the devel-
preferable, or acceptable, to the parties to engineering
opment of the New Engineering Contract1 and its sec-
and construction contracts. The choice is perceived to
ond Edition The Engineering and Construction
be between a `®tness for purpose' liability and a
Contract2. Legal advice to the drafters of the NEC/
`reasonable skill and care' liability. Research con-
ECC led to the avoidance of the term `®tness for pur-
ducted at the University of Birmingham has revealed
pose' and to the eventual adoption of the notion that
that this choice may not be as straightforward as it
the Employer would either de®ne the extent of his
seems. The problems identi®ed include:
requirements for performance through the Works
. the interaction of the various legal elements with Information or would limit the liability through the
contractual provisions and the consequent diculties choice of an optional clause. The lengthy consider-
of understanding created for practitioners in the ations which led to this policy revealed, at least in
industry; embryonic form, some of the problems subsequently
. practical problems relating to the insurability of a identi®ed by more rigorous research.
`®tness for purpose' liability and of transferring that The methods used for the research leading to this
liability to design subcontractors; paper included literature review, a questionnaire survey
. uncertainty over whether some standard forms of to contractors and interviews with specialists, including
contract achieve their desired intent of limiting liab- insurers.
ility to `reasonable skill and care'; The authors have no legal expertise beyond that
. di€erences in both principle and detail between com- acquired through their professional and academic
monly used standard forms of contract; interest in project management and construction con-
. doubts as to whether the term `®tness for purpose' is tracts. They have not attempted, within the paper, to
precisely de®ned in the English legal system. interpret or challenge the legal judgements and com-
301
Limitation of design liability for contractors: H K Gaafar and J G Perry

mentaries but to present what they regard as the sali- Express provisions in the contract (which are subject
ent features of the position. to the Unfair Contract Terms Act 1977) will a€ect the
The paper aims to provide enlightenment on the nature of the obligation. Such provisions may either
legal aspects of design liability for the bene®t of pro- seek to limit the liability to `reasonable skill and care'
ject managers and other practitioners concerned with or to make explicit a `®tness for purpose' liability.
engineering and construction contracts. It starts with Examples of these provisions in some commonly used
an introduction to the legal background of design liab- forms of construction contract are given later in the
ility and presents a brief discussion of the practical paper.
aspects of design liability based on the questionnaire In the absence of express provisions in the contract,
completed by contractors. Some commonly used forms Duncan Wallace, 19703 shows that it is submitted by
of contract are then compared in relation to their pol- the courts that a contractor undertaking to do work
icy towards design liability and legal comment is intro- and supply materials impliedly{ undertakes;
duced to show that their policies, as interpreted from
`a. to do the work undertaken with care and skill
the wording of relevant clauses, may not carry a high or, as sometimes expressed, in a workmanlike man-
certainty of being achievable.
ner.
The paper then presents the concept that, in prac-
b. to use materials of good quality. In the case of
tice, a spectrum of liability rather than two distinct
materials described expressly this will mean good of
levels can be deduced from the research. This section
their expressed kind. (In the case of goods not
of the paper includes an assessment of the extent to
described, or not described in sucient detail, it is
which the novel approach adopted by the NEC/ECC
submitted that there will be reliance on the contrac-
®ts the concept of a spectrum of liability.
tor to that extent, and the warranty in (c) below
The two main conclusions of the paper are, ®rstly,
will apply);
that there is a need for deeper understanding within
c. that both the work and materials will be
the industry of the problems posed by the assumption reasonably ®t for the purpose for which they are
that there are two distinct levels of design liability.
required, unless the circumstances of the contract
Secondly, that the industry should move towards the
are such as to exclude any such obligation (this obli-
adoption in forms of contract of those models of liab-
gation is additional to that in (a) and (b), and only
ility, through appropriately drafted clauses, which are
becomes relevant, for practical purposes, if the con-
robust in the prevailing legal and insurance contexts.
tractor has ful®lled his obligations under (a) and
(b)).'
Duncan Wallace, 19703 also explains that the ®rst
Legal background two obligations (a) and (b) correspond to the warranty
of merchantability, and that under (c) to the warranty
The level of liability that design responsibility can give of suitability, under section 14 of the Sale of Goods
rise to di€ers between contract and tort for the party Act 1873. He explains that the obligation under (c) is
holding the responsiblity. It is the same in tort for here called the `design' obligation and extends to all
both professional designers and contractors but it dif- defects of planning or conception of the building or
fers in contract. In tort, the nature of the designer's project in question including, as stated, the selection of
obligation is to exercise `reasonable skill and care' irre- all materials and work processes.
spective of the nature of the designer's organisation. In Jackson and Powell, 19924 sought to explain this
contract, however, the position in law di€ers to some position by reference to the case of Midland Bank
extent between the professional designer and the con- Trust Co. Ltd. vs. Hett, Stubbs and Kemp (1979)
tractor designer in respect of implied terms.* A pro- where they state that Oliver J. pointed out the obli-
fessional designer's liability in contract is to exercise gation to exercise `reasonable skill and care' is not the
`reasonable skill and care'. He is not taken to warrant only contractual term which ought to be considered in
that the result will be achieved (`strict liability'{). If a professional negligence action;
the result is not achieved, but he has exercised `reason-
able skill and care', he will not be liable. `The classical formulation of the claim in this sort of
The contractor designer su€ers risk by reference to case as ``damages for negligence and breach of pro-
statutory implied terms, under the Sale of Goods Act fessional duty'' tends to be a mesmeric phrase. It con-
1972 and the Supply of Goods and Services Act 1982, centrates attention on the implied obligation to devote
which will impose certain contractual warranties relat- to the client's business that reasonable care and skill to
ing to merchantable quality and ®tness for purpose be expected from a normally competent and careful
irrespective of what the contract says. The statutory practitioner as if that obligation were not only a com-
implied terms give rise to risk for the designer contrac- pendious, but also an exhaustive, de®nition of all the
tor that a contract which is silent on the point will duties assumed under the contract created by the retai-
impose on him `strict liability' for all the obligations ner and its acceptance. But, of course, it is not. A con-
he has undertaken, including his design obligation. tract gives rise to a complex of rights and duties of
which the duty to exercise ``reasonable care and skill'' is
but one.
*Terms which the parties have not themselves seen ®t to include
expressly, and so as a general rule the courts will only imply terms If I employ a carpenter to supply and put up a good
that they feel the parties must, of necessity, have agreed to if they quality oak shelf for me, the acceptance by him of that
have thought about it.
{Liability generated from actions or inactions which are not necess- employment involves the assumption of a number of
arily fault-related or negligence-related. contractual duties. He must supply wood of an ade-
{The courts will imply the term. quate quality and it must be oak. He must ®x the shelf.

302
Limitation of design liability for contractors: H K Gaafar and J G Perry

And he must carry out the fashioning and ®xing with the interpretation of `®tness for purpose' is highly
the reasonable care and skill which I am entitled to dependent on the facts and circumstances of each par-
expect of a skilled craftsman. If he ®xes the brackets ticular case. As will be shown later in the paper, it has
but fails to supply the shelf or if he supplies and ®xes a also been found that the extrapolation of the interpret-
shelf of unseasoned pine, my complaint against him is ation of speci®c cases to a new situation certainly
not that he has failed to exercise reasonable skill and appears complex and uncertain to non-lawyers.
care in carrying out the work but that he has failed to
supply what was contracted for.'
Jackson and Powell, 19924 conclude, therefore, that Liability limitation in practice
the particular obligations of a carpenter (or a contrac- The problems posed by the levels of liability is further
tor) to his client are generally of a di€erent nature to ampli®ed by the industry's needs. It might be expected
those owed by a professional man to his client. that clients would generally prefer contractors to have
The above does not state expressly that the contrac- a `®tness for purpose' liability. However, research has
tor's obligations amount to a `®tness for purpose' revealed that this is not necessarily the case. From a
requirement. However, the statement ``. . . my com- research sample that included 32 contractors (inclusive
plaint against him is not that he has failed to exercise of both interview and survey results where the survey
`reasonable skill and care' in carrying out the work but response rate was 55%), it has been found that the
that he has failed to supply what was contracted for'' majority of clients (about 70%) would prefer to
implies a higher level of liability than `reasonable skill impose a `®tness for purpose' liability. A signi®cant
and care'. The phrase `what was contracted for', inter- minority of clients (about 30%) may not necessarily
preted in the sense of normal usage of the English have this preference. The most likely reason for this
language, suggests that the precise level of liability is ®nding, as evidenced by the research, seems to be that
governed by what is stated in the totality of the con- the latter group probably recognises the practical and
tract. commercial problems posed to contractors by a strict
Case law has sought to de®ne the level of compe- `®tness for purpose' liability. As the law does not
tence and the degree of skill and care required. require professional designers to carry a higher level of
Whether `reasonable skill and care' has been exercised liability than `reasonable skill and care' there is usually
is judged by reference to the ordinary level of compe- no insurance market o€ering a higher level of cover
tence of a designer operating in that particular ®eld. for design liability and so neither they nor contractors
The generally accepted expression of the test appears are able to obtain it. We understand that occasionally
in Bolam vs. Frien Hospital Management Committee Professional Indemnity insurers may enter into special
(1957): agreements for a higher level of cover with pro-
fessional designers, though this outcome may be an
`The test is the standard of the ordinary skilled man uncertain one until the precise details of the work to
exercising and professing to have that special skill.' be covered are known.
Jackson and Powell, 19924 also state that the stan- Consequently both contractors and professional
dard of care was originally expressed over 100 years designers are unlikely to be able to obtain protection
ago in the case of Lanphier vs Philos (1838), against a `®tness for purpose' liability. If this level of
liability is placed on contractors they may not be able to
`Every person who enters into a learned profession pass it down to professional designers appointed under
undertakes to bring to the exercise of it a reasonable a subcontract, thus leaving the contractor carrying a
degree of care and skill. He does not undertake, if he is major uninsured risk. Understandably contractors pre-
an attorney, that at all events you shall gain your case fer their liability in these circumstances to be limited to
nor does a surgeon undertake that he will perform a `reasonable skill and care' and it appears that some cli-
cure, nor does he undertake to use the highest possible ents recognise that it is expedient to do so.
degree of skill. There may be persons who have higher This problem is not restricted to the design and
education and greater advantage than he has but he build procurement route though that is the area where
undertakes to bring a fair, reasonable and competent the issue and research tended to be focused. In other
degree of skill.' methods of procurement there is an increasing trend to
From this legal background, we ®nd therefore that use specialist subcontractors who are required to pro-
in both tort and contract the professional designers vide some design. The same problems arise in these
liability amounts to `reasonable skill and care'. We can situations though they may be partially obscured as
also establish that the law has sought to de®ne `reason- the subcontractors may not necessarily be aware of a
able skill and care'. The position di€ers for contractors higher level of liability in the main contract.
in contract where the lack of express provisions in a The lack of transparency of the requirements for de-
contract limiting their liability to `reasonable skill and sign responsibility of subcontractors has been commen-
care' will expose them to statutory implied terms. ted on in a di€erent context by U€ (1991)5 who stated;
Their liability then becomes more onerous and it may `The contractor's design responsibility subject has
be implied that it is a strict `®tness for purpose' liab- always had something of a Cinderella existence, its true
ility. However, the authors have been unable to ®nd a potential and importance being concealed beneath a
precise de®nition of the term `®tness for purpose' and droll exterior. Thus, under the well-known JCT forms
several lawyers have con®rmed in discussion that one of contract, there was often con¯ict between the
does not exist, at least in the U.K. construction indus- Conditions of Contract and actual events, particularly
try, though we sense that the lack of de®nition is also where design work was undertaken by nominated sub-
a wider international problem. It has been found that contractors.'

303
Limitation of design liability for contractors: H K Gaafar and J G Perry

Other writers have questioned the policy of unlim- as a limitation of liability. There is apparently nothing
ited design liability of contractors undertaking design to prevent it being ``expressly provided in the con-
and build contracts, for example, Goudsmit (1990)6 tract'' that the contractor shall design some element of
who stated; the works to achieve a particular result.
In commenting about ICE (Design and Construct)
`Why should a design and build contractor have a more
Conditions of Contract11, Capper (1996)12 highlighted
extensive liability as to his design work than a pro-
the same risk arising. He stated,
fessional designer? Why should the liabilities resulting
from a design and build contract be greater than those `Whilst it would appear that the intention of the con-
accumulating under a traditional contract structure?' tract craftsman was not to impose the higher standard,
Due to the above reasons and maybe others, some there is some risk that on the wording of the ICE
standard forms of contract have introduced clauses (Design and Construct) the higher standard is to be
which seek to limit the level of design liability carried achieved by the Contractor.'
by contractors. However, an important question arises; However, Capper (1996)12 went on to explain that
do these limitation clauses actually achieve the desired the risk stems from other clauses, for example, Clause
objective of limiting the contractors' liability to 6(2)(a) in the ICE (D and C) which reads as follows;
`reasonable skill and care'?
`The Contractor shall except as may otherwise be pro-
vided in the Contract submit to the Employer's
Liability limitation clauses within forms of contract Representative such designs and drawings as are necess-
ary to show the general arrangement of the Works and
The authors have found that liability limitation clauses that the Works will comply with the Employer's
within some existing standard forms of contract may Requirements.'
not necessarily serve their purpose of limiting the con-
tractors' liability to `reasonable skill and care'. The de®nition of the Employer's Requirements is
As the legal background showed, the strict `®tness contained in Clause 1(1)(e) which reads:
for purpose' liability would be implied in contract (by `the requirements which are identi®ed as such at the
Statute) for contractors' design and workmanship. date of the award of the Contract and any subsequent
This would be the case unless it has been expressly lim- variations thereto and which may describe the standards
ited within the contract to `reasonable skill and care'. performance and/or objectives that are to be achieved
Some writers have commented about the legal in- by the Works or part thereof.'
terpretation of such express provisions. For example,
starting with JCT817, Stuart-Ranchev, 19908 shows He states that it can readily be seen therefore that
that Clause 2.5.1 of JCT81 expressly provides that the not only are the designs and drawings to be prepared
contractor has the ``like liability as would an architect, so as to show that the Works will comply with the
or as the case may be, other appropriate designer''. The Employer's Requirements but also the Employer's
same wording is also used in Clause 2.7.1 of the Requirements themselves import standards, perform-
Contractor's Design Portion Supplement to JCT809. ance and/or objectives that are to be achieved by the
This may limit the contractor's design to `reasonable Works or parts of them.
skill and care', but this may not necessarily apply to a The ICE Conditions of Contract, 5th Edition13 do
specialist subcontractor supplying design. Stuart- not have a clause limiting the contractor's liability.
Ranchev, 19908 comments that, in relation to this The reason presumably was that the contractor was
Clause, the Architect's standard terms under the RIBA not expected to have any design duties. Also, GC/
Standard Conditions of Appointment expressly exclude Works/114 does not mention limitation of the level of
liability in relation to specialist subcontractors' design. design liability for contractors.
If the Contractor's liability is expressed as the ``like Model Form MF/115 does not limit the contractor's
liability as an architect would [have]'', then the pos- liability in relation to the Works. On the contrary,
ition may be di€erent for specialist subcontractors Clause 36.9 states,
since the liability is expressly excluded. `The Contractor's liability under this Clause shall be in
Within the ICE Conditions of Contract, 6th lieu of any condition or warranty implied by law as to
Edition10, the liability is limited through Clause 8(2) the quality or ®tness for any particular purpose . . .'
which states,
Similarly, IChemE Red Book16 has Clause 3.3 that
`The Contractor shall exercise all reasonable skill care
states,
and diligence in designing any part of the Permanent
Works for which he is responsible.' `. . . the Plant as completed by the Contractor shall be
in every respect suitable for the purposes for which it is
Whilst the clause states that the contractor is to
intended.'
exercise `reasonable skill and care' it does not specify
that the end product does not necessarily have to be ®t Bateman (1994)17 commented that the background
for its intended purpose. One interpretation of the to the ICE (D & C) and the IChemE Red Book is
clause may be that the contractor has to exercise rather di€erent. A civil engineering D & C contractor
`reasonable skill and care' and also that the structure would probably employ a consulting engineer to do
may still need to be ®t for its intended purpose. On the design work. Such a consultant is unable to accept
the same note, U€ (1991)5 commented that the inten- liability greater than that of `reasonable care and skill'.
tion appears to be to limit the contractor's design The craftsmen of the ICE (D & C) form recognised
responsibility to one requiring proof of negligence. that and chose not to leave the contractor carrying a
But, he also stated that the clauses are not expressed risk that he could not pass on, and which he was ill-
304
Limitation of design liability for contractors: H K Gaafar and J G Perry

Table 1 Limitation clauses within Standard Forms of Contract


Forms with `reasonable skill and care' Silent forms Forms with a strict `®tness for Forms with optional `reasonable
limitation clauses purpose' requirement clauses skill and care' clause
JCT81 ICE 5th Edition Model Form MF/1 ECC
ICE 6th Edition GC/Works/1 IChemE Red Book
ICE (Design and Construct) JCT80
Contractors Design Portion Supplement
(JCT80)

equipped to carry himself. In contrast, process engin- Liability spectrum


eering contractors often develop their processes in a
The e€ects of the ®ndings presented so far in this
research facility and therefore can test and re®ne the
paper are ®rstly that the precise level of design liability
process before marketing it. Such processes are often
for contractors is in¯uenced by a combination of
the subject of patents etc. and details may be subject
implied terms (from Statute), the nature of the word-
to restrictions (for commercial reasons). That, together
ing of clauses in contract forms and the manner in
with feed stocks often being of a consistent quality,
which plans and speci®cations are written for a par-
leads to a strict `®tness for purpose' liability being
ticular contract. Secondly, that whilst the concept of
acceptable to the contractor as well as desirable to the
`reasonable skill and care' is amenable to legal de®-
purchaser. The research has not been able to test
nition, or at least reasonable description, that of `®t-
whether process contractors are able to insure this risk
ness for purpose' is not. Thirdly, that attempts to limit
or feel the need to do so. Table 1 summarizes the way
liability to `reasonable skill and care' may not fully
in which commonly used standard forms deal with de-
achieve their objective, thereby introducing uncertainty
sign liability.
into the apparently clear distinction between `reason-
When we consider the ECC, we ®nd that Clause 20
able skill and care' and `®tness for purpose'.
requires compliance of the contractor's design with the
Taken together, these ®ndings appear to the authors
Works Information. The ECC has a level of liability
to produce a reality which can be described as a spec-
limitation clause through its Optional Clause M which
trum of liability rather than two distinctive levels of
states,
liability. This can be represented diagrammatricallyÐ
`The Contractor is not liable for Defects in the works see Figure 1.
due to his design so far as he proves that he used At one end of the spectrum (boundary d), the con-
reasonable skill and care to ensure that it complied with tractor will be held liable if the works or part of the
the Works Information.' works are not ®t for their intended purpose. That,
however, will be based on the assumption that the cli-
If the Optional Clause is not used, then Clause 20 ent has very clearly communicated his requirements
prevails. The contractor's liability may or may not and de®ned his purposes. In this case, the liability may
then be interpreted as a strict `®tness for purpose' liab- be due to design, defective workmanship or defective
ility depending on how the Works Information is materials. At boundary `a', the contractor will only be
drafted. The Works Information may contain some held liable if it was proved that he was negligent.
text which requires a certain level of performance or Legally, these two boundaries may be perceived as
function and other information which is in the form of easy to de®ne. However, in practice, the particular
a detailed speci®cation. The following statement from wording of the contract clauses and design speci®ca-
Hudson18 suggests that the performance speci®cation tions may place the actual liability somewhere in the
will override in terms of providing the governing level spectrum between the two extremes. For example,
of liability in these circumstances; i. The case of Greaves (Contractors) Ltd. vs.
Baynham Meikle and Partners (1975) was a com-
`Where a contractor undertakes ``to carry out work plex one which went to the Court of Appeal. The
which will perform a certain duty or function, in con- original judgement was that Baynham Meikle were
formity with plans and speci®cations, and it turns out liable for providing a design of a warehouse which
that the works constructed in accordance with the plans was not `®t for purpose' in terms of withstanding vi-
and speci®cations will not perform that duty or func- bration from fork lift trucks. The Court of Appeal
tion, it would appear that generally the express obli- upheld the original judgement but stated that
gation to construct a work capable of carrying out the Baynham Meikle had no greater duty than `reason-
duty in question overrides the obligation to comply able skill and care'. However it was also stated that
with plans and speci®cations, and the contractor will be what the original judge meant was that in the cir-
liable for the failure of the work, notwithstanding that cumstances of the case special steps were required
it is carried out in accordance with the plans and speci- to discharge the duty to exercise `reasonable skill
®cations . . .''.' and care' and that those steps had not been taken
and if they had been the design would have been `®t
If this is correct it has implications for a contractor
for purpose'.
under any contract which does not limit the liability to
`reasonable skill and care'. Where the speci®cations In e€ect the case reinforces the view that a pro-
include both performance and detailed speci®cations fessional designer has a liability which is `reasonable
the contractor should ensure that the latter do not hin- skill and care'. However the judgement that special
der his ability to achieve the former. steps were needed to exercise `reasonable skill and
305
Limitation of design liability for contractors: H K Gaafar and J G Perry

Figure 1 Liability spectrum

care' implies that there is a spectrum of such liability the purpose and adequacy of the plans and speci®ca-
between `a' and `b' and that, in such circumstances tions and they remain of paramount importance.
`reasonable skill and care' may equate to `®tness for iii. boundary `c' may occur anywhere between `b'
purpose'. and `d' in cases where higher skill and care may be
ii. compliance with the plans and speci®cations interpreted by some practitioners as `reasonable skill
may have ensured a `®t for purpose' completed and care', for example the case of George Wimpey
works but in actual fact inadequacy of information & Co Ltd. vs. D.V. Poole and others (1984). In par-
supplied by clients caused the problem, for example, ticular reference to this case, an important question
the case of Stormont Main Working Men's Club was raised by Stuart-Ranchev (1990)8. Does the test
and Institute Ltd. vs. J. Roscoe Milne Partnership di€er for someone with greater skills than the ordin-
(1988). This case signi®es the importance of convey- ary man exercising that particular skill? In answer
ance of information about the intended purpose to to this question she states,
the designer. In this case, the architect, who was
particularly experienced in designing working men's
`this question was considered in George Wimpey & Co
clubs (including snooker facilities), was sued by his
Limited vs. D.V. Poole and others (1984) where the
client when it became apparent that there was insuf-
judge held that the basic test is no di€erent where the
®cient space for competition play. The judge found
client deliberately selects and pays for someone with
that,
particularly high skills. This case concerned the curious
scenario of a design and build contractor trying to per-
`the expectations of the client, so far as the architect suade the Court that it had been negligent on the basis
can be expected to be aware of them, are relevant when that its special expertise meant it owed a higher duty of
considering the duty of the architect to seek clari®cation care than ordinary competence. The reason was that
of his brief and also that the architect has a duty to Wimpey had carried out remedial works and were now
exercise due care to ensure that the design should be claiming under their professional indemnity policy, for
reasonably e€ective to achieve the client's purpose, so which they had to establish they were negligent. The
that if the client has expressed his instructions in terms judge however held himself bound to follow the Bolam
which leave the architect in doubt as to what the pur- test which had House of Lords approval (Whitehouse v.
pose is, the architect has a duty to ascertain what is the Jordan [1981]) and rejected that Wimpey had been neg-
purpose he is instructed to achieve.' ligent.'
The judge however decided that this was not the It appears that the expected level of skill and care
case here and that it was reasonable for the architect may not be easy to establish. If negligence can easily
to assume only recreational purposes were required. In be established (boundary `a' in Figure 1), then the
this case, a spectrum was produced between `a' and `b' courts can easily establish that `reasonable skill and
but the liability laid with the client. Again `®tness for care' has not been exercised and therefore the respon-
purpose' may have been achieved by the architect if sible party win be held liable in contract and possibly
adequate information was supplied in the speci®cations in tort. However, as the case of Wimpey demonstrates,
or if the architect considered the possibility of compe- a `no negligence' case may be established but with the
tition play and sought clari®cation. Clients, therefore, result that a party may be considered, or may consider
still have a responsibility towards communication of himself, negligent. Therefore, a spectrum between `b'
306
Limitation of design liability for contractors: H K Gaafar and J G Perry

and `c' may be created where there is potential con- If the ECC Optional Clause M is used, then the in-
sideration of negligence. However, if `higher skill and terpretation will probably be di€erent from the the in-
care' is exercised then a spectrum between `c' and `d' is terpretation of similar clauses in other contracts in two
created. ways. Firstly, unlike the ICE, Option M of the ECC
introduces an explicit limitation through the words
iv. A case stated by Stuart-Ranchev (1990)8
``The Contractor is not liable . . .''. If it is not ®t for its
shows that a contractor's responsibilities may
intended purpose and the contractor can demostrate
extend to `®tness for purpose' in terms of design,
that he exercised `reasonable skill and care' then he
even when the contractor has no direct responsibil-
will not be liable. Secondly, Option M of the ECC
ity for producing the design. In Brunswick
puts the responsibility for proof of negligence on the
Construction Ltd. vs. Nowlan and Others (1974),
contractor. He is the party who has to prove that he
the contractor entered into a contract with the
exercised `reasonable skill and care'. Traditionally, the
plainti€ to build a house in accordance with the
onus of proof of negligence was on the client to prove
drawings and speci®cations. These had been pre-
that the contractor did not exercise `reasonable skill
pared by an architect employed by the plainti€, but
and care'. Abrahamson (1997)19 has commented that;
no architect or engineer was involved beyond the
design stage. Due to a design defect, the completed `Under Option M the employer avoids the diculties of
house started to leak. The contractor was held liable proving from outside that the contractor's design was
to the plainti€ because a company of its experience negligent. The contractor has an incentive to ensure
should have detected that the design was defective; that he (and his subcontractors and sub-consultants) do
the house-owner not having an architect or engineer their designing with provable care.'
to supervise the works must have been taken to Clause M is a secondary option within the structure
have relied entirely on the skill and attention of the of the NEC/ECC, which means that clients choose
contractor; and knowing of the reliance based upon whether to select it or not. This has the advantage of
him, the contractor was under a duty to warn; the taking into account the di€ering needs of the industry
contractor's obligation was to carry out work which as not all clients require a strict `®t for purpose' liab-
would perform the intended function and this over- ility from their contractors. If Option M is not used
rode the obligation to comply with the plans and the extent of liability (the position on the spectrum)
speci®cations. becomes highly dependent on the way in which the
This is perhaps an extreme case, turning on the lack Works Information is drafted.
of professional supervision of construction. However it
demonstrates vividly that assumptions about the level
of liability are dangerous and that circumstances can
move the liability right across the spectrum from `d' to Conclusions
`a'. The research has shown that the industry perception
These cases o€er support to the authors' contention of two distinctive levels of design liability is a major
that within the construction industry, a spectrum of oversimpli®cation of the legal position. Perhaps the
liability, which is discontinuous, is a better represen- most notable illustration of this is the lack of legal
tation of reality than the supposition that there are de®nition of the widely used term `®tness for purpose'.
two distinct levels. For professional designers, archi- A rather more subtle issue, though of considerable
tects, contractors and professional indemnity insurers, commercial importance, is that legal analysis and case
boundary `a' may be perceived as distinct without the law show that attempts to limit liability in some forms
knowledge that it can be established anywhere between of contract may not achieve the desired purpose and
`a' and `d'. Through more explicit statements, there may mislead parties to the contract into a false sense
may therefore be a need for a more practical under- of security.
standing by managers and engineers of the notion that These points are well understood by experts in the
`reasonable skill and care' is not distinct. For most legal profession, but it is clear that there is a need for
existing forms of contract, no attempt is made to take deeper understanding within the industry of the pro-
this concept of a spectrum into account or to recognise blems posed by the assumption that there are two dis-
that it exists. We have seen that most of them attempt tinct levels of liability. Perhaps the most evident
to limit the contractor's liability to either boundary `a' practical problem encountered is that of the unavail-
or `d'. ability or near unavailability of insurance for a `®tness
The exception to this is the ECC. As stated before, for purpose' liability. This a€ects contractors (es-
the ECC core Clause 20 requires the contractor's de- pecially in design and build contracts), specialist sub-
sign to comply with the Works Information. In contractors and professional designers, especially when
essence, this takes into account the existence of a liab- the latter are appointed under a subcontract to a de-
ility spectrum since the Clause is drafted in a way that sign and build contractor.
the liability is dependent only on the particulars of the The authors have presented the concept of a spec-
plans and speci®cations (the Works Information). The trum of liability as an aid to understanding the legal
main danger for the contractor would be inadequacy position. An analysis of several common forms of con-
of information supplied by clients. However, in this tract yields the view that the ECC is the closest to
case, the liability would remain with the client unless accomodating to this spectrum. It has been argued
the contractor, as a designer, did not exercise `reason- that through Option M in the ECC, a limitation to
able skin and care' in seeking adequacy of infor- liability is clearly established. If Option M is not used,
mation. The other uncertainty is whether Hudson's the extent to which the contract moves through the
point, referred to earlier in the paper, is correct. spectrum towards `®tness for purpose' is dependent on
307
Limitation of design liability for contractors: H K Gaafar and J G Perry

the way the Works Information is drafted rather than 10. The Institution of Civil Engineers, the Association of
relying on a legally unde®ned term. Consulting Engineers, and the Federation of Civil Engineering
Contractors, Standard Conditions of Contract, 6th ed., 1991.
Many of the existing forms of contract appear not 11. The Institution of Civil Engineers, Association of Consulting
to be robust, given the prevailing legal and insurance Engineers, and the Federation of Civil Engineering
contexts, in the ways in which they deal with design Contractors, ICE Design and Construct Conditions of Contract,
liability. The industry should move towards the adop- Thomas Telford Services, 1992.
12. Capper, P., Constructing the Team using the New Engineering
tion in forms of contract of models of liability (in Contract, Paper to conference on NEC and Construction Law,
terms of appropriately drafted clauses) which re¯ect Pretoria, South Africa, March 1996.
these contexts. 13. The Institution of Civil Engineers, the Association of
The authors do not pretend that the research has Consulting Engineers, and the Federation of Civil Engineering
Contractors, Standard Conditions of Contract, 5th ed., 1973.
been exhaustive, for example the particular position of 14. Her Majesty's Stationery Oce, General Conditions of
process plant contractors with respect to `®tness for Government Contracts for Building and Civil Engineering Works,
purpose' liability has not been pursued. Nevertheless 2nd ed., September 1977, London.
they hope that the paper has provided some enlighten- 15. The Institution of Mechanical Engineers, the Institution of
ment on the topic and will stimulate the development Electrical Engineers and the Association of Consulting
Engineers, Model Form of General Conditions of Contract for
of more robust approaches which avoid the problems Mechanical and Electrical Works, June 1988.
that have been outlined. Participants from the con- 16. The Institution of Chemical Engineers, Model Form of
struction industry, the legal profession and the insur- Conditions of Contract for Process Plants, Suitable for lump-sum
ance sector will need to work together to achieve this. contracts in the UK, Oct 1968, revised 1981.
17. Bateman, G., Process Plant Contracts. Paper presented at the
Risk, Management and Procurement in Construction Seventh
Table of cases Annual Conference, Centre of Construction Law and
Management and CIRIA, September 1994.
18. Duncan Wallace, I.N., Hudson's Building and Engineering
Contracts, Volume 1, 11th edition. Sweet and Maxwell,
. Brunswick Construction Ltd. vs. Nowlan & Others London 1995.
(1974) 21 BLR 127. 19. Abrahamson, M.W., Private communication to Professor John
. Greaves & Co. (Contractors) vs. Baynham Meikle Perry, 1997.
and Partners (1975) Court of Appeal.1.WLR.1095.
. Stormont Main Working Men's Club and Institute Dr. H. K. Gaafar is a Research
Ltd. vs. J. Roscoe Milne Partnership (1988) Associate at the School of Civil
Con.L.R.127. Engineering, the University of
. George Wimpey & Co. Ltd. vs. D.V. Poole and Birmingham. He has been in the
School for several years during
others (1984) 24.BLR.58. which he gained his BEng degree in
civil engineering in 1992 and com-
pleted his PhD. in 1997. He has
been appointed at his current pos-
ition since 1995 undertaking as an
References Associate with Prof. J. G. Perry an
1. The Institution of Civil Engineers, The New Engineering EPSRC funded Grant to look into
Contract. Thomas Telford Ltd., London, 1993. ``Risk Allocations in the New
2. The Institution of Civil Engineers, The Engineering and Engineering Contract''.
Construction Contract. Thomas Telford Ltd., London, 1995.
3. Duncan Wallace, I.N., Hudson's Building and Engineering
Contracts. Sweet and Maxwell, London, 1970.
4. Jackson and Powell, Professional Negligence, 3rd ed. Sweet and
Maxwell, London, 1992. Professor John Perry is Head of the
5. U€, J., The ICE Conditions of Contract, 6th ed. New Thoughts School of Civil Engineering at the
on Old Issues. The International Construction Law Review, University of Birmingham. He
Volume 8, Part 2, April 1991, Lloyd's of London Press Ltd. received his PhD from UMIST in
1985. His research interests cover
6. Goudsmit, J.J., Exclusion or Limitation of Liability in a
several aspects of project manage-
Turnkey Contract. The International Construction Law Review,
ment including contract strategies,
Volume 7, Part 3, July 1990, Lloyd's of London Press Ltd.
7. Joint Contracts Tribunal, Standard Form of Building Contract, risk management and the develop-
1981 Edition. ment of the New Engineering
8. Stuart-Ranchev, A., Design Responsibility, Construction Contract for the Institution of Civil
Engineers in the UK.
Disputes-Avoidance and Resolution. Conference Proceedings,
Law and Business Forum, September 1990.
9. Joint Contracts Tribunal, Contractor's Design Portion
Supplement to Standard Form of Building Contract, 1980 edi-
tion, 1981 edition revised July 1994.

308

You might also like