Provide, furnish and maintain officeaccommondation for the Engineers representatives as specified in schedule No 1.01 V1 4,000,000.00 PS PS 4,000,000.00 Provide equipment, labour and assistance as may be required by the Engineers Representative in accordance with schedule 1.02 No V1 4,000,000.00 PS PS 4,000,000.00 Provide, erect and maintain living accommodationfor the Engineers Representative as specified in schedule No 1.03 V1 2,500,000.00 PS PS 2,500,000.00 Provide or erect and maintain living accommodation for Resident Engineers as 1.04 specified in schedule No.V1 2,500,000.00 PS PS 2,500,000.00 Provide, erect and maintain living accommodation (A.T.O type) as specified 1.05 in schedule No V1 2,000,000.00 PS PS 2,000,000.00 Provide, erect and maintain living accommodation (T.A type) as specified in 1.06 schedule No V1 1,000,000.00 PS PS 1,000,000.00 OTHER PROVISIONAL SUM ITEMS
Allow for compensation in accordance with
1.09 clause 92 of the condition of contract. 5,000,000.00 PS PS 5,000,000.00
1.10 Allow for the cost of progress photographs. 300,000.00 PS PS 300,000.00
Allow for cost of stationery and equipment
1.11 required by Engineers representative. 500,000.00 PS PS 500,000.00 Allow for the provision of furniture for the living accommodation of the Engineers 1.12 Representative. 1,000,000.00 PS PS 1,000,000.00 Allow for the payment of staff wages to daily rated staff of the Engineers 1.13 Representative 2,000,000.00 PS PS 2,000,000.00 Allow for purchase, maintenance and running cost of the official vehicles or motor boats for the Engineers 1.14 Representative as directed. 25,000,000.00 PS PS 25,000,000.00 Allow for services to the Engineers 1.15 Representative. 2,500,000.00 PS PS 2,500,000.00
1.16 Allow for cost design as required 25,000,000.00 PS PS 25,000,000.00
TOTAL CARRIED TO SUMMARY 77,300,000.00 BEME ITEM DESCRIPTION UNIT QTY RATE AMOUNT (N) Clear site on either side of centre line of road up to the limits of construction width of all bush, shrub, grass and tree, remove 2.01 anthills etc and cart to spoil. M2 522,000.00 85.00 44,370,000.00 Remove topsoil 150mm deep and cart to 2.02 spoil M3 78,300.00 2,100.00 164,430,000.00
Excavate in any materials except rock in
cutting and side drains, haul excavated materials any distance, deposit, spread in 150mm layers and compact to 100% B.S compaction as filling for embankments and 2.03 trim slopes to required cross section. M3 26,950.00 2,400.00 64,680,000.00
Excavate unsuitable materials and other
material except rock in cutting and filling areas and side drains and haul to spoil 2.04 (haulage inclusive). M3 12,360.00 4,500.00 55,620,000.00 Excavate in any materials except rock to form turnouts, triangular or trapezoidal drains at toes of embankments, catch water drains at top of cutting and dispose 2.05 excavated material as directed. M3 7,320.00 2,400.00 17,568,000.00
Excavate from approved borrow pits, haul
excavated material any distance, deposit, spread in 150mm layer and compact to 100% B.S compaction as filling for embankment and trim slopes to required 2.06 cross section. M3 228,042.50 3,150.00 718,333,875.00 Provide, place and spread in layers in crushed rock as replacement of unsuitable 2.07 material. M3 0.00 4,000.00 0.00
Provide and place 200mm thick stone
pitching rip - rap protection set in 1 to 4 2.08 cement mortar as and where directed. M2 2,000.00 3,255.00 6,510,000.00 TOTAL CARRIED TO SUMMARY 1,071,511,875.00 BILL NO. 3 CULVERT AND DRAINS ITEM DESCRIPTION UNIT QTY RATE AMOUNT Clear site and debris in pipe and box 3.01 culvertsand dispose as directed. M3 200.00 1,500.00 300,000.00 Ditto item 3.01 but at inlet and outlet of 3.02 culverts and river channels. M3 0.00 1,488.00 0.00
Demolish, remove and haul to spoil pipe
culverts and concrete drains including 3.03 concrete surrounds, wing walls, aprons and M 120.50 2,500.00 301,250.00 Demolish, remove and haul to spoil box 3.04 culverts including wing walls aprons and M 12.00 5,000.00 60,000.00
Excavate for culvert, and side drains in any
material except rock and to any depth including back - filling to 100% B.S 3.05 compaction and dispose of surplus material M3 5,847.80 2,400.00 14,034,720.00
3.06 Extra over item 3.05 for excavation in rock. M3 0.00 7,500.00 0.00
Provide and lay new concrete pipe culverts
as shown on the drawings including 3.07 blinding shuttering and concrete surrounds. 3.071 600mm single access pipe culverts. M 200.00 70,000.00 14,000,000.00 3.072 900mm single pipe culverts. M 345.00 110,000.00 37,950,000.00 3.073 900mm double pipe culverts. M 195.00 180,000.00 35,100,000.00 3.074 1200mm single pipe culverts. M 0.00 200,000.00 0.00 3.075 1200mm double pipe culverts. M 0.00 265,000.00 0.00 3.076 1200mm triple pipe culverts. M 0.00 0.00 0.00 Provide, mix and place concrete grade 25 in head walls wing walls toes and aprons inclusive of blinding formwork and reinforcement, in various sizes of pipe 3.08 culverts M3 200.00 150,000.00 30,000,000.00 BOX CULVERT Provide, mix and place concrete grade 25 in box culverts inclusive of blinding formwork 3.09 and reinforcement M3 887.50 150,000.00 133,125,000.00 Provide, mix and place concrete grade 25 in head walls wing walls toes and aprons of box inclusive of blinding formwork and 3.10 reinforcement. M3 355.00 150,000.00 53,250,000.00 DRAINS Provide and install grade 25 uncovered reinforced concrete drains in townships as 3.11 specified and directed size 0.6 x 0.80 M 0.00 50,000.00 0.00 Provide and lay 225mm concrete filled sandcrete block uncovered drains in townships as specified and directed size 3.12 0.80 M 2,000.00 25,000.00 50,000,000.00 Provide concrete chutes on high 3.13 embankments as directed. M 500.00 2,325.00 1,162,500.00 TOTAL CARRIED TO SUMMARY 369,283,470.00 4.00 PAVEMENT AND SURFACING BEME ITEM DESCRIPTION UNIT QTY RATE AMOUNT (N)
Scarify, shape and compact formation level
4.01 as specified to 100% B.S compaction. M2 350,900.00 30.20 10,597,180.00
provide, spread, shape and compact to
100% West African Standard compaction approved naturally occurring laterite material as sub base in a layer of 150mm compacted thickness to carriage - way and 4.02 shoulders (haulage inclusive) M3 70,180.00 3,450.00 242,121,000.00
provide, spread, shape and compact to
100% West African Standard compaction approved naturally occurring laterite material as base in a layer of 150mm compacted thickness to carriage - way and 4.05 shoulders (haulage inclusive) M3 70,180.00 3,450.00 242,121,000.00
Provide and lay prime coat using MCO or
MC1 cut back bitumen at 1.0 liters/m2 4.06 including blinding with sand or quarry fine. M2 298,700.00 700.00 209,090,000.00 Provide and lay first coat bituminous surface dressing on the carriage - way using cut back bitumen 100/150 seconds STV at 40oc at 1.3 liters/m2 with 20mm single size 4.07 crushed stone chipping. M2 298,700.00 1,250.00 373,375,000.00
Provide and apply bituminous tack coat at
4.08 an application rate of 0.3 litres/m2 M2 0.00 0.00 0.00
Provide and lay second coat bituminous
surface dressing on the carriage - way using cut back bitumen 100/150 seconds STV at 40oc at 1.3 liters/m2 with 20mm with 4.09 12mm single crushed stone chipping. M2 211,700.00 1,100.00 232,870,000.00
TOTAL CARRIED TO GENERAL SUMMARY 1,310,174,180.00
MINISTRY OF WORKS AND TRANSPORT,
CONSTRUCTION OF ANNUNE - ANGUHAR - NAGI ROAD (29.0 Km) ROAD
ITEM DESCRIPTION AMOUNT (N)
Bill No1 GENERAL 77,300,000.00
Bill No 2 SITE CLEARANCE &EARTHWORKS 1,071,511,875.00