Professional Documents
Culture Documents
[Name of Student]
[Name of Institution]
[Date]
Event Management 2
Executive Summary
Organizing events, seems like a daunting task, as the late '90s concept, which grabbed
attention ofthe World, was a key element needed to manage any type of event. Regardless of
the type and size of the event, the mental and physical hard work is done only slightly
differently. Formula 1 racing is recognized as the pinnacle of motor sport across the globe. It
attracted large audiences, international TV viewers, media interest and huge sponsorships. F1
season is held annually in major cities of the world. Since the first Formula 1 Australian
Grand Prix in 1996, Victoria has celebrated its birthday every year in March or early April at
Albert Park, Melbourne. The Grand Prix is funded and advertised through the Australian
Grand Prix Corporation (AGPC) and partly funded by the Victorian Government. There are
lots of activities in it. First of all, the first step is to form a committee and assign different
positions to each committee. Here you will be aware of all the theoretical concepts that you
have learned so far: public relations, human resource planning, logistics, human skills,
Table of Contents
Introduction................................................................................................................................4
The objective of the Project....................................................................................................4
Project Scope..........................................................................................................................4
User acceptance criteria..........................................................................................................4
Project boundaries or exclusions............................................................................................5
Project constraints..................................................................................................................5
Stakeholder Management Plan...................................................................................................5
Marketing Plan...........................................................................................................................6
Project Budget............................................................................................................................8
Work Breakdown Structure......................................................................................................10
Work Baseline Statement.....................................................................................................11
Scope Baseline Statement.....................................................................................................11
Gantt Chart...............................................................................................................................11
Risk Management Plan............................................................................................................13
Regulatory Environment beyond the Proposed Regulations................................................13
Crowd Management and Public Safety................................................................................13
Operating Without the Regulations......................................................................................15
Conclusion................................................................................................................................15
References................................................................................................................................16
Appendix..................................................................................................................................17
Appendix A..........................................................................................................................17
Appendix B...........................................................................................................................18
Appendix C...........................................................................................................................19
Event Management 4
Introduction
The increasing number and importance of festivals is a worldwide phenomenon.
Cultural experts, government agencies involved in cultural policy and financial decision-
making, and the general public are attracted by the arts, social and economic backgrounds of
dollar industry that regularly hosts major shows and events (PMP, 2014).
held annually in major cities in the world. Since the first Formula 1 Australian Grand Prix in
1996, Victoria has celebrated its fourth birthday every year in March or early April at Albert
Park, Melbourne. The Grand Prix is funded and advertised through the Australian Grand Prix
Corporation (AGPC) and partly funded by the Victorian Government. The Victorian
Government is promoting Melbourne and Victoria to the arena, and as part of a larger way to
provide and prepare a calendar of annual world events that bring significant economic, social
and cultural benefits to the state, the Grand Prix. These benefits include challenge creation,
community participation.
This report describes the economic impact and brand equity of Victoria from hosting
Project Scope
The goal of the project is to use the network to receive feedback, entertainment, invite
participants, supervise the event, and organize race celebration party after the event. This
event not only showcases the best works of art created by participants, but also food, music
The Victorian Calendar of Events is arguably one of the most prestigious and hit activities
across the world. A report produced by the Victorian Major Events Company (VMEC)
predicted that a prime event in Victoria could add an anticipated $1.4 billion in economic
advantages in the coming year. Major activities attract more than 230,000 global visitors to
Victoria every 12 months, accounting for 23% of Victoria's general foreign visitors.
It attracts a huge number of visitors to the country and guarantees sizable branding
and positioning of Melbourne and Victoria, each across the world and internationally.
Melbourne Cricket Ground, its infrastructure and the city of Melbourne, and the
Olympic Park are loved by way of the wider network all the year round.
Create nearby business stories that could upload fee to other Victorian activities and
Organizes exhibitions for small sporting and cultural occasions, and provides services
The venture includes developing a task plan that consists of layout, creation and
implementation of subsequent The Australian Grand Prix. Also, the competition operations
Project constraints
Time – This integrated project plan is required to be done by December 13, 2020,
so the project team can only work for a limited period of time. (Pressure of
deadline)
Budget – The requirement is to complete the project under the estimated cost is $
150,000 USD. The project team has a limited budget to execute this project.
Schedule – Everything should be completed no later than June 30, 2020, which
means the full implementation of the project such as work completed, reviewed,
The Australian Grand Prix is one of the most famous and biggest events in Australia
and opens the F1 seasons every year. Due to this, different types of stakeholders work
together for the success of the event. Victoria State Government and City of Melbourne
represent the primary stakeholder and invest huge amount to set up the event. Also, there are
the sponsors (Rolex, Jaguar, Heineken, Porsche, Australian Air forceetc), the broadcast
partner, supporters, event planner, the drivers and Automakers. The stakeholder’s
Stakeholders Roles
Victoria State - Ensure the safety of all spectators
Government - Financial Support
Marketing Plan
expectations - Weekly
- Project project
overview status
- Forecasting report
project - Agenda
budget, and
schedule
- Reporting
project
progress
Mayor of Project E-mail Once a Weekly - Keeping - Weekly
Lynn – Manager week Project the mayor project
Judith F. Status informed status
Kennedy Report about the report
project
Project Project E-mail, Once a Weekly - Keeping - Weekly
Sponsor – Manager Phone week Project the project project
Tim Mills Status sponsor status
Report informed report
about the -
project
Project Event E-mail Once a New ideas - Providing - Planned
Manager Organize week about the supports, requiremen
r project information
ts list
organization
- Project
al level organizatio
nal plan
- Change
request
Form
Lynn Event Newspa Once Announceme - Informing - Fliers
Residents, Organize per, nt of the the -
and r Social Australian community Newspaper
Communit Media Grand Prix and residents - Social
y about the Media
project campaign
content
Vendors & Event E-mail, Once a Pre- - Discuss the - Request
Catering Organize Phone month commission community list
Suppliers r Event Plan expectations - List of
from the the goods
vendors - Beverage
- Prepare the menu
menu and - Food
cuisine Menu
Artists & Event E-mail Once a Pre-
Performers Organize month commission
r Event Plan
Lynn PD Program Face to Once Pre- - Provide - Safety
and Coordina Face commission provision of requiremen
Event Management 9
Project Budget
The direct advantages to the Victorian economy are the expenses of interstate and
overseas visitors who come to Victoria for the Grand Prix or amplify their stay in Victoria,
and the price of staying in Victoria for an occasion in Victoria. All interstate or remote places
grand prix expenses were deducted from this. This is summarized within the table below.
Event Management 10
The project estimates also involve the following fixed costs where the fixed amount
will be paid to the respective companies while signing the contract(Jones, 2014):
Sign Contracts $5,000 Confirming the artists with the Artists Management
(participants) Company for the Murals. Here the company will be paid
the entire fees in advance.
Sign Contracts $3,000 Here the event fee will be paid to the Entertainment
(Entertainment) Company in advance.
Sign Cleaning $3,500 Here the Cleaning company will be paid the fixed fees in
Contract advance while signing the contract.
Event Management 11
Fees
The proposed Rule 50 regulates fees for the purposes of Article 37 of the Act. Section
37 allows AGPC to move the unmanned vehicle to a convenient region when parked in a
chosen or certain access area in the course of a race. The proposed rate for the proposed rule
is a unit charge of 20 ($279 for financial 12 months 2016-2017) for towing an automobile,
daily or five fees whilst the automobile is not maintained in a convenient place. These
charges are not consequences and reflect charges incurred through AGPC when it comes to
car towing and garage.The cost baseline will only be changed when there is a change or
changes in the scope statement, which also means that the project plan was not well-
structured and planned(Kerzner, 2002). In this case, if the 10% contingency reserves are
approved by the sponsor, the project doesn’t require any immediate changes to the cost
baseline(Goldblatt, 1997); reversely, if the contingencies are not approved, we may cut down
the cost by reducing expenses in Event Execution phases were the following example
The given schedule baseline leads to finish this project no later than June 30th, 2020,
and the estimated baseline schedule is June 31, 2021, which is a day later than the projected
Event Management 12
finish date; There are two options for our team, first, talk to the sponsor and ask for an
additional days, or second, go back and reschedule our planned activities to make certain
adjustments to fit the time frame(Parent and Chappelet, 2017). The followings are the tasks
The total estimated work baseline is 4,710.88 hours, which is greater than the actual
completion hour of 4,449.68h by 261.2, which means the project team is not spending the
The project is to design and hold a two weeks event about art festival named Australian
Grand Prix. The duration of the project is from Sep 19, 2019, to Jun 30, 2020. And the budget
of the project is about 150,000 US dollars. After the creation of work breakdown structure,
our major deliverables include community research, project management, event design, artist,
food vendor, entertainment, event conduction and clean-up. At present, after the cost and
After the schedule and cost estimation and submission, a one-day delay and an
Event Management 13
Gantt Chart
Event Execution & Monitoring 149 days Mon 1/6/21 Thu 7/30/21
A risk management plan is a formal process for a group to identify, assess and deal
with risk factors in a systematic manner. The Grand Prix will continue at Albert Park until
2023, and regulations remain an important safety tool for future events. The proposed rules
are basically the same as the previous ones, with minor changes to increase clarity and
Assessing the fees and benefits of extra regulatory measures calls for an assessment of
the regulatory environment if no guidelines are proposed. This “baseline” describes presently
applicable legal guidelines and rules which may cowl the sports predicted of the proposed
rules. Some of these can be relevant, consisting of land use guidelines, crook laws, and laws
If no AGPC policies are proposed, they should construct on an existing casual crime
matrix and crook regulation for insurrection manipulate purposes. These consist of the
Victorian Criminal Act of 1958 (including belongings harm and civilian arrest provisions),
the unlawful series and procession regulation of 1958, and normal regulation crimes together
The Summary of the 1966 Criminal Act contains many provisions for retaining public order.
Victoria cops can intervene with or harass a ramification of activities in public, including:
Event Management 16
Wilful trespass
Property destruction
Obstructing traffic
The 1958 Criminal Act additionally includes many provisions that may be applicable to the
control of massive numbers of Grand Prix members and the preservation of public order in
These regulations had been first created in 1996 and revised in 2006, as the policies for
Victoria's predominant sporting activities have changed with the advent of the Major Sports
Events Act (MSEA) 2009. This law passes regulation of key aspects of predominant sporting
occasions. Sporting activities such as shopping offers, crowd management, and on-web page
advertising, unauthorized marketing and price tag resale. The Major Sports Events Act of
2009 presents all crowd manipulate and some hotfixes, but they are now not enabled in
Grands Prix. It is considered useless to apply laws on this context because they offer a more
structured set of controls for specific occasion situations. Only provisions of the Major Sports
This competition has no other felony controls, however it has precise provisions to make
sure that the methods for organizing principal carrying events do not interfere with the
walking of the Grand Prix. Several of the proposed policies provide authority to modify
crowds, most of which might be duplicated within the 2009 Major Sports Events Act. In
ladders, access or exit, throwing or kicking projectiles, blocking off the view of citizens, or
the use of speakers without permission. The rules for copy in statute are nearly or exactly the
While the above regulatory matrix can empower a couple of stakeholders to clear up
problems bobbing up from Grand Prix businesses, event organizers are the ones with most
concerned within the safe and green operation of the event. It is not sufficient to provide to
Some of the powers hooked up within the 1998 Royalland Reserve (Albert Park
Reserve and Albert Reserve) are a part of the proposed guidelines (disturbance of vegetation
and fauna, prohibition of business pastime). Please be aware that that is related to a similar
trouble. Based on this, it can be stated that the present regulatory matrix can be used to
Conclusion
The Project Manager and the project team will carry out tests at planned periods at
some stage in the task to make sure that all methods are being efficiently applied and
achieved. The great supervisor will offer each day fine management and conduct technique
audits on a weekly basis, monitor technique overall performance metrics, and guarantee all
Event Management 18
the fine supervisor will meet with the Project Manager and evaluation of the diagnosed
discrepancies. The Project Manager will schedule regularly occurring undertaking, control,
and report reviews. In these critiques, an agenda object will encompass a review of
assignment techniques, any discrepancies and/or audit findings from the nice supervisor, and
References
Goldblatt, J. J. (1997) Special events: best practices in modern event management. Van
Nostrand Reinhold.
Kerzner, H. (2002) Strategic planning for project management using a project management
maturity model. John Wiley & Sons.
Lewis, J. P. (1995) Project planning, scheduling, and control: A hands-on guide to bringing
projects in on time and on budget. Irwin.
Morris, P. W. and Hough, G. H. (1987) ‘The anatomy of major projects: A study of the
reality of project management’.
Mulcahy, R. (2011) PMP Exam Prep: Rita’s Course in a Book for Passing the PMP Exam.
RMC Publications, Inc.
Newell, M. and Grashina, M. (2003) The project management question and answer book.
Amacom.
Parent, M. M. and Chappelet, J.-L. (2017) Routledge handbook of sports event management.
Routledge.
Veal, A. J. and Burton, C. (2015) Research methods for arts and event management.
Event Management 20
Appendix A
price of a huge event may be measured using direct costs, input-output modelling,
computableGeneral Equilibrium modelling (CGE), and /or cost benefit analysis respectively.
The input-output model assumes that a big investment inside the economic system, inclusive
of keeping a huge event, can have a ripple impact on other industries, and increase in
manufacturing, employment, and profits. In comparison, the CGE model assumes that the
economy has restrained assets, and that massive investments, together with protecting a big
event, can divert resources from other productive activities. In 2007, the Chief Auditor of
Victoria made a public funding document on essential events. The auditor concluded that the
input-output evaluation became insufficient for assessing the economic effect of major
activities (that is, activities that receive more than $10 million in funding of the government
yearly). Under this approach, the estimated financial impact of the event is typically large
than the estimate based on the CGE model. In 2005, AGPC outsourced the National Institute
of Economic and Industry Research (NIEIR) to conduct a monetary evaluation of the Grand
Prix the use of input-output evaluation. They estimate that gross state product (GSP) will
boom from $1.563 million to $174.8 million due to the 2005 Grand Prix, with next figures
suggesting guided tourism ($9.1 million). As explained above, the input-output evaluation
and CGE simulation use one of the methods and assumptions to degree the financial impact
of major event, so the outcomes of the NIEIR and Audit Committee reports are not directly
compared.
Appendix B
Event Management 21
Rule 17-36. You can request delivery of an item in a stated location (carried out inside a
stated vicinity) or policies 39 and 40 (creative distribution or item sale). Rule 42 requires an
authorized man or woman or police officer to inspect for the duration of the race and any
baggage or different reservoirs that are intended to be carried or carried into the said place,
and so forth allows you to make requests to those who intend or enter the place for opening
bags using portable equipment. Anyone who refuses to conform to this request outside of this
region may not entre the stated region in the course of their career. The maximum penalties
for violating this rule is 20 penalty units. Rule 43 permits an authorized person or police
officer to train or to leave a chosen vicinity or seat if she or he refuses to reveal a price ticket
and the legal person or police officer can supply goods or merchandise. Rule 44 states that if
a person in authority or a police officer unearths that there may be a justifiable cause for
committing a crime in step with a sure rule, the authorized man or woman or police officer
can presents that you can order to go away, a included vicinity, or an area that is blanketed.
Appendix C
acts during a precise length (as described in Rule 5, which begins 12 weeks before the care
duration and it ends in 4 weeks). This can interfere with secure and orderly paintings
performance in declared regions, along with unauthorized admission to work areas. The most
penalties for violating this rule is 20 penalty units. Rule 48 permits a certified character or
police officer to train a person to go away marketed vicinity if he or she interferes with, or
compromises the provision of a commercial enterprise or service. The maximum penalty for
violating this rule is 20 penalty units. Rule 49 presents for the exclusion of certain durations
Event Management 22
at certain places, which prevent a person from working effectively and orderly for a unique