EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements for SAEP-1160 Database (Selection of Welds for NDT shall meet SAEP-1160 Reqmts)
Weld Selection for NDT shall be identified in design along with the
Project NDE
Welding specification per line class & per line (SAES-L-310, Sect 7) This
Spec
is set forth in a proposed project NDE specification for owner Inspector
A1 Reqmt,
approval (PID responsibility per ASME B31.3 & CSD).
SAES-L-310,
Follow the NDE SATIP & NDE Process Control Procedure
Section 7
Page 1 of 23
Initial production work of contractor welders shall be monitored by SAEP-324,
A7
the project inspector to determine their ability to make sound welds. Para. 6.2.6
Page 2 of 23
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Selection of Welds for NDE (On-Plot Piping & Structures) SAIC-W-2015 WELD-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
The progressive examination shall be limited to the specific welder with SAES-W-011,
A9
the defective welds. Para. 17.1.9
The last acceptable weld is defined as a weld that has been examined
SAES-W-011,
A10 and accepted by both RT (or UT) and all other specified NDT methods
Para. 17.1.9
(visual, PT, MT).
Initial Testing of Newly Certified Welders (JCC cards have been issued) ... Selection shall be based as follows:
1) Welders shall prove themselves capable of quality welding at the start of production.
B 2) Quality welding is clearly defined below as related to the start of a Project.
3) Project NDE Specs (Notes) or Process Control Procedure
shall specify initial quality to maintain qualifications.
Initial 3* socket welds for each welder are selected for RT.
SAEP-324,
B2 Welders shall meet all requirements listed in
Para. 6.2.6
SAIC-W-2037.
C SAES-W-011, Section 17.5 (NDT Coverage) & ASME B31.3 NDE Selection Requirements
Page 3 of 23
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Selection of Welds for NDE (On-Plot Piping & Structures) SAIC-W-2015 WELD-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
NDT Coverage
All welds are inspected per ASME B31.3 & SAES-W-011.
SERVICE CATEGORY IS DESIGNATED &
KNOWN: A) CATEGORY D = D
B) CATEGORY M = M
C) NORMAL SAES-W-011,
C1
SERV = N Para. 17.5
D) SEVERE CYCLE = S
NEVER SELECT OR EVALUATE NDE WITHOUT USING THE
CORRECT SERVICE CATEGORY AND CODE CRITERIA!
SEE ATTACHMENT 2 (ASME TABLE 341.3.2)
RT Exams
For welds below 100% RT requirements, selection of welds is based on
SAES-
C4 the weekly weld production at a minimum. The detailed requirements of
W-011,
SAEP-1160 apply. (Backlog basis = 7 days)
Para. 17.5.2
For on-shore piping, at least 10% of the each week's production weld
(circumferential girth welds), are radiographed for:
a. Carbon steel & low alloy steel for general & hydrocarbon Serv. RT Exams
b. Firewater systems (Interpreted to "normal fluid service") SAES-
C7
c. Shop fabricated pipe matls for low temp service below -18°C W-011,
d. Shop fabricated alloy steel, Stainless steel nonferrous materials for all Para. 17.5.2.1
services except Category D fluids.
Shop is an indoor facility approved by SA Insp per SAIC-L-2031.
Page 4 of 23
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Selection of Welds for NDE (On-Plot Piping & Structures) SAIC-W-2015 WELD-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
For off-shore piping top side piping in Category D fluid service above
0°C (includes all lines over water, over tidal flats, or within 30 m of the
shoreline), 10% of the weekly production welds are random selected for
radiography. These are:
a. Firewater systems SAES-W-011,
C9
b. Raw water system Para. 17.5.2.2
c. Pressure sewer system
d. All open non-pressure vents and drains
(NOTES: a. Stainless steel in chlorinated sea water is excluded.
b. Results are interpreted to "normal fluid service".)
For off-shore top side piping (includes all lines over water, over tidal flats,
or within 30 m of the shoreline), 100% of the welds of piping systems
SAES-W-011,
C10 listed below are selected for radiography:
Para. 17.5.2.2
a. All services other than Category D fluids
b. Stainless steel in chlorinated sea water service.
Where multiple welders are used to weld a particular joint, daily weld
SAEP-1160,
C14 record shall indicate the weld area covered by each welder, ie: Root
Section 6
weld, hot pass, capping etc.
Magnetic Particle Testing & Liquid Penetrant Testing
Magnetic particle testing (MT) for ferromagnetic materials. MT/PT Exams
Liquid penetrant testing (PT) for non-ferromagnetic materials.
C16
Exception: PT shall be allowed for small SAES-W-011,
diameters where MT (yoke) is cumbersome & impractical. This Para. 17.5.3
includes SW
Pressure containing welds, other than butts, 100% MT/PT. MT/PT Exams
Includes Branch
C17
Connections, Weldolets, Sockolets, & Welding Bosses ... Any other SAES-W-011,
Groove welded fittings. Para. 17.5.3.1
MT/PT Exams
All attachment welds on pressurized components that are not
C18 hydrotested after making the attachment weld shall be 100%
SAES-W-011,
examined.
Para. 17.5.3.2
D WELD MODIFICATIONS AFTER FINAL ACCEPTANCE (SEE ALSO SAIC-W-2036, SAIC-W-2013 & SAIC-W-2015)
Engineering Change Notice Procedure* covers such work.
D1 ID, Numbering, NDE & Special Processes are Sch Q, Att. VI
controlled. Tables
NDE Process Control Procedure was followed. Database was used to Special
D2 record NDE results. NDE sequence was followed relative to any special Process
process such as PWHT. SA Inspector witnessed the NDE.
E AWS D1.1 Structural Steel Welding, Repairs & NDE (All Applications of AWS D1.1)
Page 5 of 23
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Selection of Welds for NDE (On-Plot Piping & Structures) SAIC-W-2015 WELD-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
See
Welding & Selection of NDE meets AWS D1.1 requirements:
SAIC-M-2012
A) Visual Examination Criteria
12-
E1 B) Repair Methods &
SAMSS-007,
Required Selection of NDE See
Para.
Attachment 4 for AWS D1.1 Required NDT.
6.1.6
REMARKS:
NOTES: 1) Contractor's NDE Specification (Based on Line Class Tables & Design) & NDE Process Control Procedure shall cover elements
of this checklist and provide clear direction for NDE Service Provider Companies, along with close supervision. This requires training and
coordination between the Prime Contractor supervising the work, any Subcontractor (also supervises work) & the NDE Service Provider.
DO NOT BYPASS THIS CHECKLIST IN LIEU OF A PROJECT NDE SPECIFICATION. USE APPLICABLE ELEMENTS & ATTACHMENTS.
Attachments:
Attachment 1 - SAEP-1160 DATABASE, PROCESS CONTROL TRACKING (By Weld)
Attachment 2 - ASME B31.3 Process Piping Welding Acceptance Criteria (Table 341.3.2)
Attachment 3 - SAES-W-011 Onshore & OffShore NDE Requirements
Attachment 4 - Structural Steel Welding Requirements, Repairs & NDE (AWS D1.1)
REFERENCE DOCUMENTS:
1. SAES-W-011, Welding Requirements for On-Plot Piping, 30 th March, 2005
2. SAEP-324, Certification Review and Registration of Project Welders and Brazers, (30 June, 2003)
3. SAEP-1160, Tracking & Reporting of Welding, NDT and Pressure Testing for Capital Projects (17 July 2006)
4. 12-SAMSS-007, Fabrication of Structural and Miscellaneous Steel (30 April 2005)
5. American Welding Society (AWS) D1.1 Structural Steel Welding Code (Latest Edition)
6. ASME B31.3, Process Piping, (Latest Edition)
Page 6 of 23
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Selection of Welds for NDE (On-Plot Piping & Structures) SAIC-W-2015 WELD-
Attachment 2 - ASME B31.3 Process Piping Welding Acceptance Criteria (Table 341.3.2)
ASME B31.3 EQUAL LEG FILLET WELD (Fig 328.5.2A) - Acceptable Fillet Weld Shape & Contour
Note: Leg Size shall be determined by Fillet Gage* (Properly Used Depending upon the weld contour)
Attachment 2 - ASME B31.3 Process Piping Welding Acceptance Criteria (Table 341.3.2)
Attachment 2 - ASME B31.3 Process Piping Welding Acceptance Criteria (Table 341.3.2)
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Selection of Welds for NDE (On-Plot Piping & Structures) SAIC-W-2015 WELD-
NOTE TO INSPECTORS: Note 2 above (typo error) ... Should read P3, P4 and P5. No P6 applications at SA.
MT & PT REQUIREMENTS
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Selection of Welds for NDE (On-Plot Piping & Structures) SAIC-W-2015 WELD-
Attachment 4 - Structural Steel Welding Requirements, Repairs & NDE (AWS D1.1)
Mill Discontinuities are resolved per AWS D1.1, NDE dispositioned & repaired as per Table 5.4 below.
526.5 (1) = VT, MT or PT .... 526.5 (2) = VT, MT or PT & RT (depending on location, severity) ... 526.5 (3) = VT, MT or PT & RT
Measurement shall be per calipers or Ultrasonic Thickness Meter if excess weld metal removal is checked
REPAIR OF WELD DEFECTS* FOUND DURING NDT(*Prohibited Discontinuity)
UT, MT, PT, RT shall be performed per detailed requirements & Acceptance Criteria Tables of this section.
BEAM & COLUMN SPLICING WELD REPAIRS (NOTICE TO THE CONTRACTOR)
1. Contractor shall have approved WPS & Repair Procedure. Cut edges shall be examined* for discontinuities.
2. Contractor shall specify 100% CJP (complete joint penetration) RT Quality welds as detailed in Procedure.
3. RT OR UT SHALL BE SPECIFIED BY ENGINEER AT 100% on butt-welded load bearing* members.
*Main frames and any extensions that are part of the lateral load carrying system such as splice welds for horizontal
piperack beams or vertical columns supporting piping loads in SA Plants. Other shapes (angles, etc) in non-load
bearing secondary applications are spliced with 100% CJP (10% RT Optional). Visual Exam = OK With Hold Points.
4. Contractor shall specify flush, smooth surface after welding per 5.24.4.1 "as required" for service application.
5. Contractor Inspection (NDE HOLD POINTS): Perform 100% VISUAL ON FIT-UP, ROOT PASS, FINAL
6. Contractor shall notify Authorized SA Inspector of ANY repair or splice weld BEFORE welding.
7. Contractor shall perform supplemental NDT based on Visual Exam (suspect areas, laminations, discontinuities).
QA/QC MGRs & ENGINEER ARE RESPONSIBLE TO IMPLEMENT ABOVE REQUIREMENTS ON PROJECTS.
Attachment 4 - Structural Steel Welding Requirements, Repairs & NDE (AWS D1.1)
Attachment 4 - Structural Steel Welding Requirements, Repairs & NDE (AWS D1.1)
12-SAMMS-007 WELDING INSPECTION REQMTS
12-SAMMS-008 CORRECTION OF ERRORS (REPAIR PROCEDURE SHALL COPY & PASTE ELEMENTS)