You are on page 1of 2

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST

SAIC NUMBER

Essential Operating Facilities (EOF) HVAC Requirements


PROJECT TITLE

SAIC-K-4006
WBS / BI / JO NUMBER

EQUIPMENT ID NUMBER(S)

EQUIPMENT DESCRIPTION

LAYOUT DRAWING NUMBER

REV. NO.

SCHEDULED INSPECTION DATE & TIME

ACTUAL INSPECTION DATE & TIME

SYSTEM ID.

PLANT NO.

EC / PMCC / MCC NO.


QUANTITY INSP.

MH's SPENT

TRAVEL TIME

SAUDI ARAMCO USE ONLY

SAUDI ARAMCO ACTIVITY NUMBER

SAUDI ARAMCO INSPECTION LEVEL

CONTRACTOR INSPECTION LEVEL

REFERENCE

A1

HVAC system for EOF shall be provided with standby system.

SAES-K-002
Para 4.3.1

A2

Buildings located in Class I, Zone 2 or Class I, Division 2 electrical areas


shall be maintained at the positive pressure of 0.1 inch water gauge (NFPA 496 Para 7.4.1)
Note: See Item No. A3 in this SAIC for Control Building

SAES-K-002
Para 5.1.1

A3

Control building shall be maintained at a positive pressure of 0.25 inch


water gauge with all the openings closed.

SAES-K-002
Para 5.2

A4

Auto changeover switches shall be provided between the operating and


standby units. These switches shall be capable of providing changeover
and equal wear and tear between the operating and standby units.

SAES-K-002
Para 4.3.2

A5

If the maximum design capacity of the HVAC system is supplied by two


or more normally operating units, at least one standby unit shall be
provided with a capacity equal to or greater than the capacity of the
largest operating unit.

SAES-K-002
Para 4.3.3.1

A6

In case the maximum HVAC system demand is satisfied by one


operating unit only, the capacity of the standby unit shall be at least
equal to the capacity of the operating unit.

SAES-K-002
Para 4.3.3.2

A7

Alarms shall be provided for all HVAC systems to provide warning of


power loss (from the normal supply) and failure of any portion of the
HVAC system.

SAES-K-002
Para 4.3.4.1

A8

All alarm devices shall be independent of the normal power supply of the
HVAC system

SAES-K-002
Para 4.3.4.2

A9

Individual alarm devices shall be connected to a master alarm in a


location where they can be conveniently observed by an attendant or
other responsible person designated by the management of this
essential operating facility.

SAES-K-002
Para 4.3.4.3

A10

In cases where the facility is not attended full time, the system shall be
connected to an alarm at the security office, utilities office, fire station or
other full-time service unit with which arrangements can be made to alert
the person in charge of this facility

SAES-K-002
Para 4.3.4.3

Page 1 of 2

HVAC

CONTRACTOR / SUBCONTRACTOR

PURCHASE ORDER NUMBER

ACCEPTANCE CRITERIA

QR NUMBER

15-Dec-09

EQPT CODE

SAUDI ARAMCO TIP NUMBER

ITEM
No.

30-Jun-08
DATE APPROVED

WORK PERMIT REQUIRED?

PASS

FAIL

N/A

RE-INSP DATE

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST

SAIC NUMBER

Essential Operating Facilities (EOF) HVAC Requirements


PROJECT TITLE

30-Jun-08
DATE APPROVED

QR NUMBER

SAIC-K-4006
WBS / BI / JO NUMBER

HVAC
CONTRACTOR / SUBCONTRACTOR

REMARKS:

REFERENCE DOCUMENTS:
1-SAES-K-002 -- Air Conditioning Systems for Essential Operating Facilities 31 May, 2004
2-NFPA 496 -- Standard for Purged and Pressurized Enclosures for Electrical Equipment, 2008

Contractor / Third-Party

Saudi Aramco

Construction Representative*

PMT Representative

Work is Complete and Ready for Inspection:


Name, Initials and Date:

T&I Witnessed

QC Record Reviewed

Work Verified

T&I Witnessed

QC Record Reviewed

Work Verified

T&I Witnessed

QC Record Reviewed

Work Verified

Name, Initials and Date:

QC Inspector

PID Representative
Performed Inspection

Work / Rework May Proceed

Name, Initials and Date:

Name, Initials and Date:

QC Supervisor

Proponent and Others


Quality Record Approved:

Name, Sign and Date:

Name, Organization,
Initials and Date:

*Person Responsible for Completion of Quality Work / Test

Y = YES

Page 2 of 2

N = NO F = FAILED

You might also like