You are on page 1of 8

SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.

00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Overhead T&D - High-Potential Withstand Testing SATR-P-3220 3-Jul-18 ELECT-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

A. Preparation for Test

Schedule Q
The personnel conducting the testing must be qualified to operate the test
A1 Att. IV
equipment and also familiar with the cable system and its components.
Sec. 7.3

At all ends from where the test equipment is to be connected, position a


guard or barricade the area to prevent unauthorized access to the SAES-P-107
A2
overhead system under test.(SAES-P-104, Sec. 3.1 and S A Pre- Sec. 3.1
Commissioning Form # P-041 & Form # P-042)

Check the DC high-potential test set for proper operation. Ensure that the
input voltage to the test set is regulated. Check test set and test leads at SAES-P-107
A3
testing voltage level (lead in place but not connected). (NEC 110.3 B Sec. 3.3
and Manufacurer's Instructions)

Check clearances at the overhead conductor ends meet the requirements Schedule Q
A4
of SAES-P-107, Sec. 10.5. Sec. 1.3

Use weather protection. (Contractor Schedule Q


A5
Method Statement) Sec. 3.1

Ground adjacent conductors and adjacent objects near the conductor


Schedule Q
A6 ends. Conductors not under test are to remain grounded at all ends.
Sec. 1.3
(NETA ATS, Sec. 7.3.3.2.2)

Remove all grounds from conductor to be "hi-potted". (NETA Schedule Q


A7
ATS, Sec. 7.3.3.2.2) Sec. 1.3

Determine temperature of test set at the time of test. (NETA Schedule Q


A8
ATS, Sec. 5.4.2.3) Sec. 1.3

Determine rate of rise on voltage applied at the time of testing. (NETA Schedule Q
A9
ATS, Sec. 5.4.2.3) Sec. 1.3

Hi-pot test After Mounting or Forming Terminations (SAES-P-104, Sec.


13.2-d) - Check that termination have creepage distance per SAES-P-
104, Sec 6.12 summarized in the table below:

Minimum Creepage Distance


Termination (in mm)
Voltage Rating Indoor Outdoor
(@ 25mm/kV L-L) (@ 40mm/kV L-L)

5 kV 125 200 SAES-P-107


A10
Sec. 3.1
6/10 kV 250 400

15 kV 375 600

Saudi Aramco: Company General Use


12/20 kV 500 800

35 kV 875 1,400

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER

Overhead T&D - High-Potential Withstand Testing SATR-P-3220 3-Jul-18 ELECT-


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Hi-pot Test After Mounting or Forming Terminations - Check that


terminations are not connected to the equipment. ( Note: If conductors are SAES-P-107
A11
left connected to the equipment, the hi-pot shall not exceed the rating of Sec. 3.1
the equipment). (SAES-P-104, Sec. 13.2-d)

Hi-pot Test After Mounting or Forming Terminations - Check that there are
SAES-P-107
A12 sufficient clearances from enclosures and other adjacent objects. (SAES-
Sec. 3.1
P-104, Sec. 13.2-d)

The medium conductors shall be tested in accordance to the voltage level


listed below. (SAES-P-104, Sec. 13.2, Table 3)

DC High-Potential Field Test Voltages


Conductor Voltage Rating
After installation - before cable is placed SAES-P-107
A13 in regular service Sec. 3.1
5kV or 6/10kV 36 kV

15 kV or 12/20 kV 64 kV

35 kV 100 kV

Test voltages shall not exceed 80 percent of conductor manufacturer's


factory test value or the maximum test voltage in attachment 1, Table Schedule Q
A14
10.6. (SAES-P-104, Sec. 3.1 and S A Pre-Commissioning Form # P-041 Sec. 1.3
& Form # P-042)

Check the insulation resistance of the conductor using a 5000 volts dc


SAES-P-107
A15 megger tester. (SAES-P-104, Sec. 3.1 and S A Pre-Commissioning Form
Sec. 3.1
# P-041 & Form # P-042)
Perform DC High-potential testing in accordance with conductor and test
SAES-P-107
A16 instrument manufacturer recommendations. (NEC
Sec. 3.3
110.3 B)

Apply the test voltage slowly in a minimum of five equal increments until
maximum test voltage is reached, with no increment exceeding the
voltage rating of the conductor, and with each voltage step being held for SAES-P-107
A17
an equal interval of time long enough to allow the leakage current to reach Sec. 3.1
stability, approximately 1 to 2 minutes. (SAES-P-
104, Sec. 3.1, S A Pre-Commissioning Form # P-041 & Form # P-042)

Reading of leakage current and voltage shall be recorded at the end of


each minute prior to increasing to the next specified voltage level.
NOTE: A linear increase in leakage current is expected, and it should SAES-P-107
A18
stabilize or decrease from the initial value at each step. Sec. 3.1
(SAES-P-104, Sec. 13.6 and S A Pre-Commissioning Form # P-041 &
Form # P-042)

Plot test voltage versus leakage current on graph paper as the test
progresses. NOTE: Any excessive or non-linear increase in leakage
current can indicate imminent cable failure. Discontinue the test and, SAES-P-107
A19
consult the manufacturer for recommendations. (SAES- Sec. 3.1
P-104, Sec. 13.6 and S A Pre-Commissioning Form # P-041 & Form # P-
042)

Calculate the resistance of the cable at each step. Note: At any step
where the calculated leakage resistance decreases approximately 50% or
more of that of the next lower voltage, discontinue the test to prevent SAES-P-107
A20
conductor failure and to retain the conductor in a serviceable condition Sec. 3.3
until a replacement conductor is available. (NEC
110.3 B and Manufacurer's Instructions)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER

Overhead T&D - High-Potential Withstand Testing SATR-P-3220 3-Jul-18 ELECT-


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Upon satisfactory completion of test, connect conductors to equipment.


SAES-P-107
A21 Tighten connectors to manufacturer recommended torque levels. (NEC
Sec. 3.3
110.3 B and Manufacurer's Instructions)

The results of all tests performed on conductors rated 5 KV and above


shall be documented on the Saudi Aramco H. V. Cable Test Record Form SAES-P-107
A22
7823-ENG. (SAES-P-104, Sec. 13.6 and S A Pre-Commissioning Form # Sec. 3.1
041 & Form # P-042)

Appropriate records shall be made, as indicated in the test result form.


SAES-P-107
A23 (SAES-P-104, Sec. 13.6 and S A Pre-Commissioning Form # 041 & Form
Sec. 3.1
# P-042)

Insure that the input voltage to the test set is regulated. SAES-P-107
A24
(NEC 110.3 B and Manufacurer's Instructions) Sec. 3.3

Current- sensing circuits in test equipment shall measure only the leakage
current associated with the cable under test and shall not include internal SAES-P-107
A25
leakage of the test equipment. Sec. 3.3
(NEC 110.3 B and Manufacurer's Instructions)

Record wet-and dry-bulb temperatures or relative humidity and Schedule Q


A26
temperature. (NETA ATS, Sec. 5.4.2.3) Sec. 1.3

Test each section of conductor individually.


SAES-P-107
A27 (SAES-P-104, Sec. 3.1 and S A Pre-Commissioning Form # 041 & Form #
Sec. 3.1
P-042)
Individually test each conductor with all other conductors grounded.
SAES-P-107
A28 Ground all shields. (SAES-P-104, Sec. 3.1 and S A Pre-Commissioning
Sec. 3.1
Form # 041 & Form # P-042)
Termination shall be adequately corona-suppressed by guard ring, field
Schedule Q
A29 reduction sphere, or other suitable methods as necessary.
Sec. 1.3
(NETA ATS, Sec. 7.3.3.2.4)

Insure that the maximum test voltage does not exceed the limits for
terminations specified in ANSI/IEEE Standard 48, IEEE 386, S A Pre- Schedule Q
A30
Commissioning Form # 041 & Form # P-042, or manufacturer's Sec. 1.3
specifications.

Apply a dc high-potential test in at least five equal increments until


maximum test voltage is reached. No increment shall exceed the voltage
rating of the cable. Record dc leakage current at each step after a SAES-P-107
A31
constant stabilization time consistent with system charging current. Sec. 3.1
(SAES-P-104, Sec. 3.1 and S A Pre-Commissioning Form # P-041 &
Form # P-042)

Raise the conductor to the specified maximum test voltage and hold for 15
minutes on shielded cable and five minutes on no shielded cable. Record
SAES-P-107
A32 readings of leakage current at 30 seconds and one minute and at one
Sec. 3.1
minute intervals thereafter. (SAES-P-104, Sec. 3.1 and S A Pre-
Commissioning Form # P-041 & Form # P-042)

Reduce the conductor test potential to zero and measure residual voltage
SAES-P-107
A33 at discrete intervals. (SAES-P-104, Sec. 3.1 and S A Pre-Commissioning
Sec. 3.1
Form # P-041 & Form # P-042)
Apply grounds for a time period adequate to drain all insulation stored
SAES-P-107
A34 charge. (SAES-P-104, Sec. 3.1 and S A Pre-Commissioning Form # P-
Sec. 3.1
041 & Form # P-042)

B. TEST EQUIPMENT AND MATERIALS CRITERIA

Schedule Q
B1 Test shall be performed using a high-potential tester. Att. IV
Sec. 7.1
Schedule Q
B2 The test equipment calibration cycle shall not exceed twelve months. Att. IV
Sec. 7.1

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER

Overhead T&D - High-Potential Withstand Testing SATR-P-3220 3-Jul-18 ELECT-


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Test Equipment Manufacturer: Serial Number:

Scale Range and accuracy: Calibration date:

Calibration Company and Technician: Calibration Expiration Date:

C. TEST RESULTS

Note: Use applicable MV Cable Test Report Forms (Attachments 1 to 6) for recording of test data.

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

The step voltage slope should be reasonably linear for the graphic plots of
Schedule Q
C1 leakage current versus step voltage at each increment. (NETA
Sec. 1.3
ATS, Sec. 5.4.1.5)
Perform a physical inspection of the overhead feeders to ensure any
Schedule Q
C2 damage to the poles, conductors at termination points, insulators,
Sec. 6.4
jumpers, cable supports, stays etc. prior to energization.

Capacitive and absorption current should decrease continually until


Schedule Q
C3 steady state leakage is approached for the graphic plots for leakage
Sec. 1.3
current versus time at the final test voltage. (NETA ATS, Sec. 5.4.1.5)

Test results are acceptable and in accordance with Saudi Aramco


Schedule Q
C4 Engineering Standards and contractual requirements. (NETA
Sec. 1.3
ATS, Sec. 5.4.1.5 & Sec. 7.3.3.3.2.4.2)

REMARKS:

REFERENCE DOCUMENTS:
1. Schedule G -- Material, Tools and Equipment (Pro Forma MP-IK-LS Contract), Contract Specific
2. Schedule Q -- Quality Requirements (Pro Forma Contract), Contract Specific
3. SAES-P-104 Wiring Methods and Materials 01 January 2018
4. SAES-P-107 Overhead Distribution Systems 19 October 2008
5. NFPA 70 National Electrical Code (NEC) 2014 Edition
6. Acceptance Testing Specifications for Electric Power Distribution Equipment and Systems- NETA (2009)
7. SA Pre- Commissioning Form # P-000 Testing Guide Lines, Issue Date (March 2006)
8. S A Pre-Commissioning Form # P-041 High Voltage Cables (5kV-15kV-35kV), Issue Date (March 2006) - supersedes S A Pre-Commissioning
Form # P-004 Medium Voltage Cables, Issue Date (10/97)
9. S A Pre-Commissioning Form # P-042 High Voltage Cables (69kV-115kV), Issue Date (March 2006) - supersedes S A Pre-Commissioning
Form # P-005 High Voltage Cables, Issue Date (10/97)
ATTACHMENT DOCUMENT: HI-POT TEST REPORT FOR MV CABLE

NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
states
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
concerned
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the manufacturer

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE APPROVED QR NUMBER

Overhead T&D - High-Potential Withstand Testing SATR-P-3220 3-Jul-18 ELECT-


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

indicates compliance with appropriate standards or performance in a specified manner.

Contractor / Third-Party Saudi Aramco


Technician Performing Test* PMT Representative
Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed Work Verified
Name, Title, Department,
Name, Initials and Date:
Company, Initials and Date:

QC Inspector PID Representative


Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Overhead T&D - High-Potential Withstand Testing SATR-P-3220 3-Jul-18 ELECT-

Attachment 1 - HI-POT TEST REPORT FOR MV CABLE


PROJECT DATA
B.I. or W.O. No. _________________________________________________________ DATE: ____________________________
PLANT NO:________________________________________________________________________________________________
LOCATION ________________________________________________________________________________________________

CABLE DATA
CIRCUIT # OR DESIGNATION _______________________________________________________________________________
CABLE SIZE:_______________________ CABLE LENGTH ___________________ RATED VOLTAGE: ___________
INSULATION AND JACKET TYPE: _______________________________________ INSULATION THICKNESS: ____________
MAX. LEAKAGE CURRENT AFTER 100% TEST VOLTAGE APPLIED: _______________________________________________
CABLE TEST VOLTAGE : ________________ NOTE: REDUCE THE CABLE TEST VOLTAGE LEVEL AND HOLD TIME ACCORDINGLY,
TEST HOLD TIME IN MINUTES:_____________ WHEN PERFORMING THE TEST WITH ELBOW CONNECTOR AND/OR EXISTING CABLE.
GENERAL TEST RECORD
CABLE ACCEPTABLE : _______________________________________ Not ACCEPTABLE: ____________________________
TEMPERATURE: ______________ % RELATIVE HUMIDITY: ___________________WEATHER CONDITIONS: _______________
REMARKS:________________________________________________________________________________________________
__________________________________________________________________________________________

RESISTANCE TEST
PHASE 1 TO GND PHASE 2 TO GND PHASE 3 TO GND (MEGGER)
TEST VOLTAGE
& HOLD TIME Leakage Cable Leakage Current Cable Leakage Cable
Current (μA) Resistance (μA) Resistance Current (μA) Resistance PHASE MΩ
Step 1 kV PH 1 - 2
Step 2 kV PH 2 - 3
Step 3 kV PH 3 - 1
Step 4 kV PH 1 - G
Step 5 kV PH 2 - G
15 SEC PH 3 - G
30 SEC
45 SEC POL. INDEX = 1 MINUTE
1 MIN 5 MINUTE
2 MIN
3 MIN
4 MIN
5 MIN
6 MIN
7 MIN
8 MIN
9 MIN
10 MIN
11 MIN
12 MIN POL. INDEX RESULTS
13 MIN If 1.25 - 2.0 good
14 MIN If below 1.0 failure
15 MIN If 1.0 - 1.25 marginal
NOTES: 1. READING AT END OF I MIN. DURATION PRIOR TO RAISING VOLTAGE TO NEXT STEP.
2. BETWEEN EACH STEP RAISE VOLTAGE UNIFORMLY.
3. STOP TEST IF CURRENT STEADILY INCREASES AT CONSTANT VOLTAGE.
4. ATTACH A SEPARATE GRAPH FOR PLOT OF TEST VOLTAGE VERSUS LEAKAGE CURRENT.
TESTED BY: CHECKED BY: WITNESSED BY:

Saudi Aramco: Company General Use


DATE: DATE: DATE:

Saudi Aramco: Company General Use

You might also like