Professional Documents
Culture Documents
00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Overhead T&D - High-Potential Withstand Testing SATR-P-3220 3-Jul-18 ELECT-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Schedule Q
The personnel conducting the testing must be qualified to operate the test
A1 Att. IV
equipment and also familiar with the cable system and its components.
Sec. 7.3
Check the DC high-potential test set for proper operation. Ensure that the
input voltage to the test set is regulated. Check test set and test leads at SAES-P-107
A3
testing voltage level (lead in place but not connected). (NEC 110.3 B Sec. 3.3
and Manufacurer's Instructions)
Check clearances at the overhead conductor ends meet the requirements Schedule Q
A4
of SAES-P-107, Sec. 10.5. Sec. 1.3
Determine rate of rise on voltage applied at the time of testing. (NETA Schedule Q
A9
ATS, Sec. 5.4.2.3) Sec. 1.3
15 kV 375 600
35 kV 875 1,400
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Hi-pot Test After Mounting or Forming Terminations - Check that there are
SAES-P-107
A12 sufficient clearances from enclosures and other adjacent objects. (SAES-
Sec. 3.1
P-104, Sec. 13.2-d)
15 kV or 12/20 kV 64 kV
35 kV 100 kV
Apply the test voltage slowly in a minimum of five equal increments until
maximum test voltage is reached, with no increment exceeding the
voltage rating of the conductor, and with each voltage step being held for SAES-P-107
A17
an equal interval of time long enough to allow the leakage current to reach Sec. 3.1
stability, approximately 1 to 2 minutes. (SAES-P-
104, Sec. 3.1, S A Pre-Commissioning Form # P-041 & Form # P-042)
Plot test voltage versus leakage current on graph paper as the test
progresses. NOTE: Any excessive or non-linear increase in leakage
current can indicate imminent cable failure. Discontinue the test and, SAES-P-107
A19
consult the manufacturer for recommendations. (SAES- Sec. 3.1
P-104, Sec. 13.6 and S A Pre-Commissioning Form # P-041 & Form # P-
042)
Calculate the resistance of the cable at each step. Note: At any step
where the calculated leakage resistance decreases approximately 50% or
more of that of the next lower voltage, discontinue the test to prevent SAES-P-107
A20
conductor failure and to retain the conductor in a serviceable condition Sec. 3.3
until a replacement conductor is available. (NEC
110.3 B and Manufacurer's Instructions)
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Insure that the input voltage to the test set is regulated. SAES-P-107
A24
(NEC 110.3 B and Manufacurer's Instructions) Sec. 3.3
Current- sensing circuits in test equipment shall measure only the leakage
current associated with the cable under test and shall not include internal SAES-P-107
A25
leakage of the test equipment. Sec. 3.3
(NEC 110.3 B and Manufacurer's Instructions)
Insure that the maximum test voltage does not exceed the limits for
terminations specified in ANSI/IEEE Standard 48, IEEE 386, S A Pre- Schedule Q
A30
Commissioning Form # 041 & Form # P-042, or manufacturer's Sec. 1.3
specifications.
Raise the conductor to the specified maximum test voltage and hold for 15
minutes on shielded cable and five minutes on no shielded cable. Record
SAES-P-107
A32 readings of leakage current at 30 seconds and one minute and at one
Sec. 3.1
minute intervals thereafter. (SAES-P-104, Sec. 3.1 and S A Pre-
Commissioning Form # P-041 & Form # P-042)
Reduce the conductor test potential to zero and measure residual voltage
SAES-P-107
A33 at discrete intervals. (SAES-P-104, Sec. 3.1 and S A Pre-Commissioning
Sec. 3.1
Form # P-041 & Form # P-042)
Apply grounds for a time period adequate to drain all insulation stored
SAES-P-107
A34 charge. (SAES-P-104, Sec. 3.1 and S A Pre-Commissioning Form # P-
Sec. 3.1
041 & Form # P-042)
Schedule Q
B1 Test shall be performed using a high-potential tester. Att. IV
Sec. 7.1
Schedule Q
B2 The test equipment calibration cycle shall not exceed twelve months. Att. IV
Sec. 7.1
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
C. TEST RESULTS
Note: Use applicable MV Cable Test Report Forms (Attachments 1 to 6) for recording of test data.
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
The step voltage slope should be reasonably linear for the graphic plots of
Schedule Q
C1 leakage current versus step voltage at each increment. (NETA
Sec. 1.3
ATS, Sec. 5.4.1.5)
Perform a physical inspection of the overhead feeders to ensure any
Schedule Q
C2 damage to the poles, conductors at termination points, insulators,
Sec. 6.4
jumpers, cable supports, stays etc. prior to energization.
REMARKS:
REFERENCE DOCUMENTS:
1. Schedule G -- Material, Tools and Equipment (Pro Forma MP-IK-LS Contract), Contract Specific
2. Schedule Q -- Quality Requirements (Pro Forma Contract), Contract Specific
3. SAES-P-104 Wiring Methods and Materials 01 January 2018
4. SAES-P-107 Overhead Distribution Systems 19 October 2008
5. NFPA 70 National Electrical Code (NEC) 2014 Edition
6. Acceptance Testing Specifications for Electric Power Distribution Equipment and Systems- NETA (2009)
7. SA Pre- Commissioning Form # P-000 Testing Guide Lines, Issue Date (March 2006)
8. S A Pre-Commissioning Form # P-041 High Voltage Cables (5kV-15kV-35kV), Issue Date (March 2006) - supersedes S A Pre-Commissioning
Form # P-004 Medium Voltage Cables, Issue Date (10/97)
9. S A Pre-Commissioning Form # P-042 High Voltage Cables (69kV-115kV), Issue Date (March 2006) - supersedes S A Pre-Commissioning
Form # P-005 High Voltage Cables, Issue Date (10/97)
ATTACHMENT DOCUMENT: HI-POT TEST REPORT FOR MV CABLE
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
states
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
concerned
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the manufacturer
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED
CABLE DATA
CIRCUIT # OR DESIGNATION _______________________________________________________________________________
CABLE SIZE:_______________________ CABLE LENGTH ___________________ RATED VOLTAGE: ___________
INSULATION AND JACKET TYPE: _______________________________________ INSULATION THICKNESS: ____________
MAX. LEAKAGE CURRENT AFTER 100% TEST VOLTAGE APPLIED: _______________________________________________
CABLE TEST VOLTAGE : ________________ NOTE: REDUCE THE CABLE TEST VOLTAGE LEVEL AND HOLD TIME ACCORDINGLY,
TEST HOLD TIME IN MINUTES:_____________ WHEN PERFORMING THE TEST WITH ELBOW CONNECTOR AND/OR EXISTING CABLE.
GENERAL TEST RECORD
CABLE ACCEPTABLE : _______________________________________ Not ACCEPTABLE: ____________________________
TEMPERATURE: ______________ % RELATIVE HUMIDITY: ___________________WEATHER CONDITIONS: _______________
REMARKS:________________________________________________________________________________________________
__________________________________________________________________________________________
RESISTANCE TEST
PHASE 1 TO GND PHASE 2 TO GND PHASE 3 TO GND (MEGGER)
TEST VOLTAGE
& HOLD TIME Leakage Cable Leakage Current Cable Leakage Cable
Current (μA) Resistance (μA) Resistance Current (μA) Resistance PHASE MΩ
Step 1 kV PH 1 - 2
Step 2 kV PH 2 - 3
Step 3 kV PH 3 - 1
Step 4 kV PH 1 - G
Step 5 kV PH 2 - G
15 SEC PH 3 - G
30 SEC
45 SEC POL. INDEX = 1 MINUTE
1 MIN 5 MINUTE
2 MIN
3 MIN
4 MIN
5 MIN
6 MIN
7 MIN
8 MIN
9 MIN
10 MIN
11 MIN
12 MIN POL. INDEX RESULTS
13 MIN If 1.25 - 2.0 good
14 MIN If below 1.0 failure
15 MIN If 1.0 - 1.25 marginal
NOTES: 1. READING AT END OF I MIN. DURATION PRIOR TO RAISING VOLTAGE TO NEXT STEP.
2. BETWEEN EACH STEP RAISE VOLTAGE UNIFORMLY.
3. STOP TEST IF CURRENT STEADILY INCREASES AT CONSTANT VOLTAGE.
4. ATTACH A SEPARATE GRAPH FOR PLOT OF TEST VOLTAGE VERSUS LEAKAGE CURRENT.
TESTED BY: CHECKED BY: WITNESSED BY: