SAUDI ARAMCO TEST REPORT
SATR-X-3201
DC Cable Holiday Testing 3-Jul-18 CP-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

A. TEST PROCEDURE AND CHECKLIST

Conduct a visual and touch inspection of the impressed current anode


cable insulation immediately adjacent to the head of the anode. Anode
A1 SAES-X-400
leads with noticeable "necking", or an obvious reduction in diameter of the
insulation, shall not be used.

Inspect all cables and lead wires for burial for insulation damage
A2 immediately prior to installation. Inspect with a pulse type holiday detector SAES-X-400
set at 18,000 volts DC.

Check the holiday detector before using according to the manufacturer's


A3 SAES-X-400
instructions.

Conduct the inspection with a certified and calibrated pulse type holiday
A4 detector set at 18,000 volts DC. The calibration date shall not exceed 6 SAES-X-400
months.

A5 Do not use anodes with cables that fail the dielectric test. SAES-X-400

Repair of the insulation for buried positive cable by any method is


A6 SAES-X-400
prohibited.

CHECK-OUT INSTRUCTIONS
a) Make sure that the detector is turned OFF.
b) Select the specific voltage required by the CP manufacturer.
A7 c) Attach electrode to the voltage probe assembly and apply to the cable SAES-X-400
to be inspected. The electrode should always make intimate contact with
the surface under inspection.
Ref: Ref: Instrument Instruction Manual

OPERATING METHODS
a) The cable to be inspected must be grounded from the bare cable to
A8 earth at some point along the cable. If individual joints of the cable are to SAES-X-400
be inspected that are not electrically connected, each joint must be
grounded. Ref: Instrument Instruction Manual

c) Occasional checks of the detector operation should be made,


A9 particularly if no holidays are being found. SAES-X-400
Ref: Instrument Instruction Manual

b) V+AE21:AK30In case of LOW output voltage:


a. Check position of voltage selector switches.
A10 SAES-X-400
b. Check battery (is it fully charged?).
c. Check for "parted conductor in voltage probe and/or ground trail.

Inspect positive cables for insulation damage immediately prior to the SAES-X-600
A11
burial of the cables. SABP-X-003, Section 4.2.4.6. Sec. 5

If a holiday is detected, the entire anode/cable assembly shall be


A13 SAES-X-400
replaced.

Saudi Aramco: Company General Use


Negative cables and bond cables to be used for buried service need to be
A14 SAES-X-400
only checked visually for obvious insulation defects.

B. TEST EQUIPMENT AND MATERIALS CRITERIA

C. TEST RESULTS

ITEM
C.TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Cable
Tested Cable description and label
No.

CALIBRATION CERTIFICATE
CERTIFYING COMPANY:
EQUIPMENT NAME AND SERIAL NUMBER:
CALIBRATION STARTING DATE:
CALIBRATION EXPIRATION DATE:
Note: Maximum accepted certification time is 6 month within ARAMCO.

C. TEST RESULTS

D. CONCLUSIONS

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

D1 No Holidays were detected. SAES-X-400

Test results are acceptable and in accordance with Saudi Aramco


D2 N/A
Engineering Standards and contractual requirements.

REMARKS:

REFERENCE DOCUMENTS:
1. Schedule Q -- Quality Requirements (Pro Forma Contract)
2. Schedule G -- Material, Tools and Equipment
3. SAES-X-400 Cathodic Protection of Buried Pipelines, 29 March 2018
4. SAES-X-600 Cathodic Protection of Plant Facilities, 2 April 2018

Contractor / Third-Party Saudi Aramco


Technician Performing Test* PMT Representative
Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed Work Verified
Name, Title, Department,
Name, Initials and Date:
Company, Initials and Date:

QC Inspector PID Representative


Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

Saudi Aramco: Company General Use


QC Supervisor Proponent and Others
Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED