You are on page 1of 6

Construction of 19 Nos Farm Houses at DHA City Karachi

Activity ID Activity Name Original Start Finish Schedule % 2021


Duration Complete
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

301d 11-Aug-20 11-Aug-21 0% 11-Aug-21, Revised Const Schedule of 19 X Farm Houses D


Revised Const Schedule of 19 X Farm Houses DCK
A1000 Project Start 0d 11-Aug-20 0% Project Start, 11-Aug-20

3000 Sq Yd (11 Nos) 301d 11-Aug-20 11-Aug-21 0% 11-Aug-21, 3000 Sq Yd (11 Nos)

Main Building 260d 11-Aug-20 23-Jun-21 0% 23-Jun-21, Main Building


Super Structure 105d 03-Sep-20 09-Jan-21 0% 09-Jan-21, Super Structure
A1240 Formwork & Steel fixing for 2nd & 3rd Slab) 60d 03-Sep-20 16-Nov-20 0% Formwork & Steel fixing for 2nd & 3rd Slab)
A1250 Concreting for Slab (2nd & 3rd) 30d 04-Nov-20 10-Dec-20 0% Concreting for Slab (2nd & 3rd)
A3070 Shuttering & Steel Fixing for Car Porch Slab 30d 10-Nov-20 16-Dec-20 0% Shuttering & Steel Fixing for Car Porch Slab
A3080 Concreting for Car Porch Slab 30d 04-Dec-20 09-Jan-21 0% Concreting for Car Porch Slab
Finishes 260d 11-Aug-20 23-Jun-21 0% 23-Jun-21, Finishes
A1260 Masonry Works 110d 03-Sep-20 15-Jan-21 0% Masonry Works
A1270 Inetrnal Plaster 90d 11-Aug-20 27-Nov-20 0% Inetrnal Plaster
A1280 Primer Painting 30d 17-Aug-20 22-Sep-20 0% Primer Painting
A1290 Fixing of Door Frames 60d 28-Sep-20 10-Dec-20 0% Fixing of Door Frames
A1300 External Plaster 90d 11-Aug-20 27-Nov-20 0% External Plaster
A1310 Internal Painting 65d 10-Sep-20 27-Nov-20 0% Internal Painting
A1320 External Painting 65d 28-Nov-20 15-Feb-21 0% External Painting
A1330 Internal Plumbing Works 95d 28-Nov-20 23-Mar-21 0% Internal Plumbing Works
A1600 External Plumbing Works 90d 21-Jan-21 11-May-21 0% External Plumbing Works
A1610 Roof Tiling (Teracota) 50d 28-Sep-20 27-Nov-20 0% Roof Tiling (Teracota)
A1620 Fixing of False Cieling 60d 10-Dec-20 20-Feb-21 0% Fixing of False Cieling
A1630 Sewerage Chambers 30d 15-Jan-21 20-Feb-21 0% Sewerage Chambers
A1650 Fixing of Doors 40d 05-May-21 23-Jun-21 0% Fixing of Doors
A1660 Fixing of Kitchen Accessories 60d 07-Dec-20 17-Feb-21 0% Fixing of Kitchen Accessories
A3050 Floor Finish (Tiling, Marble, Garanite 130d 28-Nov-20 05-May-21 0% Floor Finish (Tiling, Marble, Garanite
A3060 Fixing of Toilet Accessories 30d 05-May-21 10-Jun-21 0% Fixing of Toilet Accessories
A3170 Fixing of Windows / Almunium Doors 60d 10-Sep-20 21-Nov-20 0% Fixing of Windows / Almunium Doors
Electrical Works 125d 28-Aug-20 27-Jan-21 0% 27-Jan-21, Electrical Works
A1340 Laying of Conduits 40d 28-Aug-20 16-Oct-20 0% Laying of Conduits
A1350 Establishment of Electrical Points 30d 16-Oct-20 21-Nov-20 0% Establishment of Electrical Points
A1360 Providing Wiring 30d 04-Nov-20 10-Dec-20 0% Providing Wiring
A1370 Fixing & Installation of Distribution Boards 30d 28-Oct-20 03-Dec-20 0% Fixing & Installation of Distribution Boards
A1380 Installation of LEds, Switches, Fans etc 40d 10-Dec-20 27-Jan-21 0% Installation of LEds, Switches, Fans etc
Boundary Wall 81d 03-Sep-20 11-Dec-20 0% 11-Dec-20, Boundary Wall
A3090 Excavation for Bed 35d 03-Sep-20 16-Oct-20 0% Excavation for Bed
A3100 Shuttering & Steel Fixing for Bed 25d 10-Sep-20 10-Oct-20 0% Shuttering & Steel Fixing for Bed
A3110 Concreting for Bed 35d 16-Sep-20 28-Oct-20 0% Concreting for Bed
A3120 Shuttering & Steel Fixing for Column 30d 25-Sep-20 31-Oct-20 0% Shuttering & Steel Fixing for Column
A3130 Concreting for Column 30d 06-Oct-20 11-Nov-20 0% Concreting for Column
A3140 Backfilling 20d 11-Nov-20 05-Dec-20 0% Backfilling
A3150 Masonry Works 45d 17-Sep-20 11-Nov-20 0% Masonry Works
A3160 Plaster Works 45d 17-Oct-20 11-Dec-20 0% Plaster Works
Guard Room & Pump Room 172d 31-Oct-20 28-May-21 0% 28-May-21, Guard Room & Pump Room
Sub Structure 65d 31-Oct-20 18-Jan-21 0% 18-Jan-21, Sub Structure
A1390 Excavation for Foundation 30d 31-Oct-20 07-Dec-20 0% Excavation for Foundation
A1400 Steel Fixing for Footing & Short Column 30d 04-Nov-20 10-Dec-20 0% Steel Fixing for Footing & Short Column
A1410 Shuttering for footing & Short Column 25d 09-Nov-20 09-Dec-20 0% Shuttering for footing & Short Column
A1420 Concreting for Foundations 25d 11-Nov-20 11-Dec-20 0% Concreting for Foundations
A1430 Back Filling upto NGL 30d 19-Nov-20 25-Dec-20 0% Back Filling upto NGL
A1440 Steel / Shuttering for Plinth Beams 25d 02-Dec-20 31-Dec-20 0% Steel / Shuttering for Plinth Beams

Remaining Work Milestone Page 1 of 6


Prepared By:- Engr. Syed Shariq Hassan
Critical Remaining Work summary
Construction of 19 Nos Farm Houses at DHA City Karachi
Activity ID Activity Name Original Start Finish Schedule % 2021
Duration Complete
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

A1450 Concreting for Plinth Beams 25d 04-Dec-20 04-Jan-21 0% Concreting for Plinth Beams
A1460 Backfilling upto Plinth Beam 30d 12-Dec-20 18-Jan-21 0% Backfilling upto Plinth Beam
A1470 Flooring (1:4:8) 20d 24-Dec-20 18-Jan-21 0% Flooring (1:4:8)
Super Structure 120d 02-Jan-21 28-May-21 0% 28-May-21, Super Structure
A1500 Steel Fixing for Column upto Bracing Beam 40d 02-Jan-21 19-Feb-21 0% Steel Fixing for Column upto Bracing Beam
A1510 Formwork for Column 40d 07-Jan-21 24-Feb-21 0% Formwork for Column
A1520 Concreting for Column 30d 13-Jan-21 18-Feb-21 0% Concreting for Column
A1530 Shuttering for Beams & Slab 30d 11-Mar-21 16-Apr-21 0% Shuttering for Beams & Slab
A1540 Steel Fixing for Bracing Beams & Slab 30d 16-Mar-21 21-Apr-21 0% Steel Fixing for Bracing Beams & Slab
A1550 Concreting for Slab 30d 23-Mar-21 28-Apr-21 0% Concreting for Slab
A1560 Masonry Works 40d 21-Jan-21 11-Mar-21 0% Masonry Works
A1570 Electrical Works 40d 31-Mar-21 18-May-21 0% Electrical Works
A1580 Plastering 40d 27-Jan-21 16-Mar-21 0% Plastering
A1590 Misc. Finishers 60d 16-Mar-21 28-May-21 0% Misc. Finishers
Under Ground Tank 84d 04-Dec-20 16-Mar-21 0% 16-Mar-21, Under Ground Tank
A1640 Concreting for Wall 25d 04-Dec-20 04-Jan-21 0% Concreting for Wall
A1670 Concreting for Top Slab 20d 12-Dec-20 06-Jan-21 0% Concreting for Top Slab
A1680 Construction of Pump room / Misc Work 70d 21-Dec-20 16-Mar-21 0% Construction of Pump room / Misc Work
A3200 Water Proofing 20d 08-Dec-20 31-Dec-20 0% Water Proofing
Swimming Pool 206d 04-Dec-20 11-Aug-21 0% 11-Aug-21, Swimming Pool
A3210 Excavation/Compaction of Earth Fill 45d 04-Dec-20 27-Jan-21 0% Excavation/Compaction of Earth Fill
A3220 Stone Soling 20d 10-Dec-20 04-Jan-21 0% Stone Soling
A3230 Lean 6" Thick (C.C) 20d 04-Jan-21 27-Jan-21 0% Lean 6" Thick (C.C)
A3240 Reinforcement for Pool Bed 42d 12-Jan-21 04-Mar-21 0% Reinforcement for Pool Bed
A3250 Concreting for Pool Bed 30d 20-Jan-21 25-Feb-21 0% Concreting for Pool Bed
A3260 Reinforcement for Walls 42d 26-Feb-21 17-Apr-21 0% Reinforcement for Walls
A3270 Concreting of Walls 30d 19-Apr-21 25-May-21 0% Concreting of Walls
A3280 Water Proofing 25d 25-May-21 24-Jun-21 0% Water Proofing
A3290 3" Thick Fininshing Tiles 55d 05-Jun-21 11-Aug-21 0% 3" Thick Fininshing Tiles
A3300 Drain Channel/Grating 25d 25-May-21 24-Jun-21 0% Drain Channel/Grating
A3310 Motor Room Structure 30d 24-Jun-21 30-Jul-21 0% Motor Room Structure
A3320 Plumbing Works 30d 05-Jun-21 12-Jul-21 0% Plumbing Works
Landscaping Works 197d 03-Sep-20 01-May-21 0% 01-May-21, Landscaping Works
A1690 Backfilling with soil 180d 03-Sep-20 10-Apr-21 0% Backfilling with soil
A3190 Plantation Works 167d 10-Oct-20 01-May-21 0% Plantation Works
A3830 Pavers/Tuff Tiles 167d 10-Oct-20 01-May-21 0% Pavers/Tuff Tiles

2500 Sq Yd (04 Nos) 250d 11-Aug-20 10-Jun-21 0% 10-Jun-21, 2500 Sq Yd (04 Nos)

Main Building 185d 11-Aug-20 23-Mar-21 0% 23-Mar-21, Main Building


Super Structure 79d 18-Sep-20 23-Dec-20 0% 23-Dec-20, Super Structure
A1910 Formwork & Steel fixing for 2nd & 3rd Slab) 45d 18-Sep-20 12-Nov-20 0% Formwork & Steel fixing for 2nd & 3rd Slab)
A1920 Concreting for Slab (2nd & 3rd) 25d 23-Sep-20 23-Oct-20 0% Concreting for Slab (2nd & 3rd)
A2370 Shuttering & Steel Fixing for Car Porch Slab 25d 23-Oct-20 23-Nov-20 0% Shuttering & Steel Fixing for Car Porch Slab
A2380 Concreting for Car Porch Slab 25d 23-Nov-20 23-Dec-20 0% Concreting for Car Porch Slab
Finishes 185d 11-Aug-20 23-Mar-21 0% 23-Mar-21, Finishes
A1930 Masonry Works 80d 03-Sep-20 10-Dec-20 0% Masonry Works
A1940 Internal Plaster 60d 16-Sep-20 27-Nov-20 0% Internal Plaster
A1950 Primer Painting 20d 28-Nov-20 22-Dec-20 0% Primer Painting
A1960 Fixing of Door Frames 30d 15-Feb-21 23-Mar-21 0% Fixing of Door Frames
A1970 External Plaster 60d 11-Aug-20 22-Oct-20 0% External Plaster
A1980 Internal Painting 35d 22-Dec-20 03-Feb-21 0% Internal Painting
A1990 External Painting 33d 26-Dec-20 04-Feb-21 0% External Painting

Remaining Work Milestone Page 2 of 6


Prepared By:- Engr. Syed Shariq Hassan
Critical Remaining Work summary
Construction of 19 Nos Farm Houses at DHA City Karachi
Activity ID Activity Name Original Start Finish Schedule % 2021
Duration Complete
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

A2000 Internal Plumbing Works 65d 11-Aug-20 28-Oct-20 0% Internal Plumbing Works
A2400 External Plumbing Works 60d 30-Dec-20 12-Mar-21 0% External Plumbing Works
A2410 Roof Tiling (Teracota) 30d 23-Oct-20 28-Nov-20 0% Roof Tiling (Teracota)
A2420 Fixing of False Cieling 30d 28-Dec-20 02-Feb-21 0% Fixing of False Cieling
A2430 Sewerage Chambers 25d 30-Nov-20 29-Dec-20 0% Sewerage Chambers
A2440 Fixing of Doors 30d 29-Dec-20 03-Feb-21 0% Fixing of Doors
A2450 Fixing of Kitchen Accessories 25d 11-Aug-20 09-Sep-20 0% Fixing of Kitchen Accessories
A2460 Floor Finish (Tiling, Marble, Garanite 90d 28-Oct-20 15-Feb-21 0% Floor Finish (Tiling, Marble, Garanite
A2470 Fixing of Toilet Accessories 25d 29-Dec-20 27-Jan-21 0% Fixing of Toilet Accessories
A2550 Fixing of Windows / Almunium Doors 30d 11-Aug-20 16-Sep-20 0% Fixing of Windows / Almunium Doors
Electrical Works 95d 25-Sep-20 19-Jan-21 0% 19-Jan-21, Electrical Works
A2010 Laying of Conduits 20d 25-Sep-20 20-Oct-20 0% Laying of Conduits
A2020 Establishment of Electrical Points 30d 20-Oct-20 25-Nov-20 0% Establishment of Electrical Points
A2030 Providing Wiring 20d 20-Oct-20 13-Nov-20 0% Providing Wiring
A2040 Fixing & Installation of Distribution Boards 25d 13-Nov-20 14-Dec-20 0% Fixing & Installation of Distribution Boards
A2050 Installation of LEds, Switches, Fans etc 30d 14-Dec-20 19-Jan-21 0% Installation of LEds, Switches, Fans etc
Boundary Wall 197d 03-Sep-20 01-May-21 0% 01-May-21, Boundary Wall
A3330 Excavation for Bed 15d 03-Sep-20 22-Sep-20 0% Excavation for Bed
A3340 Shuttering & Steel Fixing for Bed 20d 22-Sep-20 16-Oct-20 0% Shuttering & Steel Fixing for Bed
A3350 Concreting for Bed 20d 16-Oct-20 10-Nov-20 0% Concreting for Bed
A3360 Shuttering & Steel Fixing for Column 25d 10-Nov-20 10-Dec-20 0% Shuttering & Steel Fixing for Column
A3370 Concreting for Column 25d 10-Dec-20 09-Jan-21 0% Concreting for Column
A3380 Backfilling 15d 09-Jan-21 27-Jan-21 0% Backfilling
A3390 Masonary Works 30d 28-Jan-21 05-Mar-21 0% Masonary Works
A3400 Plaster Works 30d 26-Mar-21 01-May-21 0% Plaster Works
Guard Room & Pump Room 127d 31-Oct-20 03-Apr-21 0% 03-Apr-21, Guard Room & Pump Room
Sub Structure 55d 31-Oct-20 06-Jan-21 0% 06-Jan-21, Sub Structure
A2060 Excavation for Foundation 20d 31-Oct-20 24-Nov-20 0% Excavation for Foundation
A2070 Steel Fixing for Footing & Short Column 25d 04-Nov-20 03-Dec-20 0% Steel Fixing for Footing & Short Column
A2080 Shuttering for footing & Short Column 25d 09-Nov-20 09-Dec-20 0% Shuttering for footing & Short Column
A2090 Concreting for Foundations 20d 16-Nov-20 10-Dec-20 0% Concreting for Foundations
A2100 Back Filling upto NGL 20d 21-Nov-20 16-Dec-20 0% Back Filling upto NGL
A2120 Steel / Shuttering for Plinth Beams 15d 21-Nov-20 10-Dec-20 0% Steel / Shuttering for Plinth Beams
A2130 Concreting for Plinth Beams 15d 28-Nov-20 16-Dec-20 0% Concreting for Plinth Beams
A2140 Backfilling upto Plinth 20d 07-Dec-20 30-Dec-20 0% Backfilling upto Plinth
A2160 Flooring (1:4:8) 15d 18-Dec-20 06-Jan-21 0% Flooring (1:4:8)
Super Structure 82d 24-Dec-20 03-Apr-21 0% 03-Apr-21, Super Structure
A2170 Steel Fixing for Column upto Bracing Beam 30d 24-Dec-20 30-Jan-21 0% Steel Fixing for Column upto Bracing Beam
A2180 Formwork for Column 30d 30-Dec-20 04-Feb-21 0% Formwork for Column
A2190 Concreting for Column 25d 05-Jan-21 04-Feb-21 0% Concreting for Column
A2200 Shuttering for Beams & Slab 25d 13-Jan-21 12-Feb-21 0% Shuttering for Beams & Slab
A2210 Steel Fixing for Bracing Beams & Slab 25d 16-Jan-21 16-Feb-21 0% Steel Fixing for Bracing Beams & Slab
A2220 Concreting for Slab 25d 23-Jan-21 22-Feb-21 0% Concreting for Slab
A2230 Masonry Works 30d 13-Jan-21 18-Feb-21 0% Masonry Works
A2240 Electrical Works 30d 01-Feb-21 09-Mar-21 0% Electrical Works
A2250 Plastering 30d 20-Jan-21 25-Feb-21 0% Plastering
A2260 Misc. Finishers 30d 26-Feb-21 03-Apr-21 0% Misc. Finishers
Under Ground Tank 87d 28-Nov-20 13-Mar-21 0% 13-Mar-21, Under Ground Tank
A2310 Concreting for Wall 25d 28-Nov-20 28-Dec-20 0% Concreting for Wall
A2320 Formwork for Top Slab 20d 08-Dec-20 31-Dec-20 0% Formwork for Top Slab
A2330 Steel Fixing for Top Slab 20d 15-Dec-20 08-Jan-21 0% Steel Fixing for Top Slab

Remaining Work Milestone Page 3 of 6


Prepared By:- Engr. Syed Shariq Hassan
Critical Remaining Work summary
Construction of 19 Nos Farm Houses at DHA City Karachi
Activity ID Activity Name Original Start Finish Schedule % 2021
Duration Complete
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

A2340 Concreting for Top Slab 20d 24-Dec-20 18-Jan-21 0% Concreting for Top Slab
A2350 Construction of Pump room / Misc Work 45d 18-Jan-21 13-Mar-21 0% Construction of Pump room / Misc Work
A2480 Water Proofing 20d 02-Dec-20 25-Dec-20 0% Water Proofing
Swimming Pool 147d 04-Dec-20 01-Jun-21 0% 01-Jun-21, Swimming Pool
A3410 Excavation/Compaction of Earth Fill 35d 04-Dec-20 15-Jan-21 0% Excavation/Compaction of Earth Fill
A3420 Stone Soling 20d 10-Dec-20 04-Jan-21 0% Stone Soling
A3430 Lean 6" Thick (C.C) 20d 16-Dec-20 09-Jan-21 0% Lean 6" Thick (C.C)
A3440 Reinforcement for Pool Bed 30d 22-Dec-20 27-Jan-21 0% Reinforcement for Pool Bed
A3450 Concreting for Pool Bed 25d 31-Dec-20 30-Jan-21 0% Concreting for Pool Bed
A3460 Reinforcement for Walls 25d 30-Jan-21 02-Mar-21 0% Reinforcement for Walls
A3470 Concreting of Walls 30d 02-Mar-21 07-Apr-21 0% Concreting of Walls
A3480 Water Proofing 20d 10-Mar-21 03-Apr-21 0% Water Proofing
A3490 3" Thick Finishing Tiles 30d 07-Apr-21 13-May-21 0% 3" Thick Finishing Tiles
A3500 Drain Channel/Grating 20d 07-Apr-21 01-May-21 0% Drain Channel/Grating
A3510 Motor Room Structure 20d 20-Apr-21 13-May-21 0% Motor Room Structure
A3520 Plumbing Works 30d 26-Apr-21 01-Jun-21 0% Plumbing Works
Landscaping Works 230d 03-Sep-20 10-Jun-21 0% 10-Jun-21, Landscaping Works
A2360 Backfilling with Soil 230d 03-Sep-20 10-Jun-21 0% Backfilling with Soil
A2490 Plantation Works 230d 03-Sep-20 10-Jun-21 0% Plantation Works
A2500 Paver/Tuff Tiles 190d 03-Sep-20 22-Apr-21 0% Paver/Tuff Tiles

2000 Sq Yd (03 Nos) 278d 11-Aug-20 14-Jul-21 0% 14-Jul-21, 2000 Sq Yd (03 Nos)

Main Building 167d 11-Aug-20 02-Mar-21 0% 02-Mar-21, Main Building


Super Structure 41d 26-Sep-20 16-Nov-20 0% 16-Nov-20, Super Structure
A2580 Formwork & Steel fixing for 2nd & 3rd Slab) 30d 26-Sep-20 02-Nov-20 0% Formwork & Steel fixing for 2nd & 3rd Slab)
A2590 Concreting for Slab (2nd & 3rd) 25d 07-Oct-20 05-Nov-20 0% Concreting for Slab (2nd & 3rd)
A3530 Shuttering & Steel Fixing for Car Porch Slab 25d 10-Oct-20 10-Nov-20 0% Shuttering & Steel Fixing for Car Porch Slab
A3540 Concreting for Car Porch Slab 20d 22-Oct-20 16-Nov-20 0% Concreting for Car Porch Slab
Finishes 158d 11-Aug-20 18-Feb-21 0% 18-Feb-21, Finishes
A2600 Masonry Works 25d 06-Nov-20 07-Dec-20 0% Masonry Works
A2610 Intermal Plaster 15d 12-Nov-20 30-Nov-20 0% Intermal Plaster
A2620 Primer Painting 5d 01-Dec-20 07-Dec-20 0% Primer Painting
A2630 Fixing of Door Frames 5d 07-Dec-20 12-Dec-20 0% Fixing of Door Frames
A2640 External Plaster 5d 12-Dec-20 18-Dec-20 0% External Plaster
A2650 Internal Painting 25d 11-Aug-20 09-Sep-20 0% Internal Painting
A2660 External Painting 30d 06-Nov-20 12-Dec-20 0% External Painting
A2670 Internal Plumbing Works 5d 18-Dec-20 24-Dec-20 0% Internal Plumbing Works
A2940 External Plumbing Works 5d 26-Dec-20 31-Dec-20 0% External Plumbing Works
A2950 Roof Tiling (Teracota) 5d 31-Oct-20 05-Nov-20 0% Roof Tiling (Teracota)
A2960 Fixing of False Cieling 10d 12-Jan-21 23-Jan-21 0% Fixing of False Cieling
A3770 Sewerage Chambers 5d 01-Jan-21 07-Jan-21 0% Sewerage Chambers
A3780 Fixing of Doors 5d 12-Dec-20 18-Dec-20 0% Fixing of Doors
A3790 Fixing of Kitchen Accessories 25d 13-Jan-21 12-Feb-21 0% Fixing of Kitchen Accessories
A3800 Floor Finish (Tiling, Marble, Garanite 20d 24-Dec-20 18-Jan-21 0% Floor Finish (Tiling, Marble, Garanite
A3810 Fixing of Toilet Accessories 5d 12-Feb-21 18-Feb-21 0% Fixing of Toilet Accessories
A3820 Fixing of Windows / Almunium Doors 20d 22-Dec-20 15-Jan-21 0% Fixing of Windows / Almunium Doors
Electrical Works 167d 11-Aug-20 02-Mar-21 0% 02-Mar-21, Electrical Works
A2680 Laying of Conduits 25d 30-Sep-20 30-Oct-20 0% Laying of Conduits
A2690 Establishment of Electrical Points 30d 07-Dec-20 12-Jan-21 0% Establishment of Electrical Points
A2700 Providing Wiring 30d 25-Jan-21 02-Mar-21 0% Providing Wiring
A2710 Fixing & Installation of Distribution Boards 10d 30-Jan-21 11-Feb-21 0% Fixing & Installation of Distribution Boards
A2720 Installation of LEds, Switches, Fans etc 15d 11-Aug-20 28-Aug-20 0% Installation of LEds, Switches, Fans etc

Remaining Work Milestone Page 4 of 6


Prepared By:- Engr. Syed Shariq Hassan
Critical Remaining Work summary
Construction of 19 Nos Farm Houses at DHA City Karachi
Activity ID Activity Name Original Start Finish Schedule % 2021
Duration Complete
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Boundary Wall 157d 16-Sep-20 25-Mar-21 0% 25-Mar-21, Boundary Wall


A3550 Excavation for Bed 15d 16-Sep-20 03-Oct-20 0% Excavation for Bed
A3560 Shuttering & Steel Fixing for Bed 20d 05-Oct-20 28-Oct-20 0% Shuttering & Steel Fixing for Bed
A3570 Concreting for Bed 20d 28-Oct-20 21-Nov-20 0% Concreting for Bed
A3580 Shuttering & Steel Fixing for Column 25d 21-Nov-20 22-Dec-20 0% Shuttering & Steel Fixing for Column
A3590 Concreting for Column 25d 22-Dec-20 21-Jan-21 0% Concreting for Column
A3600 Backfilling 15d 21-Jan-21 09-Feb-21 0% Backfilling
A3610 Masonry Works 30d 09-Feb-21 17-Mar-21 0% Masonry Works
A3620 Plaster Works 30d 17-Feb-21 25-Mar-21 0% Plaster Works
Guard Room & Pump Room 204d 09-Nov-20 14-Jul-21 0% 14-Jul-21, Guard Room & Pump Room
Sub Structure 106d 09-Nov-20 17-Mar-21 0% 17-Mar-21, Sub Structure
A2730 Excavation for Foundation 20d 09-Nov-20 02-Dec-20 0% Excavation for Foundation
A2740 Steel Fixing for Footing & Short Column 25d 20-Nov-20 21-Dec-20 0% Steel Fixing for Footing & Short Column
A2750 Shuttering for footing & Short Column 25d 25-Nov-20 25-Dec-20 0% Shuttering for footing & Short Column
A2760 Concreting for Foundations 20d 03-Dec-20 26-Dec-20 0% Concreting for Foundations
A2770 Back Filling upto NGL 20d 12-Dec-20 06-Jan-21 0% Back Filling upto NGL
A2780 Steel / Shuttering for Plinth Beams 15d 06-Jan-21 23-Jan-21 0% Steel / Shuttering for Plinth Beams
A2790 Concreting for Plinth Beams 15d 15-Jan-21 03-Feb-21 0% Concreting for Plinth Beams
A2800 Backfilling upto Plinth 20d 03-Feb-21 27-Feb-21 0% Backfilling upto Plinth
A2830 Flooring (1:4:8) 15d 27-Feb-21 17-Mar-21 0% Flooring (1:4:8)
Super Structure 98d 17-Mar-21 14-Jul-21 0% 14-Jul-21, Super Structure
A2840 Steel Fixing for Column upto Bracing Beam 30d 17-Mar-21 22-Apr-21 0% Steel Fixing for Column upto Bracing Beam
A2850 Formwork for Column 30d 23-Mar-21 28-Apr-21 0% Formwork for Column
A2860 Concreting for Column 25d 29-Mar-21 28-Apr-21 0% Concreting for Column
A2870 Shuttering for Beams & Slab 25d 07-Apr-21 07-May-21 0% Shuttering for Beams & Slab
A2880 Steel Fixing for Bracing Beams & Slab 25d 10-Apr-21 11-May-21 0% Steel Fixing for Bracing Beams & Slab
A2890 Concreting for Slab 25d 15-Apr-21 15-May-21 0% Concreting for Slab
A2900 Masonry Works 30d 21-Apr-21 27-May-21 0% Masonry Works
A2910 Electrical Works 30d 03-May-21 08-Jun-21 0% Electrical Works
A2920 Plastering 30d 03-May-21 08-Jun-21 0% Plastering
A2930 Misc. Finishers 30d 08-Jun-21 14-Jul-21 0% Misc. Finishers
Under Ground Tank 161d 11-Aug-20 22-Feb-21 0% 22-Feb-21, Under Ground Tank
A2970 Formwork for Wall 20d 05-Dec-20 29-Dec-20 0% Formwork for Wall
A2980 Concreting for Wall 15d 12-Dec-20 30-Dec-20 0% Concreting for Wall
A2990 Formwork for Top Slab 20d 19-Dec-20 13-Jan-21 0% Formwork for Top Slab
A3000 Steel Fixing for Top Slab 15d 26-Dec-20 13-Jan-21 0% Steel Fixing for Top Slab
A3010 Concreting for Top Slab 15d 02-Jan-21 20-Jan-21 0% Concreting for Top Slab
A3020 Construction of Pump room / Misc Work 30d 16-Jan-21 22-Feb-21 0% Construction of Pump room / Misc Work
A3760 Water Proofing 10d 11-Aug-20 22-Aug-20 0% Water Proofing
Swimming Pool 168d 12-Dec-20 05-Jul-21 0% 05-Jul-21, Swimming Pool
A3630 Excavation/Compaction of Earth Fill 30d 12-Dec-20 18-Jan-21 0% Excavation/Compaction of Earth Fill
A3650 Stone Soling 20d 18-Dec-20 12-Jan-21 0% Stone Soling
A3660 Lean 6" Thick (C.C) 20d 24-Dec-20 18-Jan-21 0% Lean 6" Thick (C.C)
A3670 Reinforcement for Pool Bed 25d 18-Jan-21 17-Feb-21 0% Reinforcement for Pool Bed
A3680 Concreting of Pool Bed 25d 17-Feb-21 19-Mar-21 0% Concreting of Pool Bed
A3690 Reinforcement for Walls 25d 26-Feb-21 29-Mar-21 0% Reinforcement for Walls
A3700 Concreting of Walls 25d 29-Mar-21 28-Apr-21 0% Concreting of Walls
A3710 Water Proofing 20d 06-Apr-21 30-Apr-21 0% Water Proofing
A3720 3" Thick Finishing Tiles 30d 15-Apr-21 22-May-21 0% 3" Thick Finishing Tiles
A3730 Drain Channel/Grating 20d 27-Apr-21 20-May-21 0% Drain Channel/Grating
A3740 Motor Room Structure 20d 21-May-21 14-Jun-21 0% Motor Room Structure

Remaining Work Milestone Page 5 of 6


Prepared By:- Engr. Syed Shariq Hassan
Critical Remaining Work summary
Construction of 19 Nos Farm Houses at DHA City Karachi
Activity ID Activity Name Original Start Finish Schedule % 2021
Duration Complete
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

A3750 Plumbing Works 30d 29-May-21 05-Jul-21 0% Plumbing Works


Landscaping Works 180d 03-Sep-20 10-Apr-21 0% 10-Apr-21, Landscaping Works
A3030 Backfilling with Soil 180d 03-Sep-20 10-Apr-21 0% Backfilling with Soil
A3180 Plantation Works 177d 03-Sep-20 07-Apr-21 0% Plantation Works
A3640 Paver/Tuff Tiles 177d 03-Sep-20 07-Apr-21 0% Paver/Tuff Tiles

Project Finish 0d 19-Jul-21 19-Jul-21 0% 19-Jul-21, Project Finish

A3040 Project Finish 0d 19-Jul-21 0% Project Finish,

Remaining Work Milestone Page 6 of 6


Prepared By:- Engr. Syed Shariq Hassan
Critical Remaining Work summary