SCOPE :

CATCH BASIN/MANHOLE FABRICATION AND RCP LAYING WORKS

DURATION : 10.00 DAYS

COST SUMMARY :

EARTHWORKS (EXCAVATION,GRAVEL BEDDING,BACKFILLING AND SOIL COMPACTING)


NO. DESCRIPTION QTY UNIT COST
4 HELPER 1 LOT 16,000.00
MASONRY WORKS (RCP PIPE LAYING)
NO. DESCRIPTION QTY UNIT COST
2 MASON
1 LOT 32,000.00
2 HELPER
SAFETY
NO. DESCRIPTION QTY UNIT COST
1 PPE 1 LOT 2,400.00

NET
AMOUNT 50,400.00
2% -WITHHOLDING TAX 0.02 1,008.00
12% -VAT 0.12 6,048.00
10% - PROFIT 0.10 5,040.00
TOTAL CONTRACT COST 62,496.00
10% -RETENTION 0.10 6,249.60

CONTRACTOR : EVALUATED : APPROVED BY:

LEONARD ESGUERRA PHILLINE E.CLARINAN ARIEL L CANTIL


GENERAL SUPERVISOR QUANTITY SURVEYOR PROJECT MANAGER
L.S.E CONSTRUCTION & SERVICES PDPM PDPM