SCOPE : PLUMBING AND SANITATION WORKS

SPAN : ROOM 301 & 302 METERS


DURATION : 23.00 DAYS

MANPOWER OUTPUT :

NO DESCRIPTION RATE/DAY NO.OF DAYS AMOUNT


1.00 FOREMAN 750.00 23.00 17,250.00
0.00 STEELMAN 650.00 0.00 0.00
2.00 MASON/PLUMBER 650.00 23.00 29,900.00
4.00 LABORER 500.00 20.00 40,000.00
TOTAL= 87,150.00

TOOLS AND EQUIPTMENT :

1.00 LUMPSUM 1,000.00 23.00 23,000.00


TOTAL = 23,000.00

NET AMOUNT 110,150.00


2% -WITHHOLDING TAX 0.02 2,203.00
12% -VAT 0.12 13,218.00
10% - PROFIT 0.10 11,015.00
SATETY 10,000.00 10,000.00

TOTAL CONTRACT COST 146,586.00


10% -RETENTION 0.10 14,658.60

PREPARED BY: EVALUATED :

BERNARD U.UNABIA PHILLINE E.CLARINAN


QUALITY CONTROL QUANTITY SURVEYOR
PDPM PDPM

CONTRACTOR : APPROVED BY:

LEONARD ESGUERRA ARIEL L CANTIL


GENERAL SUPERVISOR PROJECT MANAGER
L.S.E LABOR & SERVICES PDPM