JANAUARY 26, 2022

COSTING PROPOSED OFFICE

SUBJECT: PROPOSED OFFICE LOBBY,CUBICLE & CR

SCOPE OF WORKS:
DESCRIPTION
GENERAL REQUIREMENTS Unit Materials Labor TOTAL
Mobilization and Demobilization 1 lot P20,000.00
Delivery of materials and PPE,Supervision 1 lot P20,000
Architectural As Built Plan Permit Processing P10,000
TOTAL P50,000.00
ARCHITECTURAL WORKS OF OFFICE
OFFICE CUBICLE STANDARD FINISH 1 lot 80,000 20,000 P100,000.00
OFFICE LOBBY/MEETING STANDARD FINISH 1 lot 150,000 30,000 P180,000.00
CR AREA RENOVATION BARE/ROUGH FINISH 1 lot 20,000 5,000 P25,000
CONSUMABLES 1 lot 10,000 10,000 P10,000
TOTAL P315,000.00
OVERALL ELECTRICAL WORKS
OVERALL SCOPE OF ELECTRICAL WORKS 1 lot 30,000 10,000 P40,000

OVERALL TOTAL P405,000

TOTAL AMOUNT P405,000.00


DISCOUNTED PRICE: P400,000.00
COMPLETION TIME: 26 weeks from receipt of DP
TERMS: 70 Percent Downpayment, remaining based on progress billing
VAT: Included

Thank you for giving us the opportunity to quote on your requirements and for possible
business engagement with you.

Respectfully Yours,

Engr.Jeffcaster M. Comel