ITEM UNIT QUANTITY PRICE

AREA: CONCRETE SLAB SQ.M 205

MATERIALS:
BITUMINOUS MEMBRANE 3MM THK. ROLLS 28 PHP 86,800.00
BITUMINOUS PRIMER 20L PAIL 5 PHP 17,500.00
MORTAR FOR CANT STRIPS CU.M 2 PHP 4,000.00
EPOXY WORKS GALLON 1 PHP 4,400.00

TOTAL PHP 112,700.00

EQUIPMENT: DAYS 30
BLOWTORCH UNIT 1 PHP 3,000.00
LPG TANK UNIT 1 PHP 2,000.00
LPG TANK REFILLS UNIT 5 PHP 5,000.00

TOTAL PHP 10,000.00

MANPOWER: DAYS 30
APPLICATOR UNIT 1 PHP 22,500.00
LABORER UNIT 1 PHP 19,500.00

TOTAL PHP 42,000.00

CONTINGENCY: LOT PHP 8,235.00

OVERHEAD PLUS TAX LOT PHP 8,646.75

MOBILIZATION/DEMOBILIZATION PHP 6,000.00

GRAND TOTAL: PHP 187,581.75