You are on page 1of 1

NDOZA CONSTRUCTION

BLK. 12 LOT 10, BRAZIL ST., PHASE 3A, TIERRA MONTE BRGY SILANGAN, SAN
MATEO, RIZAL
09202676663 / m3ndoza.con@gmail.com
*QUOTATION*
DATE : NOV. 17, 2022
OWNER : SHOWYA TELECOM
LOCATION : KINGSVILLE VILLAGE, ANTIPOLO, RIZAL
PROJECT : BAR
Sir / Ma'am,

Please find below our price Quotation for your requested scope of works as follows :

Materials Labor
Work Description Unit Qty Total Cost
Unit Cost Total Cost Unit Cost Total Cost
TRELLIS ROOFING
STEEL WORKS

2" x 3" x 1.5mm G.I. TUBULAR STEEL PCS 8.00 1,200.00 9,600.00 450.00 3,600.00 Php 13,200.00

2" x 4" x 1.5mm G.I. TUBULAR STEEL PCS 2.00 1,750.00 3,500.00 650.00 1,300.00 Php 4,800.00
WELDING ROD KGS 3.00 150.00 450.00 60.00 180.00 Php 630.00
CUTTING DISC PCS 5.00 85.00 425.00 34.00 170.00 Php 595.00
GRINDING DISC PCS 2.00 120.00 240.00 48.00 96.00 Php 336.00
12MM DSB PCS 1.00 180.00 180.00 72.00 72.00 Php 252.00
Subtotal: Php 19,813.00
PAINTING WORKS
AUTOMOTIVE PAINT FINISH (ROLLER
LOT 1.00 2,500.00 2,500.00 1,000.00 1,000.00 Php 3,500.00
BRUSH APPLICATION)
Subtotal: Php 3,500.00
ROOF SHEET
3.5MM THK SOLID POLYCARBONATE
LNF 24.00 owner supply 150.00 3,600.00 Php 3,600.00
(BROWN)
T-PROFILE PCS 3.00 owner supply 150.00 450.00 Php 450.00
END CAP PCS 4.00 owner supply 120.00 480.00 Php 480.00
SEALANT PCS 1.00 280.00 280.00 100.00 100.00 Php 380.00
Subtotal: Php 4,910.00
TOTAL: Php 28,223.00
MASONRY WORKS
CONCRETE COUNTER
REINF. CONCTRETE COUNTER LNM 6.80 1,200.00 8,160.00 800.00 5,440.00 Php 13,600.00
CHINA GRANITE COUNTER TOP LNM 4.00 5,000.00 20,000.00 2,300.00 9,200.00 Php 29,200.00
COUNTER WALL TILE SETTING SQM 5.00 owner supply 700.00 3,500.00 Php 3,500.00
Subtotal: Php 46,300.00
PAINTING WORKS
INDUSTRIAL LOOK CONCRETE WALL SQM 7.00 250.00 1,750.00 180.00 1,260.00 Php 3,010.00
Subtotal: Php 3,010.00
TOTAL: Php 49,310.00
CARPENTRY WORKS
COUNTER WOOD CLADDING (HARDIE
PCS 6.00 500.00 3,000.00 200.00 1,200.00 Php 4,200.00
PLANKS)
Subtotal: Php 4,200.00
TOTAL: Php 4,200.00
OTHERS
DROP LIGHTS SETS 4.00 OWNER SUPPLY 500.00 2,000.00 Php 2,000.00
WINE RACK SETS 2.00 2,000.00 4,000.00 800.00 1,600.00 Php 5,600.00
WALL PLANTS RACK LOT OPTIONAL Php -
Subtotal: Php 7,600.00
TOTAL: Php 7,600.00
NET TOTAL: Php 89,333.00

WORK DURATION : 3 WEEKS


TERMS OF PAYMENT : 30 % Downpayment
70 Weekly Progress Billing

Regarding this matter, We would like to express our best gratitude for giving us the opportunity to be on service with you.

Thank you and more power.

Yours Truly,

NIÑO J. MENDOZA

CONFORME