WOOD GURU CONTRACT LABOR WORKS

Salary Order No. : Week 6


Date: : Oct. 23-28 2023

CONTRACT UNIT AMOUNT PAYMENT FOR


SCOPE OF WORKS LEADMAN QUANTITY UNIT PAYABLE CA (-) REMARKS SIGNATURE
AMOUNT TOTAL RELEASE
DRY WALL PARTITION FRAMING & BOARD UP
HESUS 46.21 SQM ₱290.00 ₱13,400.90 - - ₱13,400.90 OK DULY ACCOMPLISHED
BALANCE FROM PREVIOUS WEEK
DRY WALL PARTITION FRAMING & BOARD UP HESUS 91.2 SQM ₱290.00 ₱26,448.00 - - ₱13,224.00 50% ONLY NOT YET SATISFIED

TOTAL PAID: Php.28,500.00 (3.5k,25k),


STAIRS AND FAÇADE JOI 1 LOT ₱52,000.00 ₱23,500.00 ₱18,500.00 ₱1,500.00 ₱17,000.00 BALANCE Php.5,000.00 UPON COMPLETION
OF CANOPY FRAME
ENTRY ROOF CANOPY FRAME JOI 1 LOT ₱4,500.00 ₱4,500.00 ₱4,500.00 - ₱2,250.00 50% ONLY NOT YET SATISFIED
ELECTRICIAN JAMES 1 LOT ₱19,500.00 ₱19,500.00 ₱1,500.00 ₱18,000.00 TOTAL PAID: Php.54,700.00
CONTRACT Price Canopy 6,500.00,
GATE DEMOLITION 1,500.00
CANOPY WORKS, INC. DEMO GATE JOVAN 1 LOT ₱8,000.00 ₱8,000.00 ₱6,000.00 ₱1,500.00 ₱4,500.00
(NOTE: BAL.Php.2,000.00 UPON
INSTALLATION OF ROOF SHEETS
INSTALLATION OF HEADER & ENTRY FALSE
JOVAN 1 LOT ₱1,500.00 ₱1,500.00 ₱1,500.00 ₱500.00 ₱1,000.00 OK FOR PAYMENT RELEASE
COLUMN
KITCHEN JOVAN 1 LOT ₱4,000.00 ₱4,000.00 ₱2,000.00 - ₱2,000.00 OK FOR PAYMENT RELEASE
CONTRACT Price Painting Works:
PAINTING WORKS ALVIN 1 LOT ₱45,000.00 ₱21,000.00 ₱21,000.00 ₱7,000.00 ₱14,000.00 Php. 45,000.00
(NOTE: total CA 7,000.00)
TILING WORKS VICTOR 1 LOT PER ACTUAL, OK FOR PAYMENT RELEASE

INITIAL PAYMENT FOR RELEASE: ₱85,374.90