900x900x1000 concrete MH

01 Excavation 1.20 1.20 1.20 1.73 600.00 1,036.80

02 Screed 1.20 1.20 0.05 0.07 12500.00 900.00

03 Concrete 1 1.20 1.20 0.15 0.22


2 1.20 1.00 0.15 0.36
2 0.90 1.00 0.15 0.27
0.85 18000.00 15,228.00

04 F/W 4 1.20 1.20 5.76


4 0.90 1.00 3.60
9.36 750.00 7,020.00

05 R/F 14 3.10 0.617 26.78


7 4.40 0.617 19.00
45.78 180.00 8240.652

06 Plastering 1 0.9 0.9 0.81


4 0.9 1 3.60
4.41 750 3,307.50

07 Cast iron cover 15,000.00

50,732.95

600x600x800 concrete MH
01 Excavation 0.90 0.90 1.00 0.81 600.00 486.00

02 Screed 0.90 0.90 0.05 0.04 12500.00 506.25

03 Concrete 1 0.90 0.90 0.15 0.12


2 0.90 0.80 0.15 0.22
2 0.60 0.80 0.15 0.14
0.48 18000.00 8,667.00

04 F/W 4 0.90 1.00 3.60


4 0.60 0.80 1.92
5.52 750.00 4,140.00

05 R/F 14 2.40 0.617 20.73


5 3.20 0.617 9.87
30.60 180.00 5508.576

06 Plastering 1 0.6 0.6 0.36


4 0.6 0.8 1.92
2.28 750 1,710.00

07 Cast iron cover 15,000.00

36,017.83
450x450x600 concrete MH
01 Excavation 0.75 0.75 0.80 0.45 600.00 270.00

02 Screed 0.75 0.75 0.05 0.03 12500.00 351.56

03 Concrete 1 0.75 0.75 0.15 0.08


2 0.75 0.60 0.15 0.14
2 0.45 0.60 0.15 0.08
0.30 18000.00 5,406.75

04 F/W 4 0.75 0.80 2.40


4 0.45 0.60 1.08
3.48 750.00 2,610.00

05 R/F 10 1.85 0.617 11.41


5 2.60 0.617 8.02
19.44 180.00 3498.39

06 Plastering 1 0.45 0.45 0.20


4 0.45 0.6 1.08
1.28 750 961.88

07 Cast iron cover 14,000.00

27,098.58

450x750 concrete MH wall & base 150mm tk with 100mm tk con. Cover
01 Excavation 1.00 0.75 0.90 0.68 600.00 405.00

02 Concrete 1 1.00 0.75 0.15 0.11


2 1.00 0.75 0.15 0.23
1 1.00 0.75 0.10 0.08
0.41 15000.00 6,187.50

03 F/W 2 1.00 0.75 1.50


2 1.00 0.90 1.80
3.30 750.00 2,475.00

04 R/F 8 2.10 0.617 10.37


14 1.00 0.617 8.64
5 1.00 0.617 3.09
8 0.60 0.617 2.96
25.05 185.00 4634.287

13,701.79