You are on page 1of 14

Development of a Precast

Concrete Shear-Wall System


Requiring Special Code
Acceptance
Can Bora Precast, prestressed wall panels comprising thin
Research Assistant
Department of Civil and concrete sections are not commonly used as
Environmental Engineering seismic shear walls. Many engineers and code
University of Wisconsin officials view prestressed materials as nonductile,
Madison, Wis.
and the connections between the sandwich wall
panels and the foundation may suffer from brittle
joint failures. The authors have designed a new
load-limiting foundation connection for precast,
prestressed panels used as shear walls that prevents
the development of excessive uplift forces in the
Michael G. Oliva, Ph.D.
Associate Professor
joint. This connection allows precast, prestressed
Department of Civil and Environmental concrete wall panels, such as hollow-core, to act
Engineering as shear walls in resisting seismic loading without
University of Wisconsin relying on wall ductility or causing an anchorage
Madison, Wis.
failure in a thin concrete section of the wall
panel (where a connector is located). This unique
connector allows the wall system to behave unlike
Suzanne Dow Nakaki, S.E.
that anticipated by building-code-defined design
Principal
The Nakaki Bashaw Group Inc. methods. Building codes require the behavior of
Irvine, Calif. new systems to be compared (and proven similar)
with that of code-conforming behavior before being
used. This paper describes the development and
testing of the proposed load-limiting connector and
wall system and the wall design approach needed
to obtain special building code approval for its use.

Roger Becker, P.E.


Vice President, Precasting Division
Spancrete Industries Inc.
Waukesha, Wis.
 PCI JOURNAL
P
recast concrete walls provide
an excellent envelope for low-
rise commercial and industrial
buildings. They are relatively easy to Roof mass
manufacture, structurally efficient,
durable, and attractive. Precast con-
crete walls are also extremely energy
efficient when built with an insulation
wythe. In addition, their desirability to
the owner and design professionals can Force due to
be increased tremendously if they pro-
vide lateral-load resistance. The focus seismic
of this paper is to develop a means for acceleration
practicing engineers to use precast con-
crete members with thin cross sections,
such as hollow-core panels, as shear
walls.
In practice, precast concrete walls
have been used for seismic load re-
sistance by designing them to emulate
cast-in-place shear walls. This is typi-
cally accomplished using ductile ver- Connector
tical reinforcing coupled with splice plate in
sleeves or other devices to create con-
tinuity across horizontal wall joints wall
because some codes prohibit the use of Base shear
prestressing across joints to resist seis-
mic load.1,2
Newer systems have recently been
developed to take advantage of un-
bonded, vertical post-tensioning,3–8
though they may also include spliced
Fig. 1. Force couple and overturning moment.
reinforcing bars, to develop a strong
self-righting wall in response to a seis-
mic event. These newer systems do not ness to hold spiral confined concrete the connections’ tensile capacities may
emulate normal reinforced concrete with vertical post-tensioning, may not not be sufficient to resist the uplift forc-
shear walls and, as such, have required be possible in the thin, precast concrete es generated from earthquake loads.9
validation, which is typically accom- sections. The solution for thin-walled mem-
plished by use of physical experiments In a tall, narrow shear wall (for ex- bers might be to limit the force that the
and/or analytical models with physi- ample, a 30-ft-tall [9 m] × 8-ft-wide connector could transfer into the wall.
cal testing to prove their resistance [2.4 m] hollow-core panel), the connec- If the tension force is limited below the
equivalency to a cast-in-place system. tion to the foundation has to resist the value that would crack off the panel’s
The use of vertical post-tensioning, overturning moments caused by lateral corner or pull out the anchoring rein-
however, may demand thicker walls loads. The resistance to overturning forcement, the problem of a thin sec-
that have a greater compressive force moment from lateral seismic loading tion failing in a brittle manner could
capacity, special confinement reinforc- appears as a vertical force couple at the be avoided. Limiting the tension force
ing at the edges, or special confinement wall corners as illustrated in Fig. 1. In may limit the lateral-load resistance of a
spirals. Vertically post-tensioned walls such a system, the moment arm of the single panel, but the building’s total ca-
also need a sufficient cross section to lateral force (the height of the wall in pacity for lateral-load resistance equals
allow splicing of the ductile vertical a single-story system) is often greater the sum of the lateral-load resistances
mild-steel reinforcement. than the wall width. Thus, at one base of the numerous wall panels available
Many precast concrete components connection, a large uplift force is creat- around the exterior of the building.
used as exterior walls, such as hollow- ed. At the other base corner, a compres- The force that the ground applies to
core panels, double-tees, and multi- sion force is developed. The capacity the wall system and to the connection
wythe insulated panels, do not have of the corner tension connector is lim- anchorage can be limited by the use
thick concrete cross sections. The join- ited due to the thin-wall section where of special connectors. Investigation of
ing of spliced reinforcing, as needed the connector plate must be anchored. the seismic performance of a variety
for emulative design, or the greater Tests performed on connections with of connection details shows that fric-
compression force capacity and thick- typical anchorage techniques show that tion joints or slotted-bolted (SB) con-

January–February 2007 
nector system for thin-walled precast using such connections.
Load concrete panels that allows the panels While the current focus was on
to resist earthquake lateral load like a specifically defining a connection for
shear wall while also acting as an ex- thin-concrete-sectioned wall elements,
terior curtain wall. This new connec- similar methods could be applicable to
tion system is different from typical any type of precast concrete panel. In
Slip shear-wall connector systems included developing the seismic-resisting sys-
in building-code-proposed design pro- tem described here, only a single type
cedures. Because a goal in the devel- of thin precast concrete element, an 8-
opment of this connection is to obtain ft-wide (2.4 m) hollow-core wall panel,
code approval, extensive experimental was used.
testing combined with analysis and de- When subject to lateral forces, the
Fig. 2. Ideal load-slip plot. sign procedures was required to show bottom connection in a hollow-core
that the walls could respond as well panel might fail as shown in Fig. 3.
as typical reinforced concrete shear In the figure, a steel connection plate
walls subjected to earthquake-induced with reinforcing bars or studs welded
loads.14,15 This paper focuses on de- to its back side is embedded in the top
scribing the system components, key surface of the hollow-core. When lat-
experimental tests, and a suggested de- eral load was applied to the plate, the
sign method. thin-concrete section below the plate,
along with the embedded anchorage
steel, broke free. The concrete suffered
Fig. 3. Failure of base embed.
Objective, Scope, and
a brittle failure in tension and the rein-
Solution Procedure forcing bar suffered a bond failure.
nections may provide an efficient way If SB connectors can maintain an In other research, adjacent hol-
for limiting the shear force applied to elastic-plastic response, as shown in low-core wall panels retrofitted with
the wall system while dissipating sub- Fig. 2, when subjected to a seismic fiber-reinforced polymers (FRPs) ad-
stantial earthquake energy.10–13 After force, the force passing through a con- hesively attached to the concrete faces
slip between the wall panel and the nection can be limited to avoid anchor- have shown similar failures in steel
foundation starts and the connection’s age failure in thin-wall sections while plate edge connections.16 These fail-
stiffness decreases, the devices can providing energy dissipation. Our ures might also be expected in other
also significantly lengthen the building goals were to prove the connector’s thin-sectioned precast concrete mem-
period to a range where seismic effects performance and to create a code-ac- bers. This illustrates that hollow-core
may not be as significant. cepted process for designing and using is emblematic of the general problem
The remainder of this paper will de- thin-sectioned precast concrete wall el- of obtaining satisfactory seismic base
scribe the development of an SB con- ements as seismic-resistant shear walls connections in thin-sectioned precast
concrete wall panels.
Other authors have suggested vari-
ous means of obtaining satisfactory
behavior in precast concrete shear-wall
systems.6 While much attention has
Force Roof been dedicated to achieving wall base
connections that can develop a couple
to resist overturning in thick walls, as
Shear in Fig. 1, consideration must also be
connectors directed to transferring the horizontal
base shear.17,18 Previous studies have
developed excellent methods for trans-
forming thick precast concrete panels
into shear walls but have neglected thin
sections.
One method to reduce the force
couple at the base of thin wall panels
is to connect adjoining panels, form-
ing a wide wall as in Fig. 4. The wider
Base shear moment arm at the base of the panel
reduces the vertical force components.
In many instances, this may be an ac-
Fig. 4. Joining adjacent panels. ceptable solution, and connectors have

 PCI JOURNAL
been developed for these locations.19,20
As the wall becomes wider, however, 8 ft w
the force in the connections between ide
the panels increases. Now the same
anchorage problem may exist, but it
is located in the connections between
adjoining elements. Although success-
ful wall connections have been made Top diaphragm
in this manner using FRPs, the wet connection
field layup required for use of FRPs
is difficult during inclement weather
and may not be practical for typical

Wall height ~ variable


construction.

Roof ~ variable
After considering alternative solu- Wall
tions, the use of a base connection that
could limit the force transferred into
the wall (to avoid wall or anchorage
failure) was chosen for the hollow-core
application. Adjoining panels were not Base tension
connected. connection
To develop a code-accepted process
for designing shear walls composed of
the hollow-core panels with SB base Compression
connectors, the capacity of the entire bearing
proposed wall system needs to be com-
pared with that of code-conforming
shear-wall systems, and it must prove
to behave equivalent to or better than
current systems. The solution method
includes identifying all components of
the wall that will contribute to the lat- Fig. 5. Components of the proposed system. Note: 1 ft = 0.305 m.
eral-load-resisting system, defining the
behavior and design of each component, Top Connection
and defining the design approach for
the entire lateral-load-resisting system. A typical top connection uses two
Each of these steps is discussed in the commercially produced slotted con-
following sections for the hollow-core nectors, such as Corewall or PSA-type
example. Examination of this problem inserts. A Corewall connection to
was pursued by a cooperative venture. a lightweight steel roof structure is
Engineers from Spancrete Machinery shown in Fig. 6, and added anchor-
Corp. and University of Wisconsin re- age reinforcing to affix the insert to the
concrete is shown in Fig. 7. Fig. 6. Corewall attachment to roof.
searchers developed components and
examined component behavior. The
Wall Panel
Nakaki Bashaw Group led the develop-
ment of design procedures and the code The wall is a standard hollow-core
approval process. panel, 8 ft (2.4 m) wide and 8 in. (200
mm) thick, with the cross section shown
The Proposed System: in Fig. 8. In some instances, the panel
may also include an insulation layer
Components or wythe covered by a thin, protective
Figure 5 shows a schematic sketch concrete layer. Because these added
of the proposed wall system. The sys- elements do not contribute to the pan-
tem includes all components required el’s lateral-load resistance, their pres-
to transfer lateral seismic load between ence is irrelevant in shear-wall perfor- Fig. 7. Anchorage of slotted insert.
a roof diaphragm and the foundation: mance and is ignored here. Prestressing
the connection to a roof diaphragm (top strands, not shown in the figure, are were varied in cross section at the loca-
connection), the wall itself, a compres- added inside the panel as needed for tions of the top and bottom connectors
sion/shear base connection, and a ten- out-of-plane strength and handling of to increase the concrete section and im-
sion base connection. the wall panel. Note that the core sizes prove anchorage for the connections.
January–February 2007 
Tension Base Connection
2 3/4 in. 4 in. typ.
A special SB connection is used to re-
17/8 in. sist the tension component of the base
11/4 in.
force couple. In addition to the SB con-
8 in. 51/4 in.
nection mechanism, an anchorage sys-
45/8 in. tem for it is required within the wall.
11/2 in. The SB connection system for re-
sisting tension is shown assembled in
8 ft Fig. 9, and the individual components
are shown in Fig. 10. The SB connec-
tion is intended to slip and dissipate en-
Fig. 8. Wall section. Note: 1 ft = 0.305 m; 1 in. = 25.4 mm. ergy through friction under cyclic load-
ing. Previous experiments conducted
on this kind of connection showed that
Compression/Shear Base of the wall on the foundation through a
the hysteresis loops of connections
Connection packed mortar bedding (which may ex-
with steel-brass friction slip surfaces
tend into the panel voids to form keys,
are similar to those of an ideal rigid–
The bottom connection is com- if needed). Shear forces are resisted
perfectly plastic element.13
posed of bearing to resist compression by shear friction and/or shear key ac-
The SB base slip connection consists
and friction (or grout keys) to resist tion in the compression bearing area
of two main outer steel plates sand-
shear. With lateral loading, a tension- between the bottom of the wall and
wiching a third middle steel plate that
compression couple develops, as illus- mortar bedding. The size of the bearing
has slotted holes to accommodate slid-
trated in Fig. 1. The corner of the wall area is determined by the combination
ing. One of the outer steel plates, at the
must be able to sustain the compres- of vertical gravitational load, the com-
left in Fig. 10, is embedded in the hol-
sion force through bearing. The com- pression component of the overturning
low-core wall panel and has reinforc-
pression and shear resistance of the moment, and the magnitude of rotation
ing bars attached to provide anchorage.
bottom joint comes from the bearing at the base.
The middle slotted plate is welded to a
foundation embed plate. The third outer
steel plate provides a cover and second
friction surface for the connection.
Brass plates are placed within the two
friction interfaces. The brass is used
to provide steadier, more predictable
friction behavior than would be seen
Wall embed plate in steel-to-steel surfaces. The connec-
with tion is joined using two structural bolts.
anchorage bars The bolt tension influences the friction
attached at back force resistance. Special washers are
used to control bolt tension. The bolts
are tightened with a calibrated torque
wrench to a specific torque, giving a
Cover plate desired bolt tension (or associated joint
compression) and friction capacity.
Brass An anchorage system in the wall for
the embedded plate is also an essential
friction part of the SB base connection. The type
plates of anchorage depends on the thickness
available in the wall panel. In the case
of the hollow-core wall, the anchorage
detailing is controlled by the slip-form
extrusion machine used in the wall
Center slotted plate manufacturing process. The machine
places the zero-slump concrete in three
layers and tamps or packs each layer in
mb ed place individually. The anchorage for
tion e
nda the embed plate has to lie within the
Fou thickness acceptable for the first layer
of tamping. In this case, the anchorage
Fig. 9. Diagram of slotted-bolted connector. consists of combinations of reinforc-
 PCI JOURNAL
ing bars and headed studs welded to
the plate along with G-stud clips that Wall embed
gripped the prestressing strand behind plate Brass
plates
the plate and kept the plate positioned
during concrete placement. The accept-
able thickness of the plate is limited to
Spring
2.8 in. (710 mm). The back-side of one washer Bolt
version of an embed plate is shown in
Fig. 11 with the bottom of the wall on
the right side.

Behavior of System
Components
The goal of the proposed system Washer
might be expanded beyond just the
aim of controlling forces applied to
the thin sections of special precast Center plate Cover plate
concrete wall elements. From a design to foundation
embed plate
point of view, it is desirable to iden-
tify system components that have the
ability to yield versus those that need
Fig. 10. Components of the slotted-bolted connector system.
to be protected from large forces or
yielding. As part of this added goal,
all parts of the system, except the SB (17.8 kN) in tension or shear perpendic- Two connectors were attached to a
tension base connection, might be ular to the slot with a 3:1 safety factor. A single loaded beam in measuring their
designed to remain elastic. This ap- tension cone failure calculation would horizontal shear capacities to simulate
proach can make design quite simple. estimate its capacity as approximately the actual loading of a wall panel with
The SB connection may be designated 22 kip (98 kN) in tension. Including the two top inserts. Three identical tests
as the key component to keep the size effect of the hairpin reinforcing bar, its were conducted. The final failure oc-
of loads transferred to the panel below tension cone breakout capacity might be curred with a popout or spall of the
the SB connection’s elastic limit and approximately 31 kip (138 kN). The ac- concrete on the far side of the insert,
may also be designed to dissipate en- tual connection capacities were tested in as shown in Fig. 14, due to twisting of
ergy introduced by seismic movement. tension and shear. the insert in the concrete. The connec-
The behaviors of most of the system The capacity of a single connector
components were measured in the lab- was measured in three separate out-
oratory,21,22 and they will be examined of-plane tension tests. The flat coni-
in this section to identify their behav- cal failure plane from a tension test is
ior, to define elastic force limits and to shown in Fig. 12, and the connection
establish a design approach. behavior is shown in Fig. 13. During
one of the tests shown in the figure, the
Top Connection
displacement measurement became in-
Manufacturers provide strength ca- active partway through the procedure,
pacity information with their respective but a peak load of 10.9 kip (48 kN)
slotted insert connectors. That data may was reached. The initial softening, near Fig. 11. Back of the base embed plate.
be either in the form of safe working 8 kip (36 kN), was coincident with the
loads (with safety factors such as 3:1) observation of a small amount of con-
or minimum ultimate strength capaci- crete spalling around the visible perim-
ties. Complete behavior information in eter of the insert. It is suspected that the
the form of load versus displacement bond between the insert surface and the
relationships is generally not avail- concrete broke at this load. First visible
able. Connector capacities may also be cracking in the panel concrete adjacent
changed by supplementary anchorage, to the insert occurred between a load
such as that provided by the reinforcing of 10 kip and 12 kip (44 kN to 53 kN),
bar shown attached to the back of the which was also the peak load resisted.
anchor in Fig. 7. The manufacturer’s suggested design
The insert shown in Fig. 6, without capacity of 4 kip provided a factor of
the added reinforcing bar, has a manu- safety of 2.4 relative to its lowest mea- Fig. 12. Slotted connection tension test:
facturer’s safe working capacity of 4 kip sured capacity. flat failure surface.

January–February 2007 
Load and
Load and Displacement
displacement
14

12

10
Load (kip)

8
Fig. 14. Slotted connector shear test.
6

4 lations that included the effect of pre-


stress were used to define the elastic
2 wall capacity rather than conducting
shear and flexural testing.
0 For flexural design purposes, the
0 0.05 0.1 0.15 0.2 wall panel is treated as a beam-column,
Pullout displacement (in.) using the actual cross section to deter-
mine its capacity. With no axial load,
Fig. 13. Slotted-insert pullout test results. Note: 1 kip = 4.45 kN; 1 in. = 25.4 mm. the cracking moment for a hollow-core
panel can be directly calculated. If a
lateral load was applied, as in Fig. 1, at
tor performance is shown in Fig. 15. result of the inclusion of the hairpin re- a roof height of 34 ft (10.4 m) and the
Initial softening occurred near a load inforcing bar. wall moment is limited to the cracking
of 10 kip (44 kN) when cracks devel- moment, the lateral force capacity limit
Wall Panel
oped from the strands to the concrete is equal to the cracking moment divid-
surface (see strands in Fig. 7). The Building codes have not encour- ed by the distance to the lateral force.
connector appeared to yield and capac- aged the use of prestressed members A dilemma in defining the shear ca-
ity dropped slightly after the circular for resisting seismic lateral loads due pacity for the wall comes from the two
crack visible in Fig. 14 occurred near to a perceived lack of ductility in pre- separate approaches in considering its
0.8 in. (20 mm) of displacement. Ac- stressed concrete. While the code ob- behavior. As a flexural beam-column,
tual shear capacities of 26 kip to 27 kip jective would be appropriate if the wall the prestressing and axial loads are ac-
(115 kN to 120 kN) were reached by panel was expected to develop inelas- counted for in calculating capacity and
the three sets of connectors. The ratio tic behavior, it does not apply to this the flexural force applied is limited by
of the measured capacity to the manu- system. The prestressed wall panel is the SB connection. In resisting lateral
facturer’s suggested capacity was 6.5, protected by the limited capacity of the seismic forces as a shear wall, the wall
a high factor of safety that may be a SB base connection. Analytical calcu- is considered to be more like structural
plain concrete, but shear force is also
limited by the SB connection. Wall shear
)PSJ[POUBM4IFBS capacity is estimated while ignoring the
effect of prestressing and axial load.

Determining the appropriate strength
reduction factor depends on the type of

behavior assumed for the system.
4IFBSMPBE LJQ

 ACI 31823 allows a shear stress of

 4 / 3 f c' for plain concrete. The two


face wythes of the wall in Fig. 8 could
 withstand 27 kip (122 kN) of shear at
that stress capacity. The webs between
 the face wythes that form the cores in
the hollow-core were ignored in this
 calculation. In design, a strength re-
      duction factor φ must also be selected.
This protected wall is considered to be
4IFBSEJTQMBDFNFOU JO
a special reinforced concrete structural
wall. The strength reduction factor φ
Fig. 15. Slotted-connector performance in shear. Note: 1 kip = 4.45 kN; 1 in. = 25.4 mm.

 PCI JOURNAL
for shear in reinforced structural walls, wall. Additional shear capacity will ac-
where capacity is controlled by flex- tually exist due to shear keys of dry-
ure, may be taken as 0.85. If the shear pack grout that will form in the voids of
strength is less than that corresponding the panel at the wall base. These keys
to the nominal flexural strength (unpro- will also provide resistance in partially
tected), then Section 9.3.4 of ACI 318 uplifted portions of the wall.
requires that φ be taken as 0.60. The compression capacity, which
Thus, ACI 318 allows the φ factor could not be analytically predicted, was
to be increased by 0.85/0.60, or 42%, measured. A series of wall prisms, cut
when it is ensured that the wall will from the bottom corner of a wall such
fail first in flexure. The shear φ factor as in Fig. 1, were loaded to measure
for structural plain concrete is 0.55. the useable compression capacity. The
Because the wall is considered to be prisms were wider than the predicted
plain concrete for shear capacity but is width of the compression region at the
load protected by the SB connectors, wall base due to combined axial load
φ = 0.55, which is an increase of 42%, and overturning. Each of the prisms
as is done for reinforced walls, result- was tested with an eccentric axial load
ing in a new strength reduction factor applied in a 1 million lb (454,000 kg)
of 0.78. The useable capacity may then testing machine. The application point
be considered to be 0.78 ⎛ 4 / 3 f c' ⎞ , or of the resultant compression load,
⎝ ⎠ 2.5 in. (63 mm) from the wall edge, was
1 f c' . For design purposes, the shear selected to mimic the location of the re- Fig. 16. Compression test prism with
stress will be limited to 1 f c' to ensure sultant compression force in a wall that eccentric load.
elastic response. Because a modified φ is experiencing overturning and uplift
factor is already included, it is not nec- at the tension corner. Figure 16 shows
essary to apply an additional capacity the test setup, and Fig. 17 shows a typi-
reduction factor. cal failure.
The prism test results are summa-
Compression/Shear Base rized in Table 1. The compression
Connection strength capacity would be expected
to vary from that predicted by cylin-
The right-side corner of the wall in der tests. Capacity is likely to depend
Fig. 1 develops a resultant compres- on the configuration of the wall sec-
sion reaction. The total compression is tion cores, the development of tension
the sum of applied vertical load from a stress fields perpendicular to primary
roof, the weight of the wall, and an ad- compression, and the lack of transverse
ditional couple component as needed to confining reinforcement. The results
resist the overturning moment caused in Table 1 are appropriate for the wall
by the lateral force. configuration produced. Failure ca-
In this compression region, shear pacities were consistent, and the peak
friction is relied on to transfer the seis- strain at the outside edge of the wall
mic base shear.18 If a roughened surface ranged from 0.0014 to 0.0019, with an
is provided on the foundation, ACI 318 average of 0.00162, which is about half
allows the use of a coefficient of friction the maximum strain used in normal
equal to 1. Thus, the minimum shear strength calculations. Tests with load
capacity of the wall panel would equal applied at other eccentricities produced Fig. 17. Typical failure of compression
test prism.
its weight if it were a non-loadbearing similar results.

Table 1. Prism Compression Test Results


Prism Test Specimen Peak Load, kip Peak Strain Neutral Axis Location from
Edge, in.

Prism 1 220 0.00158 8.7

Prism 2 222 0.00193 8

Prism 3 214 0.00136 7.2

Note: Peak strain is measured at the outside edge of the wall, and the neutral axis is measured from the edge at failure. 1 kip = 4.45 kN; 1 in. = 25 mm.

January–February 2007 
wall panel that is 8 ft (2.4 m) wide and
rocking about a base corner, the uplift
would be nearly 2.6 in. (66 mm).
Because the connection is expected
to experience the effects of a minor
earthquake before a major earthquake
occurs, the cyclic testing started at
low lateral force levels. Three cycles
of tension load were first applied at
a level equal to 25% of the expected
slip force (6.25 kip [27.8 kN]). They
were followed by three more cycles at
an amplitude of 50% of the expected
slip force (12.5 kip [55.6 kN]). Then
the joint was tested at a series of larger
tensile displacement levels of 0.28 in.
[7 mm], 0.4, 0.7, 1.1, 1.6, 1.1, 0.7,
cL Fig. 19. Slotted-bolted connector test and 0.4 in. (10, 18, 28, 41, 28, 18, and
assembly in test machine. 10 mm) that would induce slip yield
displacement. Three cycles were re-
peated at each displacement level.
The cycles were at displacement levels Upon completion of those tests, the
Fig. 18. Schematic of slotted-bolted of 0.4, 0.7, 1.1, 1.6, 1.1, 0.7, and 0.4 in. joint was finally subjected to three cy-
connector joint test setup. (10, 18, 28, 41, 28, 18, and 10 mm). cles at a peak tensile displacement of
The current SB connection assem- 2.5 in. (64 mm), or nearly 3% wall drift
blies were separated from the wall in an 8-ft-wide (2.4 m) panel. The two
Tension Base Connection
panel and tested alone for convenience. cyclic loading programs are shown in
Particular attention was directed at All of the components were noted pre- Fig. 20 and 21.
evaluating the performance of the SB viously in Fig. 10. The test assembly The joint property of interest was
connection because it is relied on to is shown schematically in Fig. 18 and its force-resisting ability; energy dis-
control the peak seismic base force ap- placed in the test machine in Fig. 19. sipation was secondary. Response
plied to the wall. Fifteen tests were run A loading pattern similar to Popov’s measured in the connection, plotted in
with various designs for the connection. was selected. The maximum acceptable Fig. 22, is near the ideal elastic–perfect-
The testing program was patterned sim- drift in a 36-ft-tall (11 m) wall was used ly plastic behavior desired. What looks
ilarly to previous research by Grigorian to pick a peak displacement for the con- like double yield levels are actually
and Popov on connections for diagonal nector tests. An uplift amplitude of 1.6 the results of slip occurring, first be-
bracing.13 Popov used a series of im- in. (41 mm) corresponds to a design top tween the foundation plate and the wall
posed sinusoidal displacement cycles drift of the wall of nearly 2%. There- embed plate, followed by slip between
that were intended to mimic the ex- fore, a peak displacement of 1.6 in. the foundation plate and the cover plate
pected displacements that the connec- was selected for these cyclic tests. At a at a slightly larger displacement.
tor might see during a seismic event. maximum acceptable drift of 3%, for a The load level at full slip is very near
to the target amount of 30 kip (133 kN),
and it remains nearly constant with
repetitions and at different displace-
14,000 ment levels. Force data from four tests
12,000 on the final selected joint are listed in
Table 2.
10,000
Load (lb)

The specific characteristics exhibited


8000 by the connection may be summarized
6000 as follows.
4000 • Elastic capacity: The connec-
2000 tion developed an initial av-
erage tension tie capacity of
0
33.3 kip (148 kN) before slip
0 20 40 60 initiated. Variation measured
from that average was between
Time (sec) +1.5 kip (+6.7 kN) and -2.6 kip
(-11.6 kN). The accompanying
Fig. 20. Initial slotted-bolted connector applied load cycles. Note: 1000 lb = 4.45 kN.
10 PCI JOURNAL
Table 2. Measured Slotted-Bolted Connection Test Results
Peak Measured Slotted-Bolted Connection Values
Initial Maximum and Minimum Tensile Forces, kip
Stiffness,
Test kip/in. First Cycle All Cycles Last Cycle Last/First, %
Max. Min. Max. Min. Max. Min. Max. Min.

disp04asr 903 34.8 -26.0 36.5 -32.4 30.4 -28.8 87 111


disp05asr 938 34.8 -27.3 34.8 -29.4 27.4 -25.8 79 95
disp06asr 988 30.7 -28.5 34.4 -32.3 30.1 -29.0 98 102
disp07asr 990 33.1 -29.3 36.8 -32.7 31.5 -28.9 95 99
Note: “Last cycle” is taken as the last cycle at 0.4 in. peak displacement; + values are tensile; 1 in. = 25.4 mm; 1 kip = 4.45 kN.

average elastic stiffness was


955 kip/in. (16,720 kN/mm).
• Peak capacity: The peak uplift
Applied displacement (in.)

force transferred through the con- 3.0


nection was measured as 36.8 kip
(164 kN). Peak resistance varied 2.5
2.4 kip (10.7 kN) among the four 2.0
cyclic tests. This peak resistance
occurred with 1.1 in. (28 mm) 1.5
of connection displacement. 1.0
• Capacity deterioration: Cyclic
testing proved that the elastic 3.0
resistance capacity, before joint 0
slip occurred, decreased slightly 0 50 100 150 200 250 300
under repeated cycling at large
displacements (1.1 in. [28 mm] Time (sec)
or greater). With 21 cycles of
displacement of 0.4 in. (10 mm)
and greater, all of the connec- Fig. 21. Applied displacement cycles. Note: 1 in. = 25.4 mm.
tors were able to maintain a
resistance capacity at slip of
25 kip (111 kN). The actual loss
in resistance capacity at slip
varied from 2% to 21% after 21 40
cycles of large displacement.
30
• Friction damping/energy dissi-
pation: The connector performs 20
as an excellent friction damping
10
Force (kip)

system. The energy dissipation


remains high through multiple 0
cycles of displacement at a vari- -10
ety of levels from 0.4 in. (10 mm)
to 1.6 in. (41 mm) and back to -20
0.4 in. (10 mm). The connection
-30
might be described as a stable
elastic–perfectly plastic system. -40
Base Embed Plate 0.0 0.5 1.0 1.5 2.0 2.5

The second key portion of the tension Displacement (in.)


base connection is the wall embed plate.
As noted previously, anchorage for a
large load capacity is difficult to obtain Fig. 22. Load and displacement record from slotted-bolted connector test. Note:
in a thin-walled section. The amount 1 kip = 4.45 kN; 1 in. = 25.4 mm.
January–February 2007 11
Table 3: Summary of Component Capacities and Behavior
Component Tension Pullout Test Horizontal Shear Test Vertical Force Test
Top insert Component yield at 8.3 kip, First crack at 8.8 kip, 27.1 kip
first crack at failure, 10.8 kip peak, ductile (for two inserts) —
peak, ductile failure failure

Wall panel 12.7 kip at 34 ft causes flexural


crack, 27 kip shear capacity,
— —
brittle (analytical prediction)
failure
Compression base connection 219 kip capacity with neutral
axis at 8 in. from edge,
— —
ε maximum = 0.00162 brittle
failure
Slotted-bolted connector Initial slip at 33.3 kip of ten-
— — sion, 35.6 kip capacity, elasto-
plastic

Base embed First crack at peak capacity of Initial crack at 14 kip 14.9 kip First crack at 27 kip of tension
11.4 kip, brittle failure peak, brittle failure force, 57 kip capacity, limited
ductility

Note: 1 kip = 4.45 kN; 1 ft = 0.305 m; 1 in. = 25.4 mm.

of force transferred can be controlled An initial series of three tests were The base embed plate was also tested
by changing the torque applied to the conducted to determine the uplift resis- with load applied perpendicular to the
SB connection. Because this SB con- tance capacity of the embed, without wall surface (out of plane) and with
nection is designed to develop a peak anchor studs, at two limit states: crack- shear load applied parallel to the bot-
force capacity of 36.8 kip (164 kN), the ing and ultimate. A slowly increasing tom edge of the wall. Three tests were
embed plate needs to develop a higher load was applied to the plate through a conducted in each configuration. With
anchorage capacity when resisting the hydraulic jack system, and the behavior out-of-plane loading, the first crack and
tension uplift force of the wall. The an- was observed and measured. Figure 23 peak load occur simultaneously with an
chorage provided from a combination shows the resulting failure surface. average of 11.4 kip (51 kN). Shear load
of reinforcing bars, headed studs, and The first crack, marked “1” in the applied parallel to the wall base and to-
G-studs clipped to prestress strand can- figure, occurred at an average load of ward the close edge created an initial
not be exactly calculated. A rough ap- 21 kip (93 kN). The extension of this crack at an average of 14 kip (63 kN).
proximation might be attempted using crack, marked “2,” developed at an Peak load and failure followed at an
an assumed fracture surface. average of 28 kip (124 kN) and repre- average of 14.9 kip (66 kN). For both
sented the tension capacity of the con- types of loading, the failure occurred
crete section below the embed plate. abruptly at peak load with virtually no
Subsequently, the steel anchor bars and ductility. Because friction of the mortar
strand became more active and con- joint in the compression bearing region
tinued to increase the embed capacity is relied on to resist these loads in the
until it either pulled out with anchor- wall system, the embed behavior is not
age failure (at 47.5 kip [211 kN]) or critical as long as the joint static fric-
the actuator capacity was reached (at tion capacity is not exceeded.
50 kip [222 kN]). The measured behav-
Summary of Component Capacities
ior of a typical base embed is plotted
and Behavior
in Fig. 24.
Studs were subsequently added to The aim of the connection system
the back of the embed plate, as shown design is to protect the thin walls of
in Fig. 11, and the anchor reinforc- precast concrete panels from develop-
ing bars were lengthened to develop a ing unpredictable or brittle failures,
greater ultimate capacity. With these such as pullout. Each of the compo-
changes, retesting showed that the nent capacities is reviewed in Table 3.
average cracking load remained near Mechanisms listed as brittle, or fail-
27 kip (120 kN) and the ultimate ca- ures that are difficult to predict, should
Fig. 23. Failure surface from base
pacity could reach 57 kip (254 kN). be prevented from occurring. As an
embed test.

12 PCI JOURNAL
example, the vertical compression at
the base corner of the wall should be 60.0
controlled so that the strain remains 50.0
less than 0.0016, the average of limit
values listed in Table 1. The compo- 40.0

Tension load (kip)


nent capacity test results came from 30.0
hollow-core panels with an average
28-day compressive cylinder strength 20.0
of 7340 psi (50.6 MPa) with a standard 10.0
deviation of 410 psi (2.8 MPa) in 40
0.0
cylinders.
Considering the equilibrium of forces -10.0
in Fig. 1, there is a direct link between
-20.0
the bottom compression reaction, ap-
plied vertical load, SB connector ten- 0.00 0.10 0.20 0.30 0.40 0.50
sion force, and the lateral (seismic) Pullout displacement (in.)
load. Thus, controlling the SB connec-
tor force can control the base compres- Fig. 24. Embed pullout test with cycling at peak load. Note: 1 kip = 4.45 kN;
sion reaction component and compres- 1 in. = 25.4 mm.
sion strain. A design philosophy for the
wall must be based on these relations. connectors behaved as expected, and axial load. The analyses showed that
System Behavior there was virtually no residual uplift at the wall system behaved like a ductile
the wall base after the test. reinforced concrete wall. No significant
After completion of the compo- Subsequent tests involved three permanent uplift of the wall developed
nent tests, a full-height, complete cycles of reversed cyclic displace- at the base joint except in some cases
wall system was tested and extensive ment applied to the top of the wall at with very short walls, strong seismic
non-linear analyses were conducted increasing displacement amplitudes. motion, and no added roof dead load.
to predict building behavior with the Finally, the wall was pulled laterally
wall system under various earthquake at the top until the base SB connec-
motions. These tests and analyses Design Approach
tor reached the limit of the slot and
were not required as part of the code force in the connector reached the Because the SB connector has been
approval process and are only briefly level needed to cause anchorage fail- selected as the preferred location for
described here. ure between the embed plate and the possible inelastic response and energy
The wall system test was conducted concrete wall panel. dissipation, the overall design approach
on a full-size, 38-ft-tall (11.6 m) hol- An extensive series of non-linear is to keep all of the other components of
low-core wall, but in a horizontal posi- seismic response analyses were also the system elastic. Referring to Fig. 26
tion (Fig. 25). The wall base was con- conducted at various earthquake am- and the values in Table 3, the following
nected to a fixed abutment using two plitudes and differing amounts of wall requirements might be applied.
SB connectors with dry-pack grout
under the concrete panel. Lateral dis-
placements were applied to the wall at
36 ft (11 m) from the base, the assumed
roof level for a building, by hydraulic
jacks attached to the wall with slotted
insert connectors. A constant axial load
of 20.9 kip (93 kN) was applied at the
top of the wall to simulate wall weight
(19 kip [84.5 kN]) plus some added
dead load.
The first test simulated possible ser-
vice-level earthquake motion. Before
testing, a non-linear analysis of build-
ing motion was conducted using the
1940 El Centro ground motion record
with peak acceleration of 0.33g, where
g is the acceleration of gravity. The pre-
dicted top-level displacements created
by the earthquake were then applied
statically to the top of the wall. The SB Fig. 25. Testing a full-sized wall system in a horizontal position.

January–February 2007 13
Top Insert Connector (Shear) Applied applied in either case. Because out-of-
A roof loads
plane loading on the grout bed was not
With reinforcing bars attached to the tested in this program, a brittle failure
V
back of the anchor (as shown in Fig. mode should be assumed. The out-of-
7), the failure mode of the top shear plane strength of the base connector
connector is ductile. Therefore, code- can be calculated using appropriate
Wall
proposed safety factors that acknowl- weight safety factors depending on the failure
edge ductile behavior can be used to h mechanism of the component under
reduce the allowable load-carrying
Height W consideration.
capacity of the insert, rather than the Taking this general approach, a sub-
Width mittal was proposed and subsequently
safety factors that are associated with
brittle behavior. However, even though approved by the International Code
this element is ductile, it should not be Council (ICC) Evaluation Services for
relied on to dissipate energy. Capacity V seismic design of Spancrete hollow-
design should be used to ensure that the T core shear-wall systems.24 The walls
C are accepted as precast concrete shear-
connector behavior is kept elastic.
Arm wall systems that comply with the per-
Top Insert Connector (Tension) formance requirements of International
Fig. 26. Design requirements. Building Code 2003 (IBC 2003) Chap-
With reinforcing bars attached to the ter 19 for Special Reinforced Concrete
back of the anchor, the failure mode Shear Walls.25 With that designation, in
Wall Shear Strength
of the top connection in tension is also combination with the variations in de-
ductile. The same approach for the de- The wall shear force should be lim- sign described previously, seismic re-
sign of this connector can be used for ited by capacity design to the wall shear quirements may be obtained using the
tension and shear. strength, modified by an appropriate following IBC 2003 criteria:
safety factor. Although it was not tested R = 5.5 (bearing walls)
Overturning Strength of the Base in this program, the shear failure of a = 6.0 (nonbearing walls)
Connector wall panel is likely to be brittle. A de- Cd = 5
sign shear stress in the surface wythes of Ω0 = 2.5
The base connector not only pro-
vides ductile behavior but dissipates 1 f c' may be used in limiting the wall Details of the design procedure for
energy as it cycles through repeated capacity without applying an added φ the tested system can be found in Ref-
earthquake motions. This connector factor (with f c' in units of psi). erence 26.
should be used to limit loads to the Wall Base Shear Strength
other, less ductile parts of the wall sys- Summary and
tem. The overturning moment (V × h) The shear friction capacity of the
Conclusions
must be less than the resisting moment grout bed at the base of the wall panel
(T × arm + [(A + W) × width/2]). Thus, must be greater than the applied shear Precast, prestressed concrete mem-
the base shear must be limited to: force. Appropriate safety factors should bers with thin-concrete sections, often
be applied. used as exterior curtain walls in com-
1⎡ ⎛ width ⎞ ⎤ mercial and industrial buildings, can
V≤ ( ) (
⎢T arm + A +W ⎜ ) ⎥
Compression Strain at Wall Base
act as seismic-resisting shear walls.
h ⎢⎣ ⎝ 2 ⎟⎠ ⎥⎦
The base compression force, a com- The primary problem in using these
bination of vertical load (A + W) and walls for seismic resistance is in devel-
where the moment resisting couple term T, oping a satisfactory ductile base con-
h = height of roof must be limited in amplitude and ap- nection that can transfer forces from
T = s lip force capacity of the plied at a location that will keep con- the foundation to the thin-wall panel.
SB connector crete strains less than the average com- A secondary problem is in meeting ex-
arm = distance between compres- pression strain capacity of the panel, isting code criteria for emulation, or in
sion and tension couple or 0.00162. Appropriate safety factors proving the capacity of the system.
A = applied vertical dead load should be applied because this is a brit- Prestressed concrete wall panels can
from roof tle failure mode. easily be used to resist seismic loads if
W = weight of the wall panel, as an alternate ductile mechanism is pro-
Out-of-Plane Base Connector
shown in Fig. 26 vided and the prestressing materials are
Strength
width = width of the wall panel not relied on for ductility. Walls with
The out-of-plane loading can be thin sections can form shear walls if the
Appropriate safety factors that rec- resisted either by the out-of-plane force transferred into the thin concrete
ognize that this is the ductile element strength of the base connector or by the section at the base is limited and brittle
that limits the overall earthquake load shear friction capacity of the grout bed. anchorage failure is avoided. A duc-
to the building should be used. Appropriate safety factors should be tile SB connection at the wall base is
14 PCI JOURNAL
an ideal device to provide ductility and Resistance with Precast Concrete Shear for Special Structural Walls Based on
load-limiting control. It has the added Walls. PCI Journal, V. 42, No. 5 (Sep- Validation Testing. Report draft, S. K.
advantage of high energy dissipation. tember–October): pp. 44–65. Ghosh Associates Inc., Northbrook, IL.
Through a series of experimental 3. Kurama, Y., R. Sause, S. Pessiki, L. 15. Hawkins, N., and S. K. Ghosh. 2004.
W. Lu, and M. El-Sheikh. 1997. Seis- Acceptance Criteria for Special Pre-
tests, the capacities and behavior of a
mic Design and Response Evaluation cast Concrete Structural Walls Based
complete precast concrete hollow-core of Unbonded Post-Tensioned Precast on Validation Testing. PCI Journal,
shear-wall system were defined. Those Concrete Walls. PRESSS Report No. V. 49, No. 5 (September–October): pp.
quantities were coupled with a design 98/03, Lehigh University. 78–93.
procedure developed to ensure that the 4. Kurama, Y., R. Sause, S. Pessiki, L. W. 16. Pantelides, C. P., V. A. Volnyy, J.
seismic forces introduced into the wall Lu, and M. El-Sheikh. 1996. Analytical Gergely, and L. D. Reaveley. 2003.
remained lower than the elastic capaci- Modeling and Lateral Load Behavior Seismic Retrofit of Precast Panel Con-
ties of the wall elements. With the SB of Unbonded Post-Tensioned Precast nections with Carbon Fiber Reinforced
base connection as the only yielding Concrete Walls. PRESSS Report No. Polymers. PCI Journal, V. 48, No. 1
98/02, Lehigh University. (January–February): pp. 92–104.
element, it was demonstrated that an
5. Kurama, Y., S. Pessiki, R. Sause, and 17. Llorente, C. A., J. M. Becker, and E.
overall wall response similar to or bet- L. W. Lu. 1999. Seismic Behavior and Kausel. 1981. Inelastic Behavior of
ter than that expected by the IBC 2003 Design of Unbonded Post-Tensioned Precast Concrete Shear Walls. Pub.
for special reinforced concrete shear Precast Concrete Walls. PCI Journal, No. R81-25, Massachusetts Institute of
walls could be achieved. ICC Evalua- V. 44, No. 3 (May–June): pp. 54–71. Technology, Cambridge, MA.
tion Services has accepted this perfor- 6. Kurama, Y. 2002. Hybrid Post- 18. Soudki, K., J. West, S. Rizkalla, and
mance evidence and the special design Tensioned Precast Concrete Walls for B. Blackett. 1996. Horizontal Connec-
procedure as a basis for an accepted Use in Seismic Regions. PCI Journal, tions for Precast Concrete Shear Wall
method of seismic design. V. 47, No. 5 (September–October): Panels under Cyclic Shear Loading.
pp. 36–59. PCI Journal, V. 41, No. 3 (May–June):
The principle of using special base
7. Perez, F., S. Pessiki, and R. Sause. pp. 64–81.
connections results in a unique design 2004. Seismic Design of Unbonded 19. Hofheins, C., L. Reaveley, and C.
process. A design base shear could be Post-Tensioned Precast Concrete Pantelides. 2002. Behavior of Welded
calculated using typical code methods. Walls with Vertical Joint Connectors. Plate Connections in Precast Concrete
The overall base shear capacity of an PCI Journal, V. 49, No. 1 (January– Panels under Simulated Seismic Loads.
individual wall panel is then calculat- February): pp. 58–79. PCI Journal, V. 47, No. 4 (July–
ed based on a set of rules designed to 8. Perez, F., S. Pessiki, and R. Sause. August): pp. 122–133.
keep the wall system elastic, except for 2004. Lateral Load Behavior of Un- 20. Schultz, A. E., M. K. Tadros, X. Huo,
the yielding base. Then the number of bonded Post-Tensioned Precast Con- and R. Magaña. 1994. Seismic Re-
crete Walls with Vertical Joints. PCI sistance of Vertical Joints in Precast
these specially connected seismic walls
Journal, V. 49, No. 2 (March–April): Shear Walls. In FIP ’94 XII Congress
required may be directly determined pp. 48–­65. May 29–June 2, Washington, D.C.,
from the code-required design-base 9. Private communication. 2003. Span- V. 1, pp. E23–E27. London, England:
shear force using an equivalent static crete Machinery Corp. Structural Engineers Trading Organisa-
load approach. 10. Soudki, K., S. Rizkalla, and B. LeB- tion Ltd.
Alhough this development of a de- lanc. 1995. Horizontal Connections for 21. Oliva, M. G., and C. K. Bora. 2003.
sign approach focused on hollow-core Precast Concrete Shear Walls Subject- Testing of Spancrete Wall Friction
shear walls, a similar approach could ed to Cyclic Deformations Part 1: Mild Base Connection. Report 1-03, Struc-
be used for other precast concrete Steel Connections. PCI Journal, V. 40, tures and Materials Testing Laboratory,
No. 4 (July–August): pp. 78–96. University of Wisconsin–Madison.
wall systems. The test results and de-
11. Schultz, A. E., and R. A. Magana. 22. Oliva, M. G., and C. K. Bora. 2003.
sign values presented here are based 1996. Seismic Behavior of Connections Full-Scale Test of Spancrete Wall with
on the unique characteristics of the in Precast Concrete Walls. Mete A. Friction Base Connections-Valders
Spancrete hollow-core panel. This par- Sozen Symposium, Paper SP 162-12, Tests. Research report, University of
ticular Spancrete system is currently in American Concrete Institute (ACI), pp. Wisconsin–Madison.
the process of being patented. Results 273–311. 23. ACI Committee 318. 2002. Build-
would be different for other hollow- 12. Oliva, M. G., and R. W. Clough. 1985. ing Code Requirements for Structural
core or thin-walled panels. A similar Shaking Table Tests of Large-Panel Concrete (ACI 318-02) and Commen-
test regimen would be required for dif- Precast Concrete Building System As- tary (ACI 318R-02). ACI: Farmington
semblages. EERC Report EERC-83/14, Hills, MI.
fering panels, but the same principle of
Earthquake Engineering Research Cen- 24. Nakaki Bashaw Group. 2003. Span-
controlling forces could be used. ter, University of California–Berkeley. crete Prestressed Hollow Core Wall
13. Grigorian, C. E., and E. P. Popov. Panel, ICC-ES Final Submittal. NBG
1994. Energy Dissipation with Slot- Project No 00-11.001.
References
ted Bolted Connections. EERC Report 25. International Code Council (ICC).
1. Freedman, S. 1999. Loadbearing Ar- UCB/EERC-94/02, Earthquake Engi- 2002. International Building Code
chitectural Precast Concrete Wall Pan- neering Research Center, University of 2003. Country Club Hills, IL: ICC.
els. PCI Journal, V. 44, No. 5 (Septem- California–Berkeley. 26. Spancrete Machinery Corp. 2004.
ber–October): pp. 92–115. 14. Hawkins, N. M., and S. K. Ghosh. Design Procedure for the Spancrete
2. PCI Ad Hoc Committee on Precast 2003. Proposed Provisional Standard Prestressed Hollow Core Wall Panel.
Walls. 1997. Design for Lateral Force and Commentary: Acceptance Criteria Waukesha, WI: Spancrete.
January–February 2007 15

You might also like