The GMP proposal should be bound in a three ring binder with cover, dividers, and
documentation, in the following tabulated order:
Proposal Booklet Cover - Cover must contain, at a minimum, the
title "Guaranteed Maximum Price Proposal", the project name,
project number, date of submission, and construction managers'/
design-builder's name.
TAB - A: Transmittal letter (including confirmation of project team (see
attached letter format)
TAB - B: Table of Contents
TAB - C: Project Description and Additional Documents (Exhibit A of the
Agreement): Provide required information found on the attached Tab
C.
TAB - D: GMP Summary (Exhibit __ of the Agreement): Provide a summary
of the total GMP cost using the Tab D format attached.
TAB - E: List of Documents and Specifications: Provide a recital of the
specific Construction Documents, including drawings, specifications,
and all addenda thereto, used in preparation of the GMP proposal,
(project manual(s), drawings by sheet number & date (revised
dates), etc.)
TAB - E1: Qualifications, Clarifications, and Assumptions: Provide a
summary of all qualifications and assumptions included in the
specification listing. At the minimum, the information shall be
grouped by CSI category. If possible identify specific CSI
specification number.
No qualifications or exceptions may be introduced that conflicts with
the requirements of the General Terms & Conditions, Construction
Contingency use, or Staffing/General Conditions Costs as described
in the Agreement.
TAB - E2: Exclusions: Provide a summary of all exclusions included in the
specification listing, plus any exclusions not related to the
specifications, by CSI category. No qualifications or exclusions may
be introduced that conflict with the requirements of the General
Terms & Conditions, Construction Contingency use , or
Staffing/General Conditions Costs as described in the Agreement.
TAB - E3: Proposed Substitutions, Modifications, or Variances: Provide
this information if applicable.
TAB - E4: Record of Value Engineering Items: If applicable, provide a
Revision Date:
Professional Service Guide
1 of 14
PSG EXHIBIT 6.4
Revision Date:
Professional Service Guide
2 of 14
PSG EXHIBIT 6.4
its own force and the Work the CM/D-B proposes to perform with
Subcontractors hired by the CM/D-B.
Tab - M: Project Directory
A directory including all proposed contractors, subcontractors, and
suppliers of major equipment and materials.
Tab - N: Other information as needed
Revision Date:
Professional Service Guide
3 of 14
PSG EXHIBIT 6.4
The undersigned, (Name), proposes and agrees, if this GMP Proposal is accepted, to
enter into an agreement with the University and to perform and furnish all Work as
specified or indicated in the Contract Documents for the construction phase for
Contract Price for the construction phase and within the Contract Times indicated in
this GMP Proposal and in accordance with the other terms and conditions of those
Contract Documents.
(CM's Name) accepts all of the terms and conditions of the Agreement Between the
University and Construction Manager, CM’s response to the "Notice for Professional
Consultants", and the Contract/Scope of Services for Pre-Construction Services. The
GMP Proposal will remain subject to acceptance for ______ calendar days after
received by the University. CM will sign and deliver the required number of
counterparts of the Contract with the bonds and other documents required by the
Contract Requirements for the construction phase within fifteen (15) days after the
date of University’s acceptance of the final GMP Proposal.
In submitting this proposal, CM represents, as more fully set forth in the Contract
for the construction phase, that:
CM has examined and carefully studied the Contract Documents for the
construction phase and the following Addenda receipt of all, which hereby
acknowledged: (List Addenda by Addenda Number)
CM has visited the site and become familiar with and is satisfied as to the
general, local and site conditions that may affect cost, progress, performance
and furnishing of the Work.
CM is familiar with and is satisfied as to all federal, state and local Laws and
Regulations that may affect cost, progress, performance and furnishing of the
Work.
CM has carefully studied all reports of explorations and tests of subsurface
conditions at or contiguous to the site and all drawings of physical conditions
in or relating to existing surface or subsurface structures at or contiguous to
the site which have been identified in the Contract Discounts for the
construction phase. CM acknowledges that such new reports may not be
complete for CM’s purposes. CM acknowledges that University and design
professional do not assume responsibility for the accuracy or completeness of
information and data shown or indicated in the Contract Documents for the
construction phase with respect to underground facilities at or contiguous to
the site. CM has obtained and carefully studied (or assumes responsibility for
having done so) all such additional or supplementary examinations,
investigations, explorations, tests, studies and data concerning conditions
(surface, subsurface and underground facilities) at or contiguous to the site
or otherwise which may affect cost, progress, performance or furnishing of
the Work or which relate to any aspect of the means, methods, techniques,
Revision Date:
Professional Service Guide
4 of 14
PSG EXHIBIT 6.4
2. Time of Completion.
2.1. CM agrees that the Work will be complete within ___ (___) calendar days
after the date when the Contract Time for the construction phase commences to
run as provided in The Contract Documents for the construction phase, and
Revision Date:
Professional Service Guide
5 of 14
PSG EXHIBIT 6.4
completed and ready for final acceptance in accordance with The Contract
Documents for the construction phase of within ___ (___) calendar days after the
date of the Notice to Proceed.
2.2. CM accepts the provisions of the Contract for the construction phase as to
liquidated damages in the event of failure to complete the Work within the times
specified in the Contract.
4. GMP Proposal Terms and Signatures. Terms used in this GMP Proposal, which
are defined in the General Conditions of the construction phase contract or the pre-
construction phase contract will have the meanings indicated in those documents.
Address:________________________ Phone:_________________________
_______________________________ Fax::__________________________
_______________________________
Revision Date:
Professional Service Guide
6 of 14
PSG EXHIBIT 6.4
TAB D: GUARANTEED MAXIMUM PRICE SUMMARY
Revision Date:
Professional Service Guide
7 of 14
PSG EXHIBIT 6.4
EXHIBIT F - Attachment 1
GMP SUMMARY
(Project Name and Number)
Florida A&M University
(Proposal Date)
Sq. Ft. =
Percent
Cost/ of Cost
Scope of Work GMP Total
Sq. Ft. to Total
GMP
Division 2 Subtotal
Division 3 Subtotal
Division 4 Subtotal
Division 5 Subtotal
Division 6 Subtotal
Division 7 Subtotal
Division 8 Subtotal
Division 9 Subtotal
Division 10 Subtotal
Division 11 Subtotal
Division 12 Subtotal
Division 13 Subtotal
Division 14 Subtotal
Division 15 Subtotal
Division 16 Subtotal
Division 17 Subtotal
Sub-Total Guranteed Maximum "Cost of
the Work" (4.2.1(i)) $ 10,000,000 10.10%
Construction Manager's Contingency,
(4.2.5)
Guaranteed Maximum Construction
Manager's Staffing Costs, (4.2.2)
Guaranteed Maximum General Conditions
Costs, (4.2.3)
Sub-Total
Construction Manager's Overhead
Construction Manager's Profit
Revision Date:
Professional Service Guide
8 of 14
PSG EXHIBIT 6.4
EXHBIT F - Attachment 2
GMP SUMMARY BREAKDOWN
(Project Name and Number)
Florida A&M University
(Proposal Date)
Additional Personnel
Positions Monthly
Percentage
List name and title, list Duration in Monthly Rate Cost/ Sq.
of Time Total Cost
company name if a Months Base Rate w/Labor Ft.
Alloc ated
subcontractor or Joint Venture Burden
with the CM
Revision Date:
Professional Service Guide
9 of 14
PSG EXHIBIT 6.4
Profit
List the profit assigned to this project
This list shall equal Exhibit D, Overhead and Profit Total =
Revision Date:
Professional Service Guide
10 of 14
PSG EXHIBIT 6.4
Total =
Revision Date:
Professional Service Guide
11 of 14
PSG EXHIBIT 6.4
ALLOWANCES SUMMARY
PROJECT NAME:
PROJECT NO.:
Revision Date:
Professional Service Guide
12 of 14
PSG EXHIBIT 6.4
Project Name:
Project No.:
Total =
Revision Date:
Professional Service Guide
13 of 14
PSG EXHIBIT 6.4
Revision Date:
Professional Service Guide 14 of 14