You are on page 1of 8

Gas Flow in Cements

P.R. Cheung, SPE, The Western Co. of North America


Robert M. Beirute, * SPE, The Western Co. of North America

Summary
During the last few decades, several laboratory investiga- would continue to migrate even after decreasing the for-
tions and field studies have been conducted in an attempt mation gas pressure. In their recommendations, the
to find solutions to the problem of gas migration after authors brought up the need for good mud and cement
primary or remedial cement jobs. This article reviews the placement practices as well as for the usage of cement
general findings of previous investigators and offers an slurries with good fluid-loss control and short setting
updated explanation of the mechanism of gas migration. times.
Results of our laboratory studies show that "mobili- The industry as a whole had been very aware of the
ty" of the fluids in the pore spaces during the early life need for proper displacement of the cement slurry to
of the cement, particularly after the cement structure achieve.good primary cement jobs. Even as early as 1948,
becomes load-bearing at a given hydrostatic pressure, is Howard and Clark 7 dealt extensively with the factors to
the main factor that must be controlled to minimize gas be considered for proper casing cementing.
migration within the cement lattice. We also show that Following the steps of previous investigators, Chris-
fluid-loss control alone, though helpful; is not sufficient tian et at. 8 in 1975 wrote a paper emphasizing the need
to stop gas migration. to use cement slurries with good fluid-loss control to pre-
This paper also describes an "impermeable" cement vent gas migration. Their research indicated that
system developed by applying the principles outlined in premature dehydration of cement slurries, resulting from
the laboratory investigation. This impermeable cement has lack of fluid-loss control, may be the primary cause of
been used in field applications in areas where severe gas gas communication. They proposed that fluid-loss ad-
migration problems have been experienced after cement- ditives effectively tie up the water required for hydration
ing. Thus, gas migration through the cement has been of cement and slowly release the water during the entire
prevented when this new approach is used. Several of hydration process, as well as minimize the ability of fluids
these case histories are presented and discussed. to flow through the cement porosity. In 1976, Garcia and
Clark 9 ran a series of experiments and reported that an-
Introduction nular gas influx was seen to occur if cement fluid-loss
or uneven slurry setting occurred high in the hole such
Literature Review" For many years the petroleum in-
that hydrostatic head communication no longer existed be-
dustry has recognized the problem of gas invasion of
tween the bottom of the hole and the mud column above
wellbores after cementing. In the early 1960's, Evans and
the set cement point. They indicated that while the ce-
Carter 1,2 showed the importance of the condition of the
ment slurry remained fluid, gas flow between zones was
pipe surface (roughness and wettability) in obtaining an
controlled. However, sometime after the cement set, gas
effective bond at the casing/cement and cement/forma-
flow began. Cook and Cunningham 10 in 1977 presented
tion interfaces. In 1964, Bearden et at. 3 introduced a
an improved method for evaluating the fluid-loss re-
special mechanical device that could be attached to the
quirements necessary to obtain successful liner or casing
casing to control interzonal communication. The device
cementing jobs. They recommended the use of maximum
consisted of a sealed ring of deformable rubber molded
fluid-loss control in cement slurries when cementing
between two steel flanges, one of them movable. In 1966,
across zones of varying pressure to minimize gas leakage,
Scott and Brace 4 reported that primary cementing was
since increased fluid-loss control resulted in less gas in-
improved by running resin-coated casing through com-
vasion and lower cement permeability.
pletion intervals.
Another way to improve gas migration control, as
The first published attempt to explain the problem of
reported in the literature, is to use expanding cements to
gas communication by means other than leakage at the
promote better bonding at the casing/cement and ce-
casing/cement and cement/formation interfaces was
ment/formation interfaces. One of the most recent papers
presented by Carter and Slagle 5 in 1970. The concept of
dealing with this subject was presented by Griffin et al. II
the "inability of the cement column to effectively transmit
full hydrostatic pressure" was formally introduced to the
in 1979; they discuss an expanding cement system that
industry in that paper. In 1974, Stone and Christian 6 used can provide superior bonding and zone isolation.
laboratory scale models to show that when the gas pressure A paper containing a series of practical techniques to
was higher than the hydrostatic pressure after the cement control gas migration was written by Levine et at. 12 in
had taken an initial set, a channel would form and gas 1979. A graphical technique was introduced that predicts
the potential of annular gas flow after cementing. Also
in 1979, Tinsley et al. 13 introduced, for the first time,
"Now with Amoco Production Co. a new cement system intended primarily to control gas
Copyright 1985 Society of Petroleum Engineers migration at the cement/formation interface. Their work
JUNE 1985 1041
eACK ""EI.URE RfCEIVER

NlTftOGEN-
GAS
"REaSURE TO TEMPERA TUftE CONTROLLER
REGULATOR MINERAL
OIL TANK
""~r»-- I"S TON

- - THERMOCOUPl[

325 MESH SCREEN

PRESSURE TRANSDUCER

/
TO RECORDER

SLURRY

325 MESH SCREEN


"

-NITROGEN
GAS

Fig. 1-Gas flow simulator.

also revealed that decreases in volume within the cement after cementing are reduced greatly, since gas could
matrix, whether a result of ftltrate loss or chemical hydra- migrate through the mud-contaminated cement channels.
tion, cause a rapid decrease in pore pressure within the Also, efforts should be made to achieve a good seal at
cement matrix. They reported that this rapid reduction the casing/cement and cement/formation interfaces. If a
in pressure is caused by the low compressibility of the good bonding or seal is not achieved during the primary
fluid phase (water) within the cement matrix. They sug- cementing operation, gas potentially can migrate along
gested that the pressure can be maintained by the introduc- these low-resistance paths into upper or lower zones of
tion of a highly compressible phase such as by the lesser pressure.
entrainment, addition, or in-situ generation of a highly If good mud displacement and good seals at the inter-
dispersed gas phase. Also at that time, Webster and faces are achieved, the only other way that gas can in-
Eikerts 14 presented a paper that attempted to identify the vade the wellbore is through the cement matrix itself.
relationship between water separation in a cement slurry The object of our research was to study the gas inva-
and the loss of hydrostatic head of a cement column. By sion of the cement lattice as it may occur at or near the
using a laboratory model, they observed a water channel cement/formation interface, to find ways to stop gas in-
in simulated deviated holes when slurries with excessive vasion, if possible, across the face of the gas pressure
free water were used. They stated that their studies showed zone. To do this a device was constructed that could be
that the reduction of effective density of a cement column used to study how the gas invades a small sample of ce-
depended on at least two factors: free water content and ment at the point of contact between the cement and the
the angle of deviation of the hole. formation.
In a more recent paper, Sabins et al. 15 expanded on
the concept of cement transition time. They defined tran- Description of the Apparatus
sition time as the period during which the slurry changes
from a true hydraulic fluid to a highly viscous mass show- Fig. 1 shows a diagram of the apparatus used to study
ing some solid characteristics. gas flow across a relatively small sample of cement slurry .
Early in 1982, Sabins et al. 16,17 published two other The apparatus consisted of a IO-in.- [25.4-cm]-long, 3-in.-
papers that outlined in detail a state-of-the-art theory [7.62-cm]-ID, high-pressure test cell. A hydraulic piston
describing the causes of gas flow following cementing. with a 325-mesh screen is inserted into the cell through
Once again, they indicated that the main cause of gas flow the top, simulating a very permeable formation at the top
following cementing is the incompressibility of the cement of the cell. A simulated hydrostatic head is applied by
slurry during the setting process. pressurizing the piston with mineral oil, which in turn is
pressurized with nitrogen gas. The hollow piston shaft is
Gas Movement in a Wellbore. There is no doubt that connected to a backpressure receiver where ftltrate from
the first step toward gas migration control is the proper the top of the cell can be collected. Another 325-mesh
removal of the drilling mud from the well bore during the screen is placed at the bottom of the cell. A nitrogen gas
cement placement operation. Every effort should be made source is connected to a very sensitive device for measur-
to achieve this goal. If poor mud displacement takes place, ing gas entry. This, in turn, is connected to the bottom
the chances of controlling gas invasion of the well bore of the cell, which simulates a high-pressure gas zone. The
1042 JOURNAL OF PETROLEUM TECHNOLOGY
1500

• CLASS H+1.S .. FLUID LOSS ADDITIVE A+4 ... H 2 0


• THICKENING TlME-4 hr 30 mIn
• TEMPERATURE-US of
1250 • TOP HYDROSTATIC PRESSURE -1000 pal
• SIMULATED FORMATION GAS PRESSURE-SOO pal

Time 0' Inltl.' Pore Pr••• ur. Drop


SLURRY PORE PRESSURE 'i]
1000 8

... Time When Cement Support. the


H;droatetlc Load
7

ui
...."..
a: 750
_-'l----------- •
..
a:
Time of Tot.,
Dehydration
II E
u

500 ------+-----14 ..
~
:I
3 ~
o
250 2 :I
z
o
1 :;;
;;:
o~---~---~2---~3----L4---~---~--~~-----J80
TIME, hr

Fig. 2-Pore pressure vs. time in a slurry containing fluid-loss additive.

pore pressure of the cement slurry is recorded continuous- actual well. By using a small sample of cement, the gas
ly by using a pressure transducer located in the middle flow phenomenon in cements at the cement/formation in-
of the cell. The test cell can be heated to the test terface could be examined under different test conditions
temperature by means of a heating tape wrapped around without large slurry volumes masking the response of the
the cell. The temperature is monitored by a thermocouple cement/gas system.
inserted into the side of the cell. When a cement slurry is placed in the annulus behind
The general procedure for running tests using this gas the pipe, it is exposed to the hydrostatic pressure caused
flow apparatus is as follows: by the weight of the fluids on top of the slurry. It also
1. The slurry is mixed in a household blender accord- is exposed to a pressure differential across the cement/for-
ing to API procedures and then stirred for 20 minutes in mation interface (often with a filter-cake interlayer). The
an atmospheric consistometer at the test temperature. hydraulic piston in the apparatus simulates the weight of
2. Simultaneously, the test cell is preheated to the test the fluid column above the slurry. The open valves at the
temperature. top and bottom of the cell simulate the effect of the
3. The cement slurry then is poured into the cell from pressure differential across the cement/formation inter-
the top and a simulated hydraulic pressure is applied by face (the apparatus simulates the cement slurry exposed
using the piston. to highly permeable formations).
4. A simulated gas formation pressure then is exerted In an actual field case, the cement slurry can dehydrate
at the bottom of the test cell. across the gas-bearing zone. This also is simulated in the
5. Next, the valves on the piston shaft and at the bot- apparatus. By measuring the vertical movement of the
tom of the cell are opened. The filtrates from both ends piston, it is possible to observe the point at which the ce-
of the test cell are measured and recorded periodically. ment slurry lattice becomes structurally sound and capable
Periodically, the downward movement of the piston also of supporting the load of the fluid above it.
is measured carefully to determine when the cement
becomes load-bearing (no more piston movement) at the Discussion of Test Results
given constant hydraulic pressure applied to the piston. A large number of tests have been run using the gas flow
6. The gas flow rate, measured by the highly sensitive apparatus in an attempt to understand better the
gas flow measuring device at the bottom of the test cell,
mechanism of gas invasion at the cement/formation in-
is recorded periodically throughout the test period.
terface. Several of the tests are described in the follow-
7. For tests run at temperatures above 200 ° F [93 °C],
ing paragraphs.
the slurry is preheated as in Step 1 to 190°F [88°C]. The
cell is preheated to 200°F [93°C], the preheated slurry
is placed in the cell, and then the temperature is increased Test 1. This test was conducted at 165 ° F [74 ° C] using
to the test temperature with the cell valves closed. For a cement slurry containing 1.5 % of a fluid-loss additive,
these high-temperature tests, a backpressure of about 100 A. A constant simulated hydrostatic pressure of 1,000 psi
psi [690 kPa] is applied to the backpressure receiver. After [6.9 MPa] was applied to the piston. The simulated for-
the test temperature is reached, the valves are opened and mation gas pressure used was 500 psi [3.45 MPa]. Fig.
the test is performed as described. 2 shows a plot of the slurry pore pressure, as recorded
The apparatus was designed to study the phenomenon by the pressure transducer, vs. time. The graph also shows
of gas migration in a small sample of cement, under con- the downward vertical movement of the hydraulic piston
ditions similar to those seen with a cement slurry in an vs. time.
JUNE 1985 1043
1100
previously, the first small gas entry was detected at 4.5
• CLASS H + •• ~ "20
• TEMPERATURE-IO·'
hours after the pore pressure dropped below the simulated
formation gas fressure. A significant gas entry of 3.6
1210 - • TOP HYDROSTATIC .... E •• UIIE-fOOO pa_
• SIIiULATED FOR.ATION GAl PIIES'UIIE-IOO pal
mL/hr [3.6 cm Ih] at 500 psi [3.45 MPa] was measured
at 6 hours. At 6.5 hours, a much faster gas flow rate of
1000 r- -• about 8 mLlhr [8 cm 3 /h] at 500 psi [3.45 MPa] was

750
r -- _ .!.'.~N~O~M2T
-- - -
- ,: •
E
u
recorded. At the same time at the opposite valve, gas was
flowing at a rate of approximately 212 mLlhr [212
cm 3 Ih] (at atmospheric pressure).
- •z Test 1 showed that for as long as the cement pore
·
5 '"
500
SLURRY PORE PRE •• URE
- ~'" pressure remained above the formation gas pressure, gas
- ..•~
I did not enter the cement lattice. However, once the pore
3
pressure dropped below the formation gas pressure, gas
250 - 2 ii:• entered but not in large enough volumes to "recharge"
- 1 the structure. At that point in the test, the net pressure
o i I I o change in the cement lattice was still downward because
o 10 20 30 40
the slurry was still dehydrating. The structure "pore"
TIME, min
spaces eventually lost enough filtrate that the formation
Fig. 3-Pore pressure vs. time in a neat slurry. gas was able to "recharge" the lattice to a value equal
to the gas formation pressure. This test suggests that it
is necessary for the pore spaces to become partially or
fully void of filtrate for the formation gas to be able to
For more than 3 hours after the beginning of the test, penetrate the cement load-bearing structure. It also sug-
the slurry pore pressure remained constant and equal to gests that as long as the fluid inside the cement lattice is
the constant hydrostatic pressure applied to the piston. mobile, the formation gas eventually can displace it from
After that, the pore pressure started to decline. The slurry the pore spaces. Since conventional fluid-loss additives
pore pressure eventually dropped below the simulated con- are believed to control fluid loss by forming a filter cake
stant formation gas pressure and remained below it for at the interface of the cement with a permeable zone, they
about 2 hours. The cement pore pressure increased and by themselves appear to be incapable of immobilizing the
became equal to the formation gas pressure 6.25 hours fluid within the pore spaces of the cement lattice. One
after the start of the test. last point that should be made during the discussion of
During the time when the cement pore pressure re- this first test is that the cement structure pore pressure
mained above the simulated formation gas pressure, ce- is the controlling pressure when dealing with potential for-
ment filtrate was collected at the bottom and at the top mation gas invasion. The cement pore pressure is equal
of the cell. However, after the pore pressure dropped to the hydrostatic pressure (or load) above the cement col-
below the formation gas pressure, filtrate no longer was umn up to a point approaching the time when the cement
collected at the gas entry end, but the cement continued starts to become load-bearing. After that, the pore
to dehydrate at the other end of the cell. At that time, a pressure departs from the hydrostatil: pressure value.
small initial gas volume entered the cell. The cement
became completely dehydrated after 6.5 hours, as shown Test 2. This test was conducted at room temperature using
by the absence of filtrate leaving the cell. As indicated a neat Class H cement slurry with 46% water (see Fig.

1500r---------------------~==================================~
• CLASS H+ 1.0~ FLUID LOSS ADDITIVE B+45~ H20
• THICKENING TIME-4 ,..-
• TEMPERATURE-155 OF
1250
o TOP HYDROSTATIC PRESSURE-1000 pal
• SIMULATED FORMATION GAS PRESSURE-500 pal

SLURRY PORE PRESSURE


1000

..•. 7

...
Time When C.nient 8upport. the E
c 750 5 ..
",drolt.tlc Load
..:z
OJ
...
IE FORMATION GAS .".._ - -
-?------------#~-
Tim. 0' Tol., D.It,d,aUon I ;
OJ
500 _2!'~,!!!,!E_.-L_._. _ _ ._._._._._.;V~_.:t 4 ~

.
/.
."..
•~
250
/.".
/0""
/.".
",,, 3
...a:
I
/ ,,\.
/.,,0'" 2

0
0
T'ME. It,

Fig. 4-Pore pressure vs. time in a slurry containing fluid-loss additive.

1044 JOURNAL OF PETROLEUM TECHNOLOGY


UOOr-----;:::::;::::==========::::::;:::;::=:;--,
• eLA" H+ 1.0 .. FLUID LO •• ADDITIVI C
,+0.2'" .ITA.OIII . . . . ,. H.O

UIO
• THIC.II.... G TIIlI-a tt, ao .'ft • CLA" H+1.0" "LUID LO.' ADDITIVI •
+0.'" GA' OIN •• ATlNO POWD.II + .... "to
• TIII"I.ATURe-tIO·'
1110 • TIIIP •• ATU.I-1 •• ·,.
TO .. HYO.O,TATIC .... r •• Utll·1000 ... ,

p.' • TOP M'ID.O.TATIC P •••• UIII-1000 p.1
• IIIIULATED 'O.IIATION GA. ' .. I"UIII-IOO
AM •• tlft. ,.,1." • '.IIULATIO "O.IIATION OA' P •••• ullr·.oo p.'
1000

700

\ - ---- .'"'' "'.,,'!!. - -,...


710

- - - - - --------
'''TON 1I0VElieNT

;' 'OIlIIlATIOM GAl ."., -=


100 -~/,.-. 100 ....!'!~'!'!...-;.T""'. ILU.'" PO". PII . . .U.. ,'--

/ ,I"

110

I
/
/
'LUII • ., "oltr PRr"UIII 110
/
/
/
.
/ ..
1

~ _ _~_ _~_ _~_ _~_ _~_ _~IO 4'


TUllr, It,
Till', '"

Fig. 5-Pore pressure vs. time in a slurry containing fluid-loss Fig. 6-Pore pressure vs. time in a slurry containing fluid-loss
additive and retarder. additive and gas-generating powder.

3). The constant simulated hydrostatic pressure was 1,000 Test 4. Fig. 5 gives the pore pressure curve obtained when
psi [6.9 MPa] and the simulated formation gas pressure a third fluid-loss additive, C, was used, this time with the
was 500 psi [3.45 MPa]. Shortly after opening the cell addition of a retarder. As can be seen from the figure,
valves, the slurry dehydrated complet$!ly and the slurry the pore pressure started to decline almost immediately
pore pressure, as recorded by the transducer, dropped to after the test temperature (220°F [l04°C]) was reached.
the 500-psi [3.45-MPa] formation gas pressure. At 500 This probably was caused by the lesser fluid-loss control
psi [3.45 MPa] formation gas pressure, the gas flow rate available to the cement at this higher temperature. Three
was too high to be measured. Dropping the gas pressure hours into the test, a gas flow rate of 2.0 mLlhr [2.0
to 100 psi [690 kPa], a gas flow rate through the cement cm 3 /h] at 500 psi [3.45 MPa] was recorded. At 4 hours,
was measured at 36,000 mLlhr [36000 cm 3 /h] (at at- a pore pressure increase was noticed and a faster gas flow
mospheric pressure). This extreme case simulates the rate occurred. The gas flow rate was 134 mLlhr [134
situation that could occur when a cement slurry with no cm 3 /h] at 500 psi [3.45 MPa] at 4.5 hours.
fluid-loss control is exposed to a highly permeable zone.
It is very important to notice that the pore pressure in the Test 5. This test was run at 165°F [74°C] using a slurry
slurry became equal to the gas zone pressure almost in- with fluid-loss control Additive B and a small percentage
stantly, indicating instant invasion and "charging" of the of a finely divided, gas-generating powder (see Fig. 6).
dehydrated cement lattice by the formation gas. The pressure increase in the cell during the heating period
Notice also that the cement became load-bearing almost was caused by the temperature change and the genera-
instantly, and, in this case, the load was supported by a tion of a gas inside the cement slurry (the slurry could
dehydrated, "packed" cement column rather than a set not be preheated at atmospheric pressure without gas
column. generation). When comparing this test to Test 3 (see Fig.
4), higher fluid loss was observed in this test. This prob-
Test 3. Fig. 4 gives the data obtained when a different ably was caused by some reaction between the gas-
fluid-loss additive, B, was used in a simple Class H slurry. generating powder and the fluid-loss-control polymer, or
As in Test 1, the fluid-loss additive slowed down the for- by the presence of the third (gas) phase. About 1 hour
mation gas invasion of the cement structure, but even- into the test, the cement pore pressure started to decline.
tually the gas was able to charge the structure and the pore After 6 hours, a gas flow rate of 96 mLlhr [96 cm 3 /h]
pressure of the lattice again became equal to the forma- at 500 psi [3.45 MPa] was recorded. At 24 hours, the
tion gas pressure. At that point, the gas flow rate was gas flow rate was 1,704 mLlhr [1704 cm 3 Ih] at 500 psi
measured at 45.5 mLlhr [45.5 cm 3 /h] at 500 psi [3.45 [3.45 MPa].
MPa]. Notice that as the slurry approached the point of Fig. 6 shows that even though gas was being generated
full dehydration, the pore pressure of the lattice quickly inside the slurry, this gas, when exposed to the pressure
approached the gas formation pressure, indicating a faster differential across the cell, flowed within the system in-
recharging of the structure as the "pore" spaces became stead of staying in the matrix and repressurizing the ce-
void of the slurry filtrate. Again, this test suggests that ment. The fact that the pore pressure never dropped below
if the cement slurry filtrate could be immobilized inside the formation gas pressure during the test indicates total
the pore spaces of the cement structure, particularly invasion and charging of the cement matrix by the for-
around the time when the cement becomes load-bearing, mation gas as soon as the pore pressure became essen-
the formation gas could be prevented from invading the tially equal to the formation gas pressure.
matrix even if the pore pressure of the cement falls below It is possible that if the gas bubbles generated within
the formation gas pressure as the cement sets. As the slurry could have been kept from coalescing (perhaps
previously shown in the literature, the pore pressure will by somehow forming microspheric gas bubbles), a high
fall, even if little filtrate is lost, because of the hydration pore pressure could have been maintained in the cement
process. matrix. However, in each test run to date using the gas-
JUNE 1985 1045
1.00r-~----------------------;:::::::::::::::::::::::::::::~
• IMPERIIEABLE CEIIENT+4" H20
• THICKENING TIIIE-3 ~r 30 Iftln
• TEIIPERATURE-". of
1250 • TOP HYDROSTATIC PRESSURE-l000 pol
• SIMULATED FORMATION GAS PRESSURE-500 pol

SLURRY PORE PRESSURE

....1000

7
.; Time When Cen:-ent Support. the

~ 750 HycUoUaUc Load


_V_ _ _ _ _ _ _ _ _ _ __ , ~

.....
III
III
-4~

.
~
C

500
S

4 >
o
.
:I

:I
z
o.
3

260 Time 0' Total Dehydration 2 !!!


...
V

~--------L--------l4--------~--------~---=::==~1~0~~=====2~4 0
TIM£. tu

Flg.7-Pore pressure VS. time in an impermeable cement system.

generating powder, the generated gas' flowed from within The resulting slurry properties are a function of the slurry
the cement after the valves were opened and a pressure composition and the varying well conditions across the
differential was exerted across the slurry. cemented interval. These processes include dehydration
of the liquid phase, gelation of the slurry, settling of the
Test 6. This test was run at 165°F [74°C] using a slurry solid particles, and packing of the solid particles. The ac-
containing an additive that combines the effects of good tual process of setting of the cement slurry, initiated when
fluid-loss control and free water control (at bottomhole the water was first placed in contact with the cement, also
static temperature conditions) with mobility reduction of continues at a rate dependent on the slurry composition
the cement filtrate within the bulk of the cement struc- and the localized well conditions.
ture, particularly after the cement becomes load-bearing. At a given depth, one or more of these processes can
Fig. 7 gives the results of the test. As the figure shows, become dominant over the others, thus controlling the
the pore pressure in the cement system still dropped, changes in the behavior of the slurry. Initially, the whole
because a certain amount of filtrate was lost from the cement slurry column behaves as a "pure" fluid and fully
system from the beginning of the test until the time of transmits the hydrostatic load caused by its own head plus
total dehydration. the head of the fluids above it. As the processes of
However, the gas flow rate in this experiment decreased dehydration, gelation, settling, packing, and setting of the
from an initial value of 0.3 mL/hr [0.3 cm 3 /h] at 500 psi slurry progress in time at the different depths along the
(3.45 MPa] before total dehydration to 0.11 mLlhr [0.11 cement column, changes occur in the cement slurry, caus-
cm 3 Ih] at 500 psi [3.45 MPa] after total dehydration and ing it to depart from the behavior of a pure fluid. The
finally to a value of 0.004 mLlhr [0.004 cm 3 /h] at 500 cement slurry placed across the gas formation zone even-
psi (3.45 MPa] after 24 hours. These numbers, combined tually becomes sufficiently dehydrated, gelled, packed,
with the fact that the pore pressure never showed signs and/or set at the given well conditions that the structure
of increasing toward the gas formation pressure, indicate formed by its cement particles plus the liquid left in the
that the formation gas never was allowed to "recharge" matrix is capable of supporting most of the load being
the structure to any appreciable extent. Eventually, the transmitted to that portion of the cement.
pore spaces were "choked" by the hydration process. The Once the cement structure across the gas zone can sup-
small volume of low-pressure formation gas that had port most of the load, the cement becomes load-bearing.
penetrated the lattice was incapable of preventing the clos- About the time when the cement becomes load-bearing,
ing of the pore spaces and eventually the cement became the pore pressure inside the cement structure no longer
practically impermeable to the gas. Notice that since very is controlled by the hydrostatic load transmitted to the ce-
little gas penetrated the structure, the "pore" pressure ment and, therefore, from this point on, further losses of
of the cement matrix remained very low throughout the liquid volume from the cement matrix (by dehydration
remainder of the test. or by the actual setting process) are reflected in substan-
tial cement pore pressure changes. As the pore pressure
A Mechanism of Gas Migration in the cement structure continues to drop, it eventually
Based on the previous test results, the following theory becomes essentially equal to the pressure of the forma-
of the mechanism of gas invasion of cements in a wellbore tion gas. Any further decrease in cement pore pressure
is proposed. can potentially allow the gas to invade the cement pore
After the cement is displaced and left static behind the spaces, since the cement permeability to gas in this early
pipe, several processes start to take place in the slurry. life of the cement can be very high. If invasion occurs,
1046 JOURNAL OF PETROLEUM TECHNOLOGY
the gas can eventually penneate the whole cement matrix, Case 3: Hardin County, TX. A well was drilled to a
charging it with enough gas (and pore pressure) to inhibit depth of 12,500 ft ~3810 m] with a mud density of 18.3
the hydration process from closing the pore spaces. Ibm/gal [2.19 g/cm ]. To control a lost circulation prob-
lem encountered at approximately 12,200 ft [3718 m], the
Preventing Gas Invasion Into Cement mud density was cut back to 17.1 Ibm/gal [2.05 g/cm 3],
Slurry Matrix but gas started to enter the wellbore. The job used 1,064
One way to control gas migration at the cement/forma- sacks of the impenneable cement at a density of 17.6
tion interface is to reduce the mobility of the cement Ibm/gal [2.11 g/cm 3] were used in this job. No gas cut-
flltrate within the pore spaces of the cement lattice. Also, ting was detected either after the job or after drilling to
fluid-loss-control additives generally do not immobilize TD. The well is currently on production without any gas
the flltrate inside the pores, but at the filter cake. migration problems.
An obvious way to reduce the mobility of the filtrate
Case 4: Fayette County, TX. A blowout occurred dur-
within the cement pore spaces is to increase the flltrate
ing the first attempt to cement this well. After killing the
viscosity within the structure at the test temperature by
well, the operator decided to recement it using the im-
using a polymeric material. Also, the throats of the pore
penneable cement. The TD of the well was 7,225 ft [2202
spaces can be bridged with properly sized swellable bridg-
m] and the following slurries were used: (1) lead slurry
ing particles to reduce even more the mobility of the ce-
composed of 297 sacks of Class H plus 8 % gel plus 0.25 %
ment flltrate. This mechanical bridging of the pore spaces
retarder plus 0.25 Ibm/sack [0.01 kg/sack] cellophane
keeps the flltrate in place and also restricts the gas entry
flake plus 9.97 gal/sack [0.04 m 3 / sack] mix water and
into the matrix. These goals can be achieved by selecting
(2) tail slurry composed of 330 sacks of the impenneable
polymeric materials and bridging agents properly. If the
cement plus 5.19 gal/sack [0.02 m 3 /sack] mix water. No
fluid was immobilized (or if the mobility of the fluid was
gas flow was detected after the job. The well is on pro-
greatly reduced) inside the pore spaces, thus keeping the
duction at this time without any reported gas problems.
pores full of fluid, the fonnation gas would not be able
to invade the matrix and, for all practical purposes, an Conclusions
"impermeable" cement would be created.
A system using these gas migration control principles 1. Gas does not invade the cement matrix as long as
was developed and the test results were discussed under the cement pore pressure remains above the formation gas
Test 6. pressure.
2. Conventional fluid-loss additives that function by
Field Cases forming a fllter cake at the interface of the cement with
a penneable zone are not adequate to prevent the inva-
At the writing of this paper, more than 300 jobs had been sion of fonnation gas into the cement matrix.
perfonned using this impermeable cement system. All 3. Generating a gas phase in a cement slurry may not
four major types of cementing jobs (casing, liner, plug, prevent the invasion of formation gas into the cement
and squeeze) have been perfonned using the impenneable matrix if the gas bubbles generated coalesce and fonn gas
cement system, and an overall success ratio of more than channels.
90% has been obtained. Some representative case histories 4. Invasion of fonnation gas into the cement matrix can
are presented. be prevented by immobilizing the fluid within the pore
Case 1: Galveston County, TX. Gas-cutting had been spaces through proper selection of polymeric materials
a serious problem in this field for a long time. In this par- and bridging agents.
ticular well, several high-pressure gas sands existed below
Acknowledgments
the producing oil sand. Many squeeze jobs had been per-
formed without success by various service companies We wish to express our sincere appreCIatIOn to the
using different additives. A low-pressure squeeze job was management of The Western Co. of North America for
perfonned at a depth of 8,980 ft [2737 m] using 35 sacks pennission to prepare and to publish this paper. We also
of the impenneable cement. No gas leakage was ex- thank those who offered suggestions in the preparation
perienced after the job. Since then, four more successful of this paper, especially David Williams with The Western
squeeze jobs have been performed in this field by using Co. of North America, who developed much of the data
the impenneable cement. and solved many of the mechanical problems when design-
ing and building the gas flow simulator.
Case 2: Hardin County, TX. The operator was con-
cerned about potential gas migration problems in this well References
since gas migration was common in the area. The total 1. Evans, G.W. and Carter, L.G.: "Bonding Studies of Cementing
depth (TD) of the well was 7,965 ft [2428 m]. There was Compositions to Pipe and Formations," Drill. and Prod. Prac.,
a weak zone (low pressure) 200 ft [61 m] above the gas API, Dallas (1962) 72-79.
zone. The following slurries were used to cement this 2. Carter, L.G. and Evans, G.W.: "A Study of Cement-Pipe Bond-
ing," 1. Pet. Tech. (Feb. 1964) 157-60.
well: (1) lead slurry composed of 420 sacks of commer- 3. Bearden, W.G., Spurlock, J.W., and Howard, G.C.: "Control and
ciallightweight cement plus 10% salt plus 0.2 % retarder Prevention oflnter-Zonal Flow," 1. Pet. Tech. (May 1965) 579-84;
plus 6.75 gal/sack [0.03 m 3 /sack] mix water and (2) tail Trans., AIME, 234.
slurry composed of 250 sacks of impenneable cement plus 4. Scott, J.B. and Brace, R.L.: "How Coated Casing Reduces Primary
Cementing Failures," World Oil (Aug. 1966) 66-69.
5.19 gal/sack [0.02 m 3 /sack] mix water. The job went 5. Carter, L.G. and Slagle, K.A.: "A Study of Completion Practices
well and the operator reported no gas leakage after the to Minimize Gas Communication," 1. Pet. Tech. (Sept. 1972)
cementing operation. 1170-74.

JUNE 1985 1047


6. Stone, W.H. and Christian, W.W.: "The Inability of Unset Ce- 14. Webster, W.W. and Eikerts, J.V.: "Flow After Cementing-A Field
ment to Control Formation Pressure," paper SPE 4783 presented Study and Laboratory Model," paper SPE 8259 presented at the
at the 1974 SPE Symposium on Formation Damage, New Orleans, 1979 SPE Annual Technical Conference and Exhibition, Las Vegas,
Feb. 6-7. Sept. 23-26.
7. Howard, G.C. and Clark, J.B.: "Factors to be Considered in Ob- 15. Sabins, F.L., Tinsley, J.M., and Sutton, D.L.: "Transition Time
taining Proper Cementing of Casing," Drill. and Prod. Practices, of Cement Slurries Between the Fluid and Set State," paper SPE
API, Dallas (1948) 257-72. 9285 presented at the 1980 SPE Technical Conference and Exhibi-
8. Christian, W.W., Chatterji, J., and Ostroot, G.W.: "Gas Leakage tion, Dallas, Sept. 21-24.
in Primary Cementing-A Field Study and Laboratory Investiga- 16. Sabins, F.L. and Browning, P.L.: "Cement Compressibility
tion," J. Pet. Tech. (Nov. 1976) 1361-69. Evaluated," Drill Bit (Feb. 1982) 67-69.
9. Garcia, J.A. and Clark, C.R.: "An Investigation of Annular Gas 17. Kettle, F. and Sabins, F.: "New Method Solves Gas Flow Through
Flow Following Cementing Operations, " paper SPE 5701 presented Cement," Western Oil Reponer (Feb. 1982) 141-43.
at the 1976 SPE Symposium on Formation Damage Control,
Houston, Jan. 29-30.
10. Cook, C. and Cunningham, W.C.: "Filtrate Control-A Key in SI Metric Conversion Factors
Successful Cementing Practices," J. Pet. Tech. (Aug. 1977) 951-56. OF (OF-32)/1.8 °C
11. Griffin, T.J., Spangle, L.B., and Nelson, E.B.: "New Expanding
Cement Promotes Better Bonding," Oil and GasJ. (June 25, 1979) in. x 2.54* E+OO = em
143-51. psi x 6.894757 E+OO kPa
12. Levine, D.C. etat.: "Annular Gas Flow After Cementing: A Look
at Practical Solutions," paper SPE 8255 presented at the 1979 SPE
Annual Technical Conference and Exhibition, Las Vegas, Sept. • Conversion lactor is exact. JPT
23-25.
13. Tinsley, J.M., Miller, E.C., and Sutton, D.L.: "Study of Factors Originel manuscript received in the Society 01 Petroleum Engineers office Aug. 27,
1982. Peper accepted lor publication Aug. 10, 1984. Revised manuscript received April
Causing Annular Gas Flow Following Primary Cementing, " J. Pet. 15,1985. Peper (SPE 11207) lirst presented at the 1982 SPE Annual Technical Con·
Tech. (Aug. 1980) 1427-37. lerence and Exhibition held in New Orleans Sept. 26-29.

1048 JOURNAL OF PETROLEUM TECHNOLOGY

You might also like