የኢትዮጵያ ኤሌክትሪከ ኃይል Reppie Waste to Energy Power

Project Pages = 3
Ethiopian Electric Power
Weekly Report

Ethiopian Electric Power


Reppie Waste to Energy Power Project

Weekly Report Format

Date; September 29, 2016

Report No. : _Reppie 101/2016___


1. Project Contract No. No. 33.20/41/05 Dated 04 January, 2013
2. Contractor’s Name:
EPC Contractor: Cambridge Industries Ltd. & its partner CNEEC
Plant Contractor: China National Electric Engineering Co. Ltd. [CNEEC]
3. Location of the work: __Addis Ababa, Koshe Project Site____________________________________________
4. Specific location of the work:

 √ Power House  √ SWY  √ Site Work Shop

    √ Others

5. Weather Condition (Optional): _sunny _____________________________


6. Detail Description of the activity: Design, Construction, Quality assurance as per the contract documents
7. Resource at site (Optional)
7.1 Man power(civil work): 63 local workers,9 local security guards, 24 management team members (CIL-
CNEEC), 2 woodworker & Scaffolder, 7 erection worker, and 40 Chinese workers.
7.2 Man power (M&E erection work): 29 management team members, 13 welder, 66 filters, 28 electrical
erection, 5 Turbine erection & 10 workers.
8. Machinery: mobile Crane(65t & 25t)-2, 400t crane, mixing machine-3, Dump Trucks(15t)-8, tamping machine-7,
forklift(3t and 5t)-2, pumping truck-1, diesel generator-4 , loader-1, water pump-4, 2501mixer truck-2, 7501
concrete mixture-2, electric welding machine- 8, emergency diesels -4(220kw & 75kw), concrete vibrator-10,
MC80Atower crane(80t)-1, Crawler crane (150t)-1, AC welder(type 500)-8, DC welder(ZXS-630)-4, Electric hand
drill-10.
9. Work Progress: 86.24%
Description
Design Work

(A)Civil Work

 Tipping hall: - steel roof truss secondary structure is 80% completed.


 Waste banker: - Banker wall and bottom anticorrosion is 90% completed.
- Small installation (water supply and drainage, electrical lighting, firefighting, HVAC
and lighting protection is in progress.
 Turbine hall:- Small installation (water supply and drainage, electrical lighting, firefighting, HVAC and
lighting protection is in progress.
 Leachate treatment station (comprehensive workshop):-
- Indoor putty work at L+4.00m is 100% completed.
(B)Erection work
 2#Boiler steam and water system erection is 30% completed.
- 2#Boiler left side water wall assembling is 100% completed.
- 2#Boiler rear side parapet wall water wall preassembling is 100% completed.
- 2#Boiler left rear wall water wall preassembling is 50% completed.
- 2#Boiler font partition wall water wall preassembling is 50% completed.
 1# Boiler De-acidification tower steel structure erection is 50% completed.
 Boiler Hall electrical equipment support erection is 80% completed.
 Main building electrical equipment connection is 5% completed
 Cable bracket erection is 25% completed.
 cable laying for the system is 5% completed.
 Leachate equipment erection is
- Nitrification tank erection is 25% completed.
- De-nitrification tank erection is 25% completed.
- Anaerobic tank erection is 5% completed.

Fig. Errection of steel structure

Safety and health


 No injury or accident was reported on this week.

Manufacturing
 Manufacturing work at the contractor’s facilities continues.

shipping:
25th shipment, Cable and steel structure, frequency conversion cabinet (145 packages and 2 containers in total). 2
containers arrived, break cargo truck loading started. 25 packages arrived.

26th shipment, Air pre-heater (was shut out on june16) valves, steam soot-Blower, pipes, windows and doors, etc. (101
packages and 8 containers in total. Truck loading started. 7 containers arrived.

Power house

CNEEC Store

Workshop

For Inspectors /EEP/ For the Team Leaders/EEP/

Name :_ Aklilu Admasu Name: Bilchaye Abay_______

Signature : ______ _ _ _ Signature : ___________________