Professional Documents
Culture Documents
Risk Management Package
Risk Management Package
Methodology
The risk owner will be for all risks (the same as the "risk
manager"). The project manager will be responsible for
coordination, while the project sponsor will manage all
external stakeholders.
Risk Categories
Risks will be organized as follows to the first level of the
RBS: 1) Strategic 2) Financial 3) Procedural 4) Other
Page 1 of 5
RISK MANAGEMENT PLAN
Risk Management Funding
Contingency Protocols
Risk ID 1 Risk Description If inverter manufacturer declares default, some deliveries will be not done according to the schedule, causing a delay of
2 weeks on contractual completion
Status open Risk Cause Manufacturer default
Impact
Score (*) Responses
Scope Quality Schedule Cost
Probability 20.00%
125,000 25000 Looking for some inverters available on the
market
Residual Risk New supplier could deliver inverter that is not the same quality level
Fallback Plans Ask supplier to cross-check customer acceptance creteria to be prapared for product modification.
Comments We should verify the project economical company situation of our inverter supplier.
Risk Register (Record 2)
Project Title: Date Prepared:
Risk ID 1 Risk Description If inverter manufacturer declares default, some deliveries will be not done according to the schedule, caus
2 weeks on the contractual completion
Status open Risk Cause Manufacturer default
Impact
Score (**) Responses
Scope Quality Schedule Cost
Probability high
medium 0.08 looking for some inverters
on the market
Example of numeric score Revised medium Revised Impact Revised Score (**) Risk owner
Probability
Scope Quality Schedule Cost
low 0.03 Mr. Howard
Example of relative score Secondary Risks customer missed approval during acceptance test
Residual Risk new supplier could deliver inverter of not the same quality level
(**) you should find the relative hire an inverter installation expert Contingency Time
percent into the third tab both Fallback Plans ask supplier to cross check customer acceptance creteria to be prapared for product modification
probability and impact
Comments We should best verified , for new project economical company situation of our inverter supplier
according to the schedule, causing a delay of
Responses
50,000
1 month
IMPACT ASSESSMENT
Element Rating Threats Opportunities
Scope impact Very high The product does not meet the objectives and Scope requirements met with significant
is effectively useless. decrease in effort and/or cost.
High The product is deficient in multiple essential Scope requirements met with noticeable improvement in effort
requirements. and/or cost.
Medium The product is deficient in one major requirement Scope requirements met with minimal improvement in effort
or multiple minor requirements. and/or cost.
Low The product is deficient in a few minor requirements. Insignificant impact.
High Between 10% and 20% overall schedule increase. Between 10% and 20% overall schedule.
Medium Between 5% and 10% overall schedule increase. Between 5% and 10% overall schedule decrease.
Low Noncritical paths have used all their float, or overall Noncritical paths have used all their float, or overall
schedule increase of 1% to 5%. schedule decrease of 1% to 5%.
Very Low Slippage on noncritical paths but float remains. No change on critical path duration.
Cost impact Very high Cost increase of greater than 20%. Cost decrease of greater than 20%.
Low Cost increase that requires use of all contingency funds. Cost decrease of <5%.
Very Low Cost increase that requires use of some contingency but some contingency funds remain. Insignificant impact.
PROBABILITY ASSESSMENT
Probability Very high The event will most likely occur: 80% or The event will most likely occur: 80% or
greater probability. greater probability.
High The event will probably occur: 61% to 80% probability. The event will probably occur: 61% to 80% probability.
Medium The event is likely to occur: 41% to 60% probability. The event is likely to occur: 41% to 60% probability.
Low The event may occur: 21% to 40% probability The event may occur: 21% to 40% probability.
Very Low The event is unlikely to occur: 1% to 20% The event is unlikely to occur: 1% to 20%.
RATING ASSESSMENT
Rating Threats Opportunities
High Any event with a probability of medium or above and a very high impact on any objective. Any event with a probability of medium or above and a very high impact on any objective.
Any event with a probability of high or above and a high impact on any objective. Any event with a probability of high or above and a high impact on any objective.
Any event with a probability of very high and a medium impact on any objective. Any event with a probability of very high and a medium impact on any objective.
Any event that scores a medium on more than two objectives. Any event that scores a medium on more than two objectives.
Medium Any event with a probability of very low and a high or above impact on any objective. Any event with a probability of very low and a high or above impact on any objective.
Any event with a probability of low and a medium or above impact on any objective. Any event with a probability of low and a medium or above impact on any objective.
Any event with a probability of medium and a low to high impact on any objective. Any event with a probability of medium and a low to high impact on any objective.
Any event with a probability of high and a very low to medium impact on any objective. Any event with a probability of high and a very low to medium impact on any objective.
Any event with a probability of very high and a low or very low impact on any objective. Any event with a probability of very high and a low or very low impact on any objective.
Any event with a probability of very low and a medium impact on more than two objectives. Any event with a probability of very low and a medium impact on more than two objectives.
Low Any event with a probability of medium and a very low impact on any objective. Any event with a probability of medium and a very low impact on any objective.
Any event with a probability of low and a low or very low impact on any objective. Any event with a probability of low and a low or very low impact on any objective.
Any event with a probability of very low and a medium or less impact on any objective Any event with a probability of very low and a medium or less impact on any objective.
PROBABILITY & IMPACT MATRIX
The Probability and Impact Matrix is a grid for mapping the probability of each risk
occurrence and its impact on project objectives if that risk occurs. The Probability and
Impact Assessment determines the probability and impact of the risk. It may be
constructed for threats and opportunities. This matrix provides a helpful way to view
the various risks on the project and prioritize them for responses. It also provides an
overview of the amount of risk on the project. The project team can get an idea of the
overall project risk by seeing the number of risks in each square of the matrix.
The organizations overall risk tolerance is usually indicated by the shading or range of cells
within the matrix. For example, an organization with a low risk threshold may rank events that
fall in the very high or high range for both impact and probability as high risk. An organization
with a higher risk threshold may only rank risk with a very high probability and impact as high
risk.
The organization may use the relative risk rankings to specify what type of risk
response should be taken.
For example, the organization may specify an avoidance strategy for all threats that are
ranked as high risks.
A project with many risks in the dark gray zone will need more contingency to absorb the risk,
and likely more time and budget to develop and implement risk responses. In some situations,
a decision is made not to pursue a project because there is more risk than the organization is
willing to absorb.
A sample Probability & Impact Matrix follows. The needs of your project will determine the
exact layout of the matrix.
Very High
High
Medium
Low
Very Low
Scope Quality
evised Impact Revised Score (*) Risk owner Actions
Schedule Cost
Secondary Risks Residual Risk Contingency Plan
0
Comments