Professional Documents
Culture Documents
IFR Installation Manual March 2016 PDF
IFR Installation Manual March 2016 PDF
Installation Instructions
2. USING STRING LINES; ALWAYS CHECK THAT MAIN-BEAMS ARE STRAIGHT BEFORE
TIGHTENING PONTOONS. PONTOONS WILL LOCK MAIN BEAMS INTO POSITION. A
LITTLE TIME CHECKING I-BEAM STRAIGHTNESS WILL AVOID MAJOR PROBLEMS
LATER ON.
3. WHEN MAIN BEAMS SAG BETWEEN SUPPORTS, PUT A TEMPORARY SUPPORT MID-
SPAN. NEVER FIX A SHEETING CLAMP CHANNEL WITH A MAIN I-BEAM SAGGING,
OTHERWISE THE I-BEAM WILL REMAIN LOCKED IN A SAGGED POSITION. (See
Steps 25 & 26).
4. WHERE MAIN I-BEAMS CONNECT TO THE RIM, ALWAYS CHECK MAIN BEAM
SPACING. YOU CAN CHECK THIS BY TEMPORARILY HOLDING A STANDARD
CROSS-BEAM SQUARELY BETWEEN 2 MAIN BEAMS. (See Fig. 8).
5. USE STRING LINES TO CHECK THE IFR IS BUILT LEVEL. IN TANKS ABOVE
30m(100ft) DIA. STRING LINES SAG TOO MUCH SO USE A LASER LEVEL .
6. LANDING LEGS ARE TO BE CROSS DRILLED AND A SUPPORT BOLT FITTED TO SET
THE IFR HEIGHT. BECAUSE OF VARIATIONS IN FLOOR LEVEL, CROSS-DRILLED
HOLE HEIGHTS VARY. WHEN INSTALLING THE SHEETING, IT IS NECESSARY TO
TEMPORARILY REMOVE LANDING LEGS. BE CAREFUL TO RE-INSTALL THE SAME
LEG IN THE SAME LOCATION.
Step 1 Install Airscoops, overflow vents, and weld anti-rotation cable anchors to the floor as per Matrix drawing
IFR300. Fit diffuser to inlet nozzle if required. All cutting and welding is to be finished before starting IFR
installation work. All paint work should be completed prior to IFR installation.
Step 2
Check the tank inside. The surface of the shell (and any columns) should be smooth, without any sharp edges.
This means that any items welded to the shell or columns (in the path of the IFR rim seal or column seals), must
be removed, and the area made smooth. Main Columns should be checked for verticality and corrected if outside
API650H requirements.
Step 3
Install the overflow vents and Airscoops (see Matrix Drawing No. IFR300). If possible this is best done before the
IFR arrives at the job site. This requires cutting holes in the roof and shell, and welding of:
a) The Airscoop frames to the roof, including modification to handrails if necessary.
b) The Overflow vents to the shell
c) The Anti-Rotation cable anchor brackets to the tank floor
Step 4
Arrival of the container containing the IFR at site:
It is advisable to leave IFR components inside the container until installation. This prevents loss and/or damage of
components.
If there is more than 1 IFR packed in a container, look for colour coding. Each IFR will be marked with a separate
colour.
Step 5: Before loading the components into the tank, do the following:
a) Determine the roof installation height. The recommended construction height is the
lowest height that will allow personnel to pass through the manway.
To achieve this, drill holes in the leg as shown for each Rim Leg Sleeve. This work can
be done outside the tank. See Fig. 1.
Inside the tank, insert the landing leg into the Rim Leg Sleeve, and fit the 5/16” x 2-1/2” cross bolt.
Step 9: Lift up 2 rim segments and connect them together as shown in Fig 5.
Rim connection bolts are 3/8” x 1-”. Use 2 flat washers per bolt.
Continue around the tank until you arrive at the starting point.
If there are 2 makeup segments, they are to be diametrically opposite to each
other as shown in Fig. 3.
If it is difficult to fit the final rim segment, ease off the rim spacers around the tank
until you can fit the final segment.
IMPORTANT: MAKE SURE THERE ARE NO GAPS AT THE RIM SEGMENT JOINTS. If there are
gaps
between the rim segments this will alter the IFR diameter & later on, you will have problems
fitting the main beams. (see also Note below).
AFTER FITTING THE FINAL SEGMENT, RELEASE THE TEMPORARY RIM SPACERS.
Note 1:
The beams on the Matrix Heavy Duty IFR are accurately cut to length to suit a ROUND
internal floating roof. If the rim-space is set equal everywhere, it is possible that the IFR rim
will not be perfectly round, if the shell is out-of-round.
This creates a problem with fitting pre-cut beams designed for a round IFR.
Step 11: Carefully mark a point 815mm offset from the 0° to 90° string line. Install a new string line as
shown in Fig. 7.
This string line is to run parallel to the centre string line with 815mm offset.
Step 12: From one end of the tank, construct the 2 central beams on the floor. Include cross beams
and leg supports where indicated on the drawing. Assemble the make-up end main beams plus
standard length main beams on the floor.
Put legs through the leg sleeves. Prepare temporary supports. Assemble enough men to lift the
assembled 2 central main beams to rim height and lift the main beams into place. Using 10R and
11SP Vise Grips, clamp the main beams to the rim as shown below.
Straight
Connector
PEM Stud
Straight
Connector
Step 14: Setting centre deck leg height.
For each main beam run, set the deck level by running a very tight string line from the top of
the rim to the top of the rim at the other end of the beam run. Use string lines up to a tank
diameter of 30m (100ft). Above 30m dia, there is too much string sag, so use a laser level.
Once deck level is set, mark and drill the leg, and fit a 5/16” x 2-3/4” bolt and nut as shown
below. Leg locations to be as per plan drawing.
Centre Deck
Leg Sleeve
Assembly
Step 15:
Now continue installing main beams Row 2. Refer to Fig. 8 and Fig. 9 below
Be careful to ensure the correct Main Beam spacing where Beams connect to the rim. This
can be checked by holding a STANDARD CROSS BEAM squarely between the main
beams before clamping the beam to the rim. (See Fig 8 above).
Angle Centre
connector Deck
Leg
Sleeve
STRING LINE
(pull tight)
Centre
pontoons
Step 17:
Fit the remainder of the beams, leg sleeves, legs and cross beams to complete beam/main structure
installation.
Step 18: If a shoe seal is to be fitted, install this now as per the separate installation
instructions. Fit the vapour barrier fabric after the sheeting is installed. See Step 30.
Pontoon
Strap clamp
plate
Sheeting
Screw
Pontoon Strap
IFR227 IFR277
Rim
PEM Pontoon
Stud Plate
Pontoon
longitudinal
weld-seam
Now prepare to fit the first central sheet(sheet ‘O’). Fit at least 4 temporary supports per open bay
under the sheeting, (see photo, above right).
1. Rim creep on large diameter tanks (150ft ~ 45m diameter & bigger) When installing the main
beams furthest from the tank centre on large tanks, you may encounter rim creep. That is, the rim
circumference is bigger that it should be. The gap between adjacent rim segments has been
1mm or so too big & this has accumulated to make the rim circumference bigger than it should
be. It may become difficult to pull the rim in to properly fit the end beams. We try to allow for this
problem by slightly shortening the rim segments at Matrix factory. If you have this problem, you
may need to cut a small section from the last rim segment. Sometimes, it has been necessary to
cut 100 ~ 150mm from the rim length. This allows the rim to move inward & correctly meet with
the end beams.
2. The IFR is moving about too much. If the IFR is built in a very high position, sometimes there
is much IFR movement with people walking on it. There is always a slight possibility of the IFR
rotating & causing a leg failure as the IFR spirals downward. This is most unlikely, however for
safety’s sake it is a good idea if the IFR is moving around, to re-fit some of the rim spacers and
lock the IFR to any columns in the tank. See diagram below.
SCREW GUN USE: The recommended Makita screw gun has a maximum torque adjustment.
Set torque to the minimum to properly tighten the screws. If the torque is set too high or screws
are not inserted vertically, screws may break. Broken screws cannot be easily removed. Drill a
new clearance hole in the clamp channel and re-fix another screw next to any broken one.
TIP: Allow the screw gun to cool: Electric motors have an internal fan to cool the internal
windings. Repeated screw insertion at low RPM does not allow the motor to get enough cooling
particularly in hot working conditions. This can lead to screw gun motor burn out.
Remedy: Keep your finger on the trigger to get the motor to spin at full speed between screws,
thereby allowing the internal fan to do its job and cool the internal windings.
wrinkled edge
SHEET
SHEET
1-1/2” pipe
Screw jack
& base
here
hole in the sheeting & replace the landing leg and cross-bolt,
together with the top cap item IFR107. Fit the leg sleeve
gasket supplied between the sheeting &top cap. Remove
temporary support.
Clearance hole
Speed nut
Fit rim bolts with speed nut Make clearance hole in the sheeting
Safety Note!
DO NOT WALK ON THE SHEETING NEAR THE RIM .
STEP ONLY ON TEMPORARY SUPPORTS OR TIMBERS.
You may safely walk on sheeting near the rim after the seal & rim bolts are tightened.
1. Angle connector
2. Straight
connector
5. Pontoon Saddle
6. Pontoon Strap
7.Pontoon Strap
Clamp Plate
9. Sheeting Screws
18V/24V Battery Drill 10mm (3/8") variable speed, reversible with clutch/torque settings 2 2 3 3 4 4
and spare battery (Lithium Ion) for each drill
Bricklayers Nylon String Line 50m 100m 150m 200m 250m 300m
No. 8 gauge
See dwg Adjustable Height Pipe Stands (Screw Jacks) (IFR503A) 20 40 60 80 100 120
SK-2 + pipes to suit pipe stands (to suit pipe stand x ~1200mm long depending on IFR height) 20 40 60 80 100 120
attached (working height = distance ~ floor to top of manhole + 300mm(12"))
Drill Bit 5/16" or 7.9mm dia.(Must be this dia. for PEM studs ) 4 5 5 5 8 10
Drill Bit 3/8" or 10mm dia. 2 3 3 3 4 6
Razor knife 2 3 4 4 4 4
Nylon Hammer 2 2 2 2 2 2
150 x 45 (6" x 1 -3/4") softwood timber Dress finished x 3.6m (12ft) long (smooth) 4 8 10 15 20 24
100 x 50 (4" x 2") softwood timber x 1685mm long (smooth) 30 60 90 130 160 190
Extension cables & Power Boards to reach all over the tank
(with earth leakage safety devices) As Req. As Req. As Req. As Req. As Req. As Req.
50 [1.97]
'I' BEAM CNETERS
MAX.
100 [3.94]
2"x4" TIMBER
PAPER
TANK
28/12/01 HT.
TANK
AND SHALL BE USED ONLY FOR THE
INTENDED PURPOSE AND PROJECT. LOCATION: SIZE A3 No.
IT MAY NOT BE COPIED IN WHOLE
OR IN PART. PARTS MAY NOT BE DRAWING TITLE DRAWING NUMBER REV.
NOTES: FABRICATED FROM THE DOCUMENT,
AND THE INFORMATION THEREIN
1. UNLESS OTHERWISE STATED ALL DIMENSIONS IN MILLMETERS/[INCHES].
REV. DETAILS DATE BY
MAY NOT BE DIVULGED WITHOUT
MATRIX APPLIED TECHNOLOGIES
EXPRESS WRITTEN PERMISSION.
TIMBER TEMPORARY SUPPORT IFR502 0
Note: Experience has shown that contractors
installing IFRs frequently try to save money by not
buying the above tools. This is false economy. These
tools will pay for themselves by saving labour cost &
helping to ensure a quality installation. We strongly
recommend purchase of correct tools before starting
IFR assembly.
API 650
S.4.10.2 f, states the following; “The chloride content of the water
shall be below 50ppm unless specified otherwise by the Purchaser”.
S.4.10.3 “When testing with potable water, the exposure time shall
not exceed 21 days, unless specified otherwise by the Purchaser”.