You are on page 1of 12

Journal of the Operational Research Society

ISSN: 0160-5682 (Print) 1476-9360 (Online) Journal homepage: https://www.tandfonline.com/loi/tjor20

Project portfolio implementation under


uncertainty and interdependencies: A simulation
study of behavioural responses

Lin Wang, Martin Kunc & Jianping Li

To cite this article: Lin Wang, Martin Kunc & Jianping Li (2019): Project portfolio implementation
under uncertainty and interdependencies: A simulation study of behavioural responses, Journal of
the Operational Research Society, DOI: 10.1080/01605682.2019.1609890

To link to this article: https://doi.org/10.1080/01605682.2019.1609890

Published online: 21 May 2019.

Submit your article to this journal

Article views: 107

View related articles

View Crossmark data

Full Terms & Conditions of access and use can be found at


https://www.tandfonline.com/action/journalInformation?journalCode=tjor20
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY
https://doi.org/10.1080/01605682.2019.1609890

Project portfolio implementation under uncertainty and


interdependencies: A simulation study of behavioural responses
Lin Wanga, Martin Kuncb and Jianping Lia
a
Institutes of Science and Development, Chinese Academy of Sciences, Beijing, China; bSouthampton Business School, University
of Southampton, Southampton, UK

ABSTRACT ARTICLE HISTORY


Even though systems thinking has been highlighted in portfolio management theory, inde- Received 10 September 2018
pendent project control logic still dominates its implementation process. This paper Accepted 13 April 2019
constructs a system dynamics model for portfolio monitoring and control. Considering the
KEYWORDS
on-going portfolio as a complex social system, the impacts of project interdependencies
System dynamics;
(PIs) on portfolio decision-making are investigated under a behavioural paradigm. Our find- behavioural OR; project
ings indicate the remedial actions, affected by behavioural factors like planning fallacy and portfolio; uncertainty
“Pet project” effects, may generate escalation of commitment under specific levels of uncer-
tainty and interdependencies. Thus, portfolio coordination decisions should be made from a
strategic perspective with the consideration of complexities embedded in the system and
behavioural responses from portfolio managers.

1. Introduction factors (e.g. market development, technological tur-


bulence, and resource deficiencies) prevail generat-
In the multi-project context, most organisations
ing disruptions on projects (Petit, 2012; Voss &
undertake project portfolio management (PPM) to
Kock, 2013), their portfolio-level impacts vary
improve the project investment efficiency and realise
because the existence of complex project interdepen-
value (PMI, 2017). As portfolios are intrinsically
dencies (PIs). On the one hand, synergies that add
dynamic and exposed to the ever-changing environ-
benefits to the portfolio arise from the sharing of
ment, uncertainties regarding projects, inter-project
resources and knowledge between projects (Daniel
issues, and organisational changes induce disrup-
& Daniel, 2018). On the other hand, projects com-
tions and even failures on the achievement of goals
pete for scarce resources to improve their invest-
for projects portfolios (Petit & Hobbs, 2010). While ment in order to achieve the project’s objectives
project control activities have been widely applied (Chao & Kavadias, 2008). These PIs form multiple
for decades, however, limited evidence shows how feedback mechanisms so deviations in one project
to resolve issues originated at the portfolio level can be compensated or diffused, affecting the rest of
continuously (Petit, 2012). Empirical research indi- the portfolio (Williams, Ackermann, & Eden, 2003).
cates that only half of the organisations using PPM Likewise, as project and portfolio managers are
regularly track the portfolio benefits (De Reyck responsible for the implementation process, includ-
et al., 2005; KPMG, 2017). Even if the benefits are ing reporting projects’ deviations and evaluating dif-
evaluated, managers seem not to perform well in ferent remedial action proposals, the heuristics and
coordinating project portfolios (Sobtsenko & behavioural biases can affect their decisions depart-
Tararyko, 2009) because they often lack a broad ing from a rational and optimal management of the
overview of the multiple projects and their manager- project (Martinsuo, 2013).
ial decisions (e.g. resource re-allocation and project Therefore, the projects’ dynamics, their complex
re-prioritisation) are made in an isolated way and interdependencies, and the interplay between behav-
fail to improve the portfolio performance (Blichfeldt ioural choices underpin the portfolio implementa-
and Eskerod, 2008). As such, a strategic portfolio tion system and, consequently, a separate analysis of
implementation model to facilitate systemic deci- each aspect may lose the strategic perspective to
sion-making is in urgent need for portfolio success achieve the goals for the project portfolio (Lechler &
(Kopmann, Kock, Killen, & Gemunden, 2015). Thomas, 2015). System dynamics modelling is a
Portfolio implementation is more challenging suitable method for its advantages in visualising
than scaling-up the implementation of individual portfolio structure and behaviours, observing the
projects (Repenning, 2000). As internal and external consequences of external events and rehearsing the

CONTACT Martin Kunc M.H.Kunc@soton.ac.uk Southampton Business School, University of Southampton, Southampton SO17 1BJ, UK
ß Operational Research Society 2019
2 L. WANG ET AL.

Figure 1. Hierarchical framework of portfolio implementation (adapted from Loch and Kavadias (2002), Schultz et al. (1987),
and Wang et al. (2017)).

managerial actions taken to mitigate the deviations. Section 2 illustrates the theoretical background,
It does not replace portfolio optimisation models or with discussions of the research framework and
project control techniques discussed in other oper- complexities in the portfolio implementation pro-
ational research literature but it complements them cess. In Section 3, a system dynamics model is con-
by transparently formulating the complex portfolio structed and the variables involved are explained.
implementation system from the strategic and Section 4 presents the experimental results, describ-
behavioural perspectives (Rodrigues & Bowers, ing the interactive effects of uncertainties and pro-
1996a; Rodrigues, 2000). Moreover, research has ject interdependencies, the selection of remedial
already introduced system dynamics to project man- actions, and the influences of behavioural responses,
agement (e.g. Eden, Williams, Ackermann, & followed by the discussions in Section 5 and conclu-
Howick, 2000; Wang, Kunc, & Bai, 2017; Williams, sions in Section 6.
Eden, Ackermann, & Tait, 1995) but few models
related to the management of project portfolios have
been constructed (Repenning, 2000).
In the subsequent sections, a system dynamics 2. Theoretical background
model (Sterman, 2000) is proposed to integrate the 2.1. Hierarchical framework for portfolio
interactive effects of uncertainties and complexities implementation
and to identify the adequate responses of portfolio
managers to these effects. With the goal to maxi- For a better understanding of the system, we firstly
mise the overall portfolio benefits (Serra & Kunc, present a portfolio implementation framework (see
2015), this research looks beyond the “hard” and Figure 1). Portfolio managers are responsible for
isolated project operational data and focuses on a transforming the portfolio strategy into multiple
wide scope of complexities regarding project inter- goals for different projects and allocate the resources
dependencies and behavioural biases. It not only accordingly so the value generated by each project
contributes to the PPM practice by providing a deci- can support the realisation of the benefits at port-
sion support system for strategic portfolio imple- folio-level (Chiang & Nunez, 2013). However, the
mentation but also offers a novel application of existence of uncertainties and disruptions implies
behavioural OR in project management by model- the need for monitoring & control processes (follow
ling behaviours in a multi-project context. the bold lines).
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY 3

For example, we take Project A to illustrate the 2.2. Uncertainties and the portfolio
relevant project-level activities and project–portfolio implementation process
interactions.
Uncertainties are emphasised in project portfolio stud-
The project level concentrates on operational
ies to represent the changes and developments whose
activities to meet the project goals (Wang et al.,
outcomes and probabilities are not known (Korhonen,
2017). When uncertainties unfold and induce a
Laine, & Martinsuo, 2014). The sources of portfolio
deviation between the project performance (realised
uncertainties have been traced back to individual proj-
value) and its strategic goals (expected value), the
ects (Olsson, 2008; Petit & Hobbs, 2010), organisa-
deviation is monitored and reported to portfolio
tional complexity (Engwall & Jerbrant, 2003; Petit,
managers periodically, and decisions are made to
2012), and business environment (Voss & Kock, 2013;
define the degree of remedial actions (i.e. adjust- Petit, 2012). Please see Martinsuo, Korhonen, and
ment of investment) required to mitigate Laine (2014) for a systematic review. Some research
the deviation. suggest managing or mitigating uncertainties through
The portfolio level identifies the synergetic effects responsive actions that can continually monitor and
among projects and makes/adjusts funding decisions capture the dynamic information (Pedersen &
to maximise the overall benefits. Portfolio managers Nielsen, 2011). Petit (2012) applies a dynamic capabil-
often make outcome-based decisions using oper- ities framework to portfolio implementation and sug-
ational information (Aritua, Smith, & Bower, 2009): gests using sense-making to grasp the impacts of
they are informed about the project performance uncertainties and adjust the portfolio accordingly.
deviation (step 1), make decisions on how to re- Korhonen et al. (2014) argue that, by providing infor-
allocate investments (step 2), and then take remedial mation about the uncertain situations, management
actions to adjust the project performance (step 3). A control systems can help to appease uncertainties but
critical issue at this level is the impact of project the integration of individual project changes to the
interdependencies since changes in one project can portfolio level has not been well-studied.
affect the performance of others. This research concentrates on how project uncer-
This template is suitable for most organisations tainties affect the portfolio behaviour in the imple-
according to our discussions with experienced mentation system. Disruptions & delays (DD),
PMOs. Nevertheless, since we have the ambition to proposed by a collection of project litigation papers
provide a general framework that can be easily (Howick, 2003; Howick & Eden, 2001; Williams et al.,
adapted to different portfolio contexts; we ignore 2003), is the concept employed to indicate the tactical
interventions that can alter the characteristics of the impact of uncertainties on project implementation:
system. For example, we focused on the uncertain- cost and schedule overruns, missed opportunities,
ties at project level that can be solved by adjusting and reduced performances (Howick & Eden, 2004;
resources and not re-organising the overall portfolio. Wang et al., 2017). When faced with DD, increasing
Additionally, we set the remedial actions as different the available resources to remove delays is one of the
investment policies, for example, more budget, yet key remedial actions in conventional project manage-
in reality these actions can also involve the changes ment practices (Lyneis & Ford, 2007).
regarding staff, technology, materials, etc., which The portfolio-level resolutions to cope with DD
may cause side-effects, such as increases in product- mainly focus on priority setting and resource re-alloca-
ivity but also further disruptions (Howick, 2003). tion. Literature suggests that the portfolio decision-mak-
Another potential change in the characteristics is ers have the flexibility to “improve” or “abandon”
the impact of the organisations’ culture and rules on projects (Loch & Kavadias, 2002). In most circumstan-
the flows of information between hierarchies. ces, requests for additional funds and scope change are
Finally, in some situations, the value generated by frequently made from project managers to portfolio
projects is also reinvested to the portfolio generating managers (Petit, 2012). Engwall and Jerbrant (2003)
a change in the available resources (Petit, 2012; describe that, in practice, the investment is normally re-
Jafarzadeh, Tareghian, Rahbarnia, & Ghanbari, distributed from low-prioritised, or smoothly going,
2015). These simplifications have two implications. projects to high-prioritised projects or projects in urgent
On the one hand, they can help to concentrate on need of funds. However, few analytical tools can help to
the main problems such as observing the portfolio verify the reasonability and validity of these decisions.
behaviour and defining the adequate managerial
decisions. On the other hand, they reduce the com-
2.3. Project interdependencies at the
plexity existing in real cases and their idiosyn-
portfolio level
cratic issues.
The dynamism and complexities involved are dis- PIs originate from technological leverage, knowledge
cussed subsequently to clarify the research scope. sharing, and market dependencies (Verma & Sinha,
4 L. WANG ET AL.

2002). The importance of PIs in portfolio decision- planning fallacy and “Pet project” effects (Beringer,
making has been highlighted by a number of Jonas, & Kock, 2013; Loch, 2000).
researchers, for example, Aritua et al. (2009). Planning fallacy (PF) demonstrates that managers
Sanchez (2017) emphasises that portfolios, as com- forecast the outcomes based on delusional optimism,
plex adaptive systems, cannot be fully known with- which may induce overestimation of benefits, and
out understanding the interdependencies. From the underestimation of costs, demand, risks, etc.
strategic point of view, this research considers two (Kahneman & Tversky, 1979). Flyvbjerg (2008)
typical typologies of PIs: resource competition (RC) argues that on average, the underestimation of costs
and synergetic effects (SE) (Repenning, 2000). in transportation infrastructure projects was found
Normally RC can constrain the generation of value 44.7% for rail, 33.8% for bridges and tunnels, and
during the implementation of multiple projects 20.4% for roads, and one of the main psychological
while SE increases the value realised in portfolios. explanations for this inaccuracy is planning fallacy.
Resource competition (RC): Projects often share a As the total budget serves as a key variable to deter-
common resource pool, for example, specialised mine the portfolio implementation behaviour, the
technical staff, in the portfolio (Loch & Kavadias, direct impact of PF on its estimation, that is, a
2002). As the resources in an organisation are often shortage of the overall available budget, is one of
scarce, for example, 73% of organisations report the key elements of our study.
lacking enough resource capacity for supporting ‘Pet project’ effects (PE) refer to the fact that port-
projects (Planview, 2017), the implementation of folio managers hold on to their personally preferred
one project may take resources away from other projects regardless of the execution performances
projects if they share similar resources, for example, (Beringer et al., 2013). Blichfeldt and Eskerod (2008)
resource dependency (Verma & Sinha, 2002). suggest that PE influence the resource allocation
Empirical studies demonstrate that competition on system and have detrimental impacts on portfolios.
priorities, resources and personnel are “continuous As priorities are often set to individual projects
negations … on … the access to available based on their estimations, there may be a need for
resources” (Engwall & Jerbrant, 2003). changing priorities during the implementation of a
Synergetic effects (SE): The synergetic effects arise project portfolio (Childs & Triantis, 1999).
when the performance of one project relates to Nevertheless, due to personal interests or social–po-
others (Repenning, 2000). When two projects com- litical issues, the advocacy of project managers for
plement each other, their implementation can lead their “pet projects” can restrict the adjustments on
to a positive synergy that adds additional benefits investment and priorities or reduce the adjustments
beyond the sum of the individual benefits. On the so they become insufficient (Beringer et al., 2013).
contrary, having two projects with significant func-
tional overlap may lead to costs that surpass the
3. System dynamics model development
combined benefit. This paper focuses on a posi-
tive synergy. Following the theoretical framework, a stylised
model of a two-project portfolio is constructed on
the basis of well-established system dynamics mod-
2.4. Behavioural factors in portfolio
els related with project management such as Ford,
implementation
Lyneis, and Taylor (2007), Son and Rojas (2011),
The study of behavioural aspects in project manage- and Wang et al. (2017). Different from case-based
ment emerges from the discussion on project escal- models, stylised models can offer the possibility of
ation issues, that is, the tendency to continue experimenting with multiple situations, which helps
investing in the failing projects (Pala, Vriens, & to formulate generalizable structures rather than
Vennix, 2015; Pan & Pan, 2011). Several cognitive focusing on regularities of a specific case (Brenner
limitations have been proposed to explain its occur- & Werker, 2007; Kunc & Morecroft, 2007). While
rence, such as self-justification theory, prospect the- the two projects can represent the basic behaviour
ory, and sunk-cost effects (Keil, Mann, & Rai, of a portfolio, this model can be extended to mul-
2000). Extending the research scope from projects tiple projects by connecting multiple projects
to portfolios, heuristics and biases of portfolio man- through key interdependencies and formulating
agers can also occur when they decide upon remed- operating policies that allocate the resources to
ial actions for multiple competing projects. each project.
Concerning the impact of heuristics and biases on In real cases, the portfolio implementation system
portfolio level decisions before and during the may overlap with a series of decision-making proc-
implementation stage, this paper investigates the esses or other project portfolio systems within the
impacts of two common behavioural factors: business, which increase the degree of uncertainty
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY 5

Figure 2. The system dynamics model of portfolio implementation.

and complexity (Cooper, Edgett, & Kleinschmidt, loops B1 and B2 dominate each sub-system, respect-
1997). Thus, more constraints and assumptions ively: If remedial actions are taken to increase the
should be considered and the system and variables project’s investment priority, its realised value will
involved require further adjustment. For instance, increase, which mitigates the deviation and then
the value creation index (VCI) is assumed as an decreases the corresponding investment priority
external variable in our model, nevertheless, it can (Lyneis & Ford, 2007; Schultz, Slevin, & Pinto,
be influenced by remedial actions causing further 1987). Synergetic effects (SE) connect the two proj-
DD (Howick, 2003); or, sometimes, remedial actions ects through a reinforcing feedback loop R3 (follow
can improve VCI forming different feedback loops, the bold lines). When SE increase, the value creation
for example, higher VCI reduces the need to invest of Project A increases, which in turn decreases its
more resources as the efficiency of the project is deviation from the expected value and, thus, the
higher. Moreover, the VCI function can also change investment rate of Project A declines. Since the total
due to the environment turbulence (Loch & budget is limited, resources for Project B increase
Kavadias, 2002). The stock and flow diagram for correspondingly at the expense of resources for
our stylised model is presented in Figure 2. Project A (Loch & Kavadias, 2002). Another situ-
As shown in Figure 2, two self-organised project ation that may occur is the organisation reserves the
sub-systems (Project A and Project B) are coordi- budget for one specific project, then no resource
nated by a centralised investment adjustment pro- competition exists in the portfolio. This situation is
cess (Aritua et al., 2009). The balanced feedback explored with the “pet project” effect in Section 4.3.
6 L. WANG ET AL.

The total value creation, that is, the value of


Project A and B together, involves the impact of all
three feedback loops so it is difficult to estimate
intuitively (Sterman, 2000). To isolate the impacts of
uncertainties, interdependencies and behavioural
factors, the two projects are set of the same size and
contribute to the same strategic goal, of which
Project A is the control project free from uncertain-
ties and project B is assumed to be initially pre-
ferred, for example, the “pet project”, but suffering
from DD. The variables for the project sub-system
and portfolio-level links will be described in the fol-
Figure 3. The interactive effects of DD and SE.
lowing section and the corresponding equations are
presented in the Appendix.
system dynamics models in project management
(Rodrigues & Bowers, 1996b).
3.1. Project implementation sub-system
We take Project A (feedback loop B1) as an example 4. Experimental results
since the two projects share the same structure.
We investigate how portfolio managers should react to
When implementing projects, an expectation for the
uncertainties with the consideration of interdependen-
project development in each period, DEVðAÞ; is set
cies and behavioural factors using system dynamics
and accumulates into the expected value EVðAÞ: As
modelling software Vensim DSS. The time horizon for
uncertainties cause DDðAÞ and in turn reduce the
the implementation of the two projects is 100 months
work progression WPðAÞ; the value yield for the
and it is similar for both projects that run in parallel. A
project RVðAÞ cannot match EVðAÞ; thus it creates
comprehensive set of plausible parameters have been
the deviation DðAÞ: The requests for additional tested to present the results of the model and extreme
investment are reported to the portfolio manager, conditions have been tested. Moreover, the experimen-
who will adjust the investment priority IPðAÞ; that tal results are presented comparing with an equilib-
is, an index determining the investment of projects, rium situation where the portfolio is exempt from any
and improve the investment CðAÞ: The value cre- uncertainty or complexity.
ation productivity of the investment is denoted by
value creation index (VCI).
4.1. The interactive effects of DD and SE

3.2. Portfolio-level links This section firstly explores how DD and SE influence
the portfolio value creation without specific manager-
The portfolio is constrained by total budget (TB)and ial interventions. The interactive effects of DDðBÞ and
the goal is to maximise the overall strategic benefits SE are investigated by Monte Carlo simulations using
TVC. The implementation of Project B facilitates a range of values (SI in [0.5%, 1.5%], and DDðBÞ in
the value creation of Project A through SE, for [0, 1]). In Figure 3, x-axis represents the value of SI,
example, two marketing projects where one project y-axis represents the DDðBÞ level, and z-axis repre-
creates a brand (Project B) and another project is sents the deviation of TVC with respect to the equilib-
for the advertising campaign (Project A), so the rium (in percentage). A positive value at z-axis
brand effects created by Project B improves the denotes an increase of the portfolio value, and vice
value creation efficiency of Project A, and if the versa. We can see that with constrained resources, the
investment in Project B expands, the synergetic increase of SE generally generates an uptrend of TVC
effects on project A will be more obvious. The rise while a higher level of uncertainties may decrease the
of DRVðAÞ decreases its deviation and, thus, the value. Their interactive effects, however, makes the
investment rate of Project A declines. The portfolio landscape complex and difficult to estimate.
manager takes remedial actions (RA) to adjust the
investment priorities. In our experiments, if only
DDðBÞ occurs and induces DðBÞ; we will test if the 4.2. Managerial interventions and the influences
main RA is to decide whether or not to increase of project interdependencies
IPðBÞ:In other words, our model focuses on the 4.2.1. Remedial actions for portfolio implementation
interrelationships that are responsible for overrun When the projects underperform, adding additional
and overspend, which are the critical advantage of investment to the troubled projects is the common
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY 7

Table 2. The influence of SI on RA decision-making.


SI level \ DD(B) DD(B) mean  0:3 DD(B)mean ¼ 0:4 DD(B)mean ¼ 0:5 DD(B)mean ¼ 0:6 DD(B)mean  0:7
No SI NRA NRA NRA NRA NRA
SI RA SI  0:58%; NRA SI  0:88%; NRA SI  1:32%; NRA NRA
SI  0:58%; RA SI  0:88%; RA SI  1:32%; RA
NRA denotes “no remedial actions”, and RA denotes “taking remedial actions.”
The values used have been tested using sensitivity analysis.

policy to bring them “back on track.” Literature sug- created and cost of investment resulting from both
gests that project managers use a basic heuristic of the value creation process and synergetic effects, for
taking remedial actions in proportion with the project example, at the time t; the SROI of Project B can be
deviation (Lyneis & Ford, 2007; Wang et al., 2017). In calculated by the functionSROIt ðBÞ ¼ ðDRVt ðBÞ þ
response to the request for additional investment SEt Þ=Ct ðBÞ: After the impact of DDðBÞ; the value
from project B, the portfolio managers have two created by per unit investment of Project B
choices to prevent the portfolio from failing: (DRVt ðBÞ=Ct ðBÞ) is lower than that of Project A,
No remedial actions (NRA). No remedial actions thus the flow of investment to Project B actually
are taken. reduces the value creation efficiency. Meanwhile, SE
Taking remedial actions (RA). Remedial actions can compensate the losses and increase SROIt ðBÞ:
are taken for project B. As SROIt is a real-time variable determined by both
If resources are sufficient, remedial actions can the project’s realised benefits and non-linear syner-
increase the portfolio benefits by improving the getic benefits, tracking its exact value means model-
each individual project’s benefits. However, resour- ling the projects in much detail, which is outside
ces are always limited (Engwall & Jerbrant, 2003), the scope of this paper. Our proposed system
thus improving one project’s use of resources, or dynamics model can integrate the effects of SROI
investments, will reduce the available investment for and present the overall portfolio value from the stra-
the others if the resources are specifically parti- tegic perspective, which facilitates the policies driv-
tioned. In other words, resource competition can ing remedial actions.
easily occur between Project A and Project B so we
experiment with a wide range of data in order to 4.3. Influences of behavioural factors on
investigate how SE affects the decisions. portfolio implementation
We run experiments with the model to investigate
4.2.2. Influences of SE on remedial action deci-
how behavioural factors in remedial actions affect
sion-making
the portfolio implementation results with different
DDðBÞ is set as normal distribution following the pre-
combinations of DDðBÞ and SI levels (the value of
vious literature, for example, Son and Rojas (2011)
each level is presented in the Appendix). Since TB
and Wang et al. (2017). Under certain DDðBÞ; the
is often underestimated, a behavioural bias called
decision on remedial actions varies according to dif-
planning fallacy, it induces competition for resour-
ferent SI levels. Comparing the portfolio value with
ces and further triggering fights for setting the pri-
and without RA, Table 2 shows that doing nothing orities of projects, another bias called “pet project”
would be a good choice without synergetic effects but effect. As the two behavioural biases are interwoven,
the situation is different when SI exceeds a certain their impacts are discussed together.
level. For example, when DDðBÞ affects the advance When a project underperforms, except for business-
of the project significantly, for example, a variation of as-usual (NRA) and taking remedial actions (RA),
50%, and SI is high, the value creation for Project A switching the implementation priorities (SP) is the
increases substantially, the total value for the project usual choice (Childs & Triantis, 1999). In our experi-
portfolio generated by adding investment to Project B ment, SP means periodically allocating investment to
is profitable. The existence of SE alters portfolio guarantee the success of Project A. The previous
implementation decisions. Section 4.2 has already embodied the effects of plan-
The above results demonstrate that the traditional ning fallacy and “pet project” effect: the lack of add-
project control logic is not fit for portfolio imple- itional investment is induced by the underestimation
mentation as it moves resources towards “troubled” of risks, and the business-as-usual policy allows for suf-
projects, instead of the strategically important ones. ficient investment to Project A. We also set other
We suggest the relative strategic importance, experiments: TB is only 70% and 50% with respect to
dynamically evaluated by strategic return on invest- the equilibrium level. Table 3 shows the deviation gap
ment (SROI), should be taken into consideration as between RA and SP with respect to the equilibrium (in
a driver of the operating policy to adjust resources. percentage) to demonstrate the impacts of “pet proj-
We define SROI as the ratio between the net value ect” effect. We can see that briefly more severe
8 L. WANG ET AL.

Table 3. The deviation gap between RA and SP (% with portfolio implementation process: resource competi-
regard to equilibrium). tion and synergetic effects. The results demonstrate
SI \ TB DD(B) TB ¼ 100% TB ¼ 70% TB ¼ 50% that considering the constraint of resource competi-
High, High 2.01% 6.21% 10.39%
High, Medium 3.85% 9.39% 14.08%
tion and uncertainties in the environment, syner-
High, Low 5.70% 12.57% 17.77% getic effects may make the portfolio behaviour
Medium, High 2.62% 3.85% 2.57% complex to estimate (Figure 3) and alter the deci-
Medium, Medium 0.54% 0.79% 3.13%
Medium, Low 1.56% 5.44% 8.83% sions on portfolio remedial actions (Table 2). As the
Low, High 3.95% 11.58% 14.01% previous literature indicates the dynamism and com-
Low, Medium 2.22% 5.91% 6.58%
Low, Low 0.51% 0.23% 0.85% plexities surrounding portfolio implementation are
far from being well-understood, and once the port-
planning fallacy bias induces higher deviation gap. The folio is constructed, project interdependencies are
losses can be almost 20% from the benchmark (e.g. in always put aside other than discussed in adjusting
the 3rd experiment when TB ¼ 50%). In some occa- the resources for multiple on-going projects (Killen,
sions, changing the priority is not reasonable, for 2013), our experiments demonstrate the significant
example, in the 4th, 6th, and 7th experiment, because role of project interdependencies in portfolio imple-
switching priority induces more losses. mentation. Moreover, our system dynamics model
also provides an analytical tool for managers to
understand and model various project interdepen-
5. Discussion dencies on an ongoing basis.
5.1. From “project control” to “portfolio
coordination”: the strategic perspective matters 5.3. Project portfolio management should
Adding additional investment to underperforming concentrate more on human factors
projects is a common practice to bring them “back on The simulation study shows the losses caused by
track” (Lyneis & Ford, 2007). However, when we simu- planning fallacy and pet project effects, which high-
late this process, counterintuitively, remedial actions light the importance of contemplating the behav-
may even induce more losses (see Table 2). The reason ioural aspects involved in the portfolio
lies that the value generated by the “troubled” project implementation process. Some mitigation actions to
is not as much as that yield by the other projects in the reduce these behavioural biases, based on authors’
portfolio. This result shows the erroneous belief in experiences, are to separate the responsibilities for
most PPM practice and literature that the portfolio project execution and portfolio governance and
goals cannot be fully satisfied by individual project bring in third-party consultants to initiate and
management but requires a strategic perspective monitor the portfolio. Further discussions regarding
(Rodrigues & Bower, 1996a, b; Engwall & Jerbrant, the rewards and penalty policies and the construc-
2003; Serra & Kunc, 2015). Although a multitude of tion of a transparent and collaborative team culture
instructions have been made on how to strategically (Pederson & Nielson, 2011) that can influence the
select and allocate resources to initiatives (Chiang & stakeholders’ behaviours are important. Some of
Nunez, 2013; Jafarzadeh et al., 2015; Chao & Kavadias, these policies can be tested by modifying this model
2008), our research, as far as we know, is one of the such as the impacts of reward criteria on portfolio
pioneering works to support strategic portfolio imple- implementation can be formulated and tested.
mentation by providing an overview of the portfolio Furthermore, the results provided by models similar
behaviour. Moreover, we further define the portfolio to our model can reduce deviations generated by
coordination logic as re-allocating resources to the inconsistent decision-making processes as the conse-
relatively important projects other than the “troubled” quences of different remedial actions can be directly
ones. The strategic return on investment (SROI) index compared. Although this paper just focuses on the
is proposed to present the complexities of calculating portfolio-level behaviours, the impacts of project
the projects’ contributions, thus a systemic model is managers’ behavioural biases can also be studied
highlighted for portfolio coordination to improve the through the use of simulation, which may reduce
overall strategic benefits. the escalation of commitment by providing a broad
view of the overall portfolio (Pala et al., 2015).
5.2. Incorporating project interdependencies
at the implementation stage is vital for 6. Conclusion
portfolio success
Considering the uncertainties and complexities in
Our preceding experiments investigate two typical the portfolio implementation process, a system
project interdependencies occurring during the dynamics model is proposed to illustrate how
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY 9

portfolio managers make resource adjustment deci- and its impact on success. International Journal of
sions from a strategic and behavioural perspective. Project Management, 31(6), 830–846. doi:10.1016/
j.ijproman.2012.11.006
The contribution of our work is threefold: From the
Blichfeldt, B. S., & Eskerod, P. (2008). Project portfolio
managerial side, this research provides a first step management – There’s more to it than what manage-
towards constructing an integrated decision support ment enacts. International Journal of Project
system for portfolio coordination, which improves Management, 26(4), 357–365. doi:10.1016/
PPM practice by transparently demonstrating how j.ijproman.2007.06.004
Brenner, T., & Werker, C. (2007). A taxonomy of infer-
projects are connected in a portfolio, comparing
ence in simulation models. Computational Economics,
possible alternatives and providing reasonable evi- 30(3), 227–244. doi:10.1007/s10614-007-9102-6
dence for coordinating multiple projects. Moreover, Chao, R. O., & Kavadias, S. S. (2008). A theoretical
it complements the PPM theory by emphasising the framework for managing the new product development
strategic perspective of portfolio implementation, portfolio: When and how to use strategic buckets.
Management Science, 54(5), 907–921.
the importance of project interdependencies and the
Chiang, I. R., & Nunez, M. A. (2013). Strategic alignment
impacts of “pet project” effects using experimental and value maximization for IT project portfolios.
results. Last but not least, the introduction of SD Information Technology and Management, 14(2),
into portfolio implementation also implies new 143–157. doi:10.1007/s10799-012-0126-9
opportunities for applying behavioural OR to facili- Childs, P. D., & Triantis, A. J. (1999). Dynamic R&D
investment policies. Management Science, 45(10),
tate problem-solving in multiple projects.
1359–1377.
As discussed in Sections 2 and 3, since this Cooper, R. G., Edgett, S. J., & Kleinschmidt, E. J. (1997).
research mainly highlights the model’s generalizabil- Portfolio management in new product development:
ity, the details of specific cases are omitted. Further Lessons from the leaders—I. Research-Technology
research will investigate the applications to empirical Management, 40(5), 16–28.
Daniel, P. A., & Daniel, C. (2018). Complexity, uncer-
studies in specific contexts to adapt the model to
tainty and mental models: From a paradigm of regula-
contextual issues, for example running projects tion to a paradigm of emergence in project
sequentially or with some overlaps over time instead management. International Journal of Project
of parallel. Furthermore, this paper just investigates Management, 36(1), 184–197. doi:10.1016/
the behavioural biases arising at the portfolio-level j.ijproman.2017.07.004
De Reyck, B., Grushka-Cockayne, Y., Lockett, M.,
in a simplified way (e.g. the planning fallacy is mod-
Calderini, S. R., Moura, M., & Sloper, A. (2005). The
elled as the underestimation of the total budget, yet impact of project portfolio management on informa-
more implications regarding the benefits and risks tion technology projects. International Journal of
can also be considered). More efforts can be done Project Management, 23(7), 524–537. doi:10.1016/
to study a wide scope of behaviours and the further j.ijproman.2005.02.003
Eden, C., Williams, T., Ackermann, F., & Howick, S.
involved organisational restrictions (e.g. prizes, pen- (2000). The role of feedback dynamics in disruption
alties, collaborations) applying the behavioural and delay on the nature of disruption and delay
OR methods. (D&D) in major projects. Journal of the Operational
Research Society, 51(6), 774.
Engwall, M., & Jerbrant, A. (2003). The resource alloca-
Disclosure statement tion syndrome: The prime challenge of multi-project
management? International Journal of Project
No potential conflict of interest was reported by
Management, 21(6), 403–409.
the authors.
Flyvbjerg, B. (2008). Curbing optimism bias and strategic
misrepresentation in planning: Reference class forecast-
Funding ing in practice. European Planning Studies, 16(1), 3–21.
doi:10.1080/09654310701747936
National Natural Science Foundation of China (Grant ID Ford, D. N., Lyneis, J. M., & Taylor, T. R. (2007). Project
71425002). controls to minimize cost and schedule overruns: A
model, research agenda, and initial results. 2007
International System Dynamics Conference (pp.
ORCID 23–27).
Jianping Li http://orcid.org/0000-0003-4976-4119 Howick, S. (2003). Using system dynamics to analyse dis-
ruption and delay in complex projects for litigation:
Can the modelling purposes be met? Journal of
Reference Operational Research Society, 54(3), 222–229. doi:
10.1057/palgrave.jors.2601502
Aritua, B., Smith, N. J., & Bower, D. (2009). Construction Howick, S., & Eden, C. (2001). The impact of disruption
client multi-projects – A complex adaptive systems per- and delay when compressing large projects: Going for
spective. International Journal of Project Management, incentives? Journal of the Operational Research Society,
27(1), 72–79. doi:10.1016/j.ijproman.2008.02.005 52(1), 26–34.
Beringer, C., Jonas, D., & Kock, A. (2013). Behavior of Howick, S., & Eden, C. (2004). On the nature of disconti-
internal stakeholders in project portfolio management nuities in system dynamics modelling of disrupted
10 L. WANG ET AL.

projects. Journal of the Operational Research Society, the Operational Research Society, 66(4), 593–601. doi:
55(6), 598–605. 10.1057/jors.2014.24
Jafarzadeh, M., Tareghian, H. R., Rahbarnia, F., & Pan, G., & Pan, S. L. (2011). Transition to IS project de-
Ghanbari, R. (2015). Optimal selection of project port- escalation: An exploration into management executives
folios using reinvestment strategy within a flexible time influence behaviors. IEEE Transactions on Engineering
horizon. European Journal of Operational Research, Management, 58(1), 109–123. doi:10.1109/
243(2), 658–664. doi:10.1016/j.ejor.2014.12.013 TEM.2010.2048908
Kahneman, D., & Tversky, A. (1979). Prospect Theory: Pedersen, K., & Nielsen, J. A. (2011). Managing uncer-
An Analysis of Decision under Risk. Econometrica, tainty and conflict in IT project portfolio management.
47(2), 263–291. doi:10.2307/1914185 Journal of Information Technology Case and Application
Keil, M., Mann, J., & Rai, A. (2000). Why software proj- Research, 13(4), 51–83. doi:10.1080/
ects escalate: An empirical analysis and test of four the- 15228053.2011.10856217
oretical models. MIS Quarterly, 24(4), 631–664. doi: Petit, Y. (2012). Project portfolios in dynamic environ-
10.2307/3250950 ments: Organizing for uncertainty. International
Killen, C. (2013). Visualizations of project interdependen- Journal of Project Management, 30(5), 539–553. doi:
cies for porftolio decision making: Evaluation through 10.1016/j.ijproman.2011.11.007
decision experiments. In Decision Sciences Institute Petit, Y., & Hobbs, B. (2010). Project portfolio in dynamic
Annual Meeting. environments: Sources of uncertainty and sensing
Kopmann, J., Kock, A., Killen, C. P., & Gemunden, H. G. mechanisms. Project Management Journal, 41(4),
(2015). Business case control in project portfolios – An 46–58. doi:10.1002/pmj.20201
empirical investigation of performance consequences Planview (2017). The project and portfolio management land-
and moderating effects. IEEE Transactions on scape. Retrieved from https://info.planview.com/rs/456-
Engineering Management, 62(4), 529–543. doi:10.1109/ QCH-520/images/2Planview_Landscape_Report_2017.pdf.
TEM.2015.2454437 PMI. (2017). Pulse of the profession. Retrieved January 28,
Korhonen, T., Laine, T., & Martinsuo, M. (2014). 2019, from PMI database.
Management control of project portfolio uncertainty: A Repenning, N. P. (2000). A dynamic model of resource
managerial role perspective. Project Management allocation in multi-project research and development
Journal, 45(1), 21–37. doi:10.1002/pmj.21390 systems. System Dynamics Review, 16, 173–212.
KPMG. (2017). Driving business performance: Project Rodrigues, A. G. (2000). The application of system
dynamics to project management: An integrated meth-
management survey 2017.
odology (Doctoral Dissertation). University of
Kunc, M., & Morecroft, J. (2007). System dynamics model-
Strathclyde, Glasgow.
ling for strategic development. Supporting strategy:
Rodrigues, A., & Bowers, J. (1996a). The role of system
Frameworks, methods and models. Chichester: Wiley.
dynamics in project management. International Journal
Lechler, T. G., & Thomas, J. L. (2015). Examining new
of Project Management, 14(4), 213–220. doi:10.1016/
product development project termination decision
0263-7863(95)00075-5
quality at the portfolio level: Consequences of dysfunc-
Rodrigues, A., & Bowers, J. (1996b). System dynamics in
tional executive advocacy. International Journal of
project management: A comparative analysis with trad-
Project Management, 33(7), 1452–1463. doi:10.1016/ itional methods. System Dynamics Review, 12(2),
j.ijproman.2015.04.001 121–139. doi:10.1002/(SICI)1099-1727(199622)12:
Loch, C. H. (2000). Tailoring product development to 2<121::AID-SDR99>3.3.CO;2-O
strategy: Case of a European technology manufacturer. Sanchez, H. (2017). A matrix for monitoring the strategic
European Management Journal, 18(3), 246–258. doi: performance of project portfolios. International Journal
10.1016/S0263-2373(00)00007-4 of Project Organisation and Management, 2(2),
Loch, C. H., & Kavadias, S. (2002). Dynamic portfolio 135–153. doi:10.1504/IJPOM.2010.033659
selection of NPD programs using marginal returns. Schultz, R., Slevin, D., & Pinto, J. (1987). Strategy and
Management Science, 48(10), 1227–1241. tactics in a process model of project implementation.
Lyneis, J. M., & Ford, D. N. (2007). System dynamics Interfaces, 17(3), 34–46. doi:10.1287/inte.17.3.34
applied to project management: A survey, assessment, Serra, C. E. M., & Kunc, M. (2015). Benefits realisation
and directions for future research. System Dynamics management and its influence on project success and
Review, 23(2–3), 157–189. doi:10.1002/sdr.377 on the execution of business strategies. International
Martinsuo, M. (2013). Project portfolio management in Journal of Project Management, 33(1), 53–66.
practice and in context. International Journal of Project Sobtsenko, O., & Tararyko, J. (2009). Control, review and
Management, 31(6), 794–803. doi:10.1016/ monitoring of a project portfolio: The study of projects
j.ijproman.2012.10.013 in the implementation phase (Bachelor Thesis).
Martinsuo, M., Korhonen, T., & Laine, T. (2014). J€onk€
oping International Business School, J€ onk€oping.
Identifying, framing and managing uncertainties in Son, J., & Rojas, E. M. (2011). Impact of optimism bias
project portfolios. International Journal of Project regarding organizational dynamics on project planning
Management, 32(5), 732–746. doi:10.1016/ and control. Journal of Construction Engineering and
j.ijproman.2014.01.014 Management, 137(2), 147–157. doi:10.1061/
Olsson, N. O. (2008). External and internal flexibility–a- (ASCE)CO.1943-7862.0000260
ligning projects with the business strategy and execut- Sterman, J. (2000). Business dynamics: Modelling for a
ing projects efficiently. International Journal of Project complex world. USA: Mc-Graw Hill.
Organisation and Management, 1(1), 47–64. doi: Verma, D., & Sinha, K. K. (2002). Toward a theory of
10.1504/IJPOM.2008.020028 project interdependencies in high tech R&D environ-
€ Vriens, D. J., & Vennix, J. A. M. (2015). Causal
Pala, O., ments. Journal of Operations Management, 20(5),
loop diagrams as a de-escalation technique. Journal of 451–468.
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY 11

Voss, M., & Kock, A. (2013). Impact of relationship value application of cause-mapping and system dynamics.
on project portfolio success – Investigating the moder- European Journal of Operational Research, 148(1),
ating effects of portfolio characteristics and external 192–204.
turbulence. International Journal of Project Williams, T., Eden, C., Ackermann, F., & Tait, A. (1995).
Management, 31(6), 847–861. doi:10.1016/ The effects of design changes and delays on project
j.ijproman.2012.11.005 costs. The Journal of the Operational Research Society,
Wang, L., Kunc, M., & Bai, S. J. (2017). Realizing value
46(7), 809–818. doi:10.2307/2583965
from project implementation under uncertainty: An
exploratory study using system dynamics. International
Journal of Project Management, 35(3), 341–352. doi:
10.1016/j.ijproman.2017.01.009 Appendix
Williams, T., Ackermann, F., & Eden, C. (2003).
Structuring a delay and disruption claim: An See Table 1.

Table 1. A portfolio implementation variables and equations.


Variables (with dimensions) Description of variables Symbols Equations References
Project-level variables
Expected value creation Expected value creation per period DEVðAÞ DEVðAÞ ¼ DEV0 ðAÞ þ SC; DEV0 ðAÞ ¼ 25 Son and Rojas (2011),
rate of A (dollar /month) Wang et al. (2017)
Ð 100
Expected value of A (dollar) Accumulated expectations for EVðAÞ EV ¼ t¼0 DEVðAÞ  dt þ 25 Son and Rojas (2011),
value creation Wang et al. (2017)
Value creation rate of The value created in each period by DRVðAÞ DRVðAÞ ¼ VCCðAÞ  WPðAÞ Son and Rojas (2011),
A (dollar/month) project implementation and syner- Wang et al. (2017)
getic benefits
Ð 100
Realised value of A (dollar) The accumulated value created by RVðAÞ RV ¼ t¼0 DRVðAÞ  dt Son and Rojas (2011),
project implementation Wang et al. (2017)
Deviation of A The discrepancy between DðAÞ DðAÞ ¼ RVðAÞ=EVðAÞ1 Son and Rojas (2011),
(dimensionless) EVðAÞand RVðAÞ Wang et al. (2017)
Ð 100 DðAÞþREðAÞPDðAÞ
Perceived deviation of A Deviation Perceived by the port- PDðAÞ PDðAÞ ¼  dt Son and Rojas (2011),
t¼0 TPðAÞ
(dimensionless) folio manager Wang et al. (2017)
Budget demand of A Original investment demand for BDðAÞ A constant value 50 Wang et al. (2017)
(dollar/month) each period
Investment priority of A An index showing the priority of A IPðAÞ Determined by remedial Wang et al. (2017)
(dimensionless) action and PDðAÞ
Investment rate of A Available Investment for A in CðAÞ CðAÞ ¼ IPðAÞ  BDðAÞ Wang et al. (2017)
(dollar/month) each period
Ð 100
Total cost of A (dollar) The total consumed investment of TCðAÞ TCðAÞ ¼ t¼0 CðAÞ  dt Son and Rojas (2011),
Project A Wang et al. (2017)
Value creation index of A Amount of value created by per VCIðAÞ A constant value of 0.5 Loch and Kavadias (2002),
(dimensionless) unit investment Wang et al. (2017)
Value creation capacity The maximum value created by the VCCðAÞ VCCðAÞ ¼ VCIðAÞ  CðAÞ Wang et al. (2017)
of A (dollar) available fund
Expected work progression Expected work to accomplish in EWPðAÞ A constant value 1 Wang et al. (2017)
of A (dimensionless) each period
Disruptions& delays of Impact of uncertainties on work pro- DDðAÞ Normal ðmean; sdev2 Þ Son and Rojas (2011),
A (dimensionless) gression, modelled a random nor- High level ¼ Normalð0:7; 0:09Þ Wang et al. (2017)
mal distribution Medium level ¼ Normalð0:5; 0:04Þ
Low level ¼ Normalð0:3; 0:01Þ
Work progression Work accomplished in each period WPðAÞ WP ¼ EWPðAÞDDðAÞ Son and Rojas (2011),
(dimensionless) Wang et al. (2017)

Portfolio-level variables
Total budget (dollar) Investment constraint for portfolio TB A constant value 10,000 Expert opinion
implementation
Ð 100
Total value creation (dollar) Value realised by the portfolio TVC TVC ¼ t¼0 ðDRVðAÞ þ DRVðBÞÞ  dt Loch and Kavadias (2002)
Remedial action Adjustment policies for the compo- RA Determined by the Lyneis and Ford (2007)
(dimensionless) nent projects portfolio manager
Synergetic index The synergetic value created by per SI A constant value Expert opinion
(dimensionless) unit value of project B High level ¼ 1.5%;
Medium level ¼ 1.0%;
Low level ¼ 0.5%
Synergetic effects (dollar) The synergetic value created by SE SE ¼ RVðBÞ  SI Loch and Kavadias (2002)
Project B to A

You might also like