You are on page 1of 25

Project Planning : Work Breakdown Structure

Copyright © 2015 - 2018, Victorian Institute of Technology.


The contents contained in this document may not be reproduced in any form or by any means, without the written permission of VIT, other
than for the purpose for which it has been supplied. VIT and its logo are trademarks of Victorian Institute of Technology.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 1


Develop the Management Plan and
Schedule
• Effective scheduling can result in benefits in the critical
areas of time, cost, and quality. Consequently, project
managers must be good schedulers.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 2


Develop the Management Plan and
Schedule
• The scheduling process consists of the following steps:
– clarify the project’s goal
– develop the work breakdown structure (WBS)
– put the WBS activities in sequence
– compute and chart the durations of all WBS activities

continued on next slide

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 3


Develop the Management Plan and
Schedule
• The scheduling process consists of the following steps:
– develop the network diagram and determine the critical path
– update the schedule as needed
– monitor the schedule throughout the project

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 4


Creating the Work Breakdown Structure
(WBS)
• A WBS is a deliverable-oriented grouping of the work
involved in a project that defines the total scope of the
project
• WBS is a foundation document that provides the basis for
planning and managing project schedules, costs, resources,
and changes
• Decomposition is subdividing project deliverables into
smaller pieces
• A work package is a task at the lowest level of the WBS
• The scope baseline includes the approved project scope
statement and its associated WBS and WBS dictionary

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 5


Approaches to Developing WBSs

• Using guidelines: Some organizations, like the DOD,


provide guidelines for preparing WBSs
• The analogy approach: Review WBSs of similar projects
and tailor to your project
• The top-down approach: Start with the largest items of the
project and break them down
• The bottom-up approach: Start with the specific tasks and
roll them up
• Mind-mapping approach: Mind mapping is a technique that
uses branches radiating out from a core idea to structure
thoughts and ideas

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 6


Figure 5-7. Sample Mind-Mapping
Approach for Creating a WBS

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 7


Figure 5-8. Gantt Charts With WBS
Generated From a Mind Map

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 8


The WBS Dictionary and Scope Baseline

• Many WBS tasks are vague and must be explained more so


people know what to do and can estimate how long it will
take and what it will cost to do the work
• A WBS dictionary is a document that describes detailed
information about each WBS item

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 9


Table 5-5. Sample WBS Dictionary Entry

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 10


Advice for Creating a WBS and WBS
Dictionary
• A unit of work should appear at only one place in the WBS.
• The work content of a WBS item is the sum of the WBS
items below it
• A WBS item is the responsibility of only one individual, even
though many people may be working on it
• The WBS must be consistent with the way in which work is
actually going to be performed; it should serve the project
team first, and other purposes only if practical

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 11


Advice for Creating a WBS and WBS
Dictionary (cont’d)
• Project team members should be involved in developing the
WBS to ensure consistency and buy-in
• Each WBS item must be documented in a WBS dictionary to
ensure accurate understanding of the scope of work
included and not included in that item
• The WBS must be a flexible tool to accommodate inevitable
changes while properly maintaining control of the work
content in the project according to the scope statement

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 12


What Went Wrong?

• A project scope that is too broad and grandiose can cause


severe problems
– Scope creep and an overemphasis on technology for technology’s
sake resulted in the bankruptcy of a large pharmaceutical firm,
Texas-based FoxMeyer Drug
– In 2001, McDonald’s fast-food chain initiated a project to create an
intranet that would connect its headquarters with all of its restaurants
to provide detailed operational information in real time. After
spending $170 million on consultants and initial implementation
planning, McDonald’s realized that the project was too much to
handle and terminated it

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 13


Figure 4.6 WBS for producing a motorcycle with time
allocations and numbering.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 14


Figure 4.9 Sample Gantt chart schedule.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 15


Figure 5.3 Example of a milestone schedule summary that tracks any approved schedule
variances.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 16


Figure 5.7 Planning a project overview.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 17


Figure 6.1 Partial graphical WBS for a software selection project.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 18


Figure 6.2 Partial outline WBS for a software selection project.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 19


This image cannot currently be displayed.

Figure 8.1 An example of a partial schedule displayed in table form.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 20


Figure 8.2 An example of a partial schedule displayed in Gantt chart form.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 21


Figure 8.3 The schedule development points to be reviewed in this chapter.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 22


Figure 8.4 The ten steps involved in creating a schedule.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 23


This image cannot currently be displayed.

Figure 8.5 Example of a partial network diagram showing logical sequence of tasks.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 24


Figure 8.6 Overview of developing a schedule.

ITSU 2006 [ Lesson 3 ] Copyright © 2018 VIT, All Rights Reserved 25

You might also like