You are on page 1of 2

1.

Solution Application Areas


This system can be used in many organizations in order to shortlist expert
candidate. In this project, we have implemented an organization-oriented recruitment
system that would assist the human resource department in short listing the right
candidate for a specific job profile. The system would be used in many business
sectors that will require expert candidate, thus reducing the work load on the human
resource department.

2. Tools/Technology
The following tools and technology we will use in our proposed project:
In our project, we have tried to combine both personality prediction using
Machine Learning algorithms like Logistic regression to predict the personality of a
person and used term frequency algorithm to get the skill in which the person is good
at.

Software Requirements:
 Windows 7 or higher.
 SQL 2008
 Python  
 Django
 TensorFlow 

Hardware Requirements:
 Processor – i3
 Hard Disk – 5 GB
 Memory – 1GB RAM
 Internet Connection

3. Expertise of the Team Members


All team members are pre-equipped with the level of knowledge needed for the
successful completion of this project. We have studied the relevant course. This
project is of equal interest to all team members.

4. Milestones
The project will start immediately after approval from Project Coordinator.
Milestone Milestone Goal Start Date End Date
Feasibility studies and basic system concepts have been
Concept
approved by management and the project is authorized to 21/10/2020
approval
proceed to detailed requirements definition.
Requirements Requirements specifications are complete, correct,
22/10/2020 05/11/2020
review approved and suitable for input to design.
The architectural design satisfies all product
Preliminary
requirements, is approved and is suitable for input into the 06/11/2020 19/11/2020
design review
detailed design process.
Detailed designs fully implement the system architecture,
Critical design
are approved and are suitable for input into the 20/11/2020 30/04/2021
review
development of code.
Test plans are adequate for the testing of all product
Test plan
features, are approved and are suitable for input to the 03/05/2021 24/05/2021
review
development of test cases and test procedures.
Operational
The software product has passed unit testing and is ready
readiness 25/05/2020
for deployment in its target production environment.
review