Professional Documents
Culture Documents
CN-333 Lecture 21 PDF
CN-333 Lecture 21 PDF
SLIDE NO. 01
CN-333:
CONSTRUCTION
ECONOMIC ▪ Spring 2020
ANALYSIS ▪ Lecture 21
Once i’ has been calculated, it is compared with the MARR to assess whether the
alternative in question is acceptable.
If i’ > MARR, the alternative is acceptable; otherwise, it is not.
To use linear interpolation, we first need to try a few values for i’.
A good starting point is to use the MARR.
At i’ = 20%:
PW =-$345,000 + $98,000(3.3255) + $115,000(0.3349)
=+$19,413
Since the PW is positive at 20%, we know that i’ > 20%.
At i’ = 25%:
PW =-$345,000 + $98,000(2.9514) + $115,000(0.2621)
=-$25,621
Now that we have both a positive and a negative PW, the answer is bracketed
(20% < i’ % < 25%).
The dashed curve in Figure is what we are linearly approximating.
The answer, i’ %, can be determined by using the similar triangles represented by dashed lines
in Figure.
i’ = 22.16% (approx.)
Because the IRR of the project (22.16%) is greater than the MARR, the project is
acceptable.
What Is Incremental
Analysis?