You are on page 1of 2

28 TheStructuralEngineer Professional guidance


February 2015 Willow Island

Willow Island cooling tower


collapse: a lesson from nature
W Figure 1
Memorial to 51 workers killed in Willow Island collapse

system, along with the hoisting loads and


This month’s structural newly placed steel and concrete, was
failure review from Sean supported by concrete poured in the previous
days’ lifts.
Brady highlights the perils of
sticking rigidly to a concrete Failure

SNOOPYWV / CC-BY-SA 3.0


construction schedule The morning of 27 April 1978 started out with
preparation for Lift 29 of the second tower.
regardless of weather The lift-form system was approximately
conditions. 52m above ground level, following Lift 28
the previous day. The Lift 28 formwork and
the lower jumpform beam were removed,
Driving southwest along Riverview Drive, both the inside and outside of the shell, were the system was jumped, and the jumpform
leaving the town of Belmont behind, the connected to one another by anchor bolts, beam and formwork were installed for Lift 29.
highway follows the curve of the Ohio River, which transferred the system and applied Reinforcement was installed and concrete
separating the state of Ohio from West loading directly into the tower shell. Each placement for Lift 29 commenced.
Virginia. About 2km out of town, just off jumpform beam consisted of an upper and The system was now entirely supported by
the left-hand side of the highway, stands lower section, with the lower beam essentially the Lift 28 concrete, which was approximately
a memorial, its sides cut in a distorted leapfrogging above the upper beam as the 20 hours old. There were 51 workers on the
hourglass shape mimicking the two power system ascended the tower. scaffolding. As the third bucket of concrete
station cooling towers that stand across the In order to jump the system, the formwork was being hoisted into position by cathead
highway in the distance. The memorial bears from the previous day’s lift was removed; gantry cranes No. 4 and No. 5, eyewitnesses
a black plaque with gold lettering. It lists 51 the lower jumpform beams were detached described hearing a loud crack coming from
names, fatalities in what is still considered from the tower shell, moved upward, and the vicinity of cathead gantry crane No. 4.
one of the worst construction disasters in US reattached above the upper jumpform beam. The scaffolding at this location suddenly tilted
history (Figure 1). The jacking frame was then jacked upwards. inwards, tearing concrete from the tower.
Once in place, the formwork for that day’s Progressive collapse commenced. The entire
Cooling towers pour or ‘lift’ would be installed, with the four scaffolding system, along with the Lift 28
In the late 1970s, two cooling towers – known levels of scaffolding providing access for concrete, began to peel away from the top of
as the Willow Island cooling towers – were these activities. Below Lift 10, construction the tower in both a clockwise and counter-
constructed as part of the Pleasants Power materials were lifted into position by clockwise direction, like cascading dominos1.
Station, the first being completed in 19771. standalone cranes, but above this level six The collapse took less than a minute, with
The towers are formidable reinforced- cathead gantry cranes, supported on the the 51 workers, as well as the lift-form system
concrete structures standing 131m high, with lift-form system and spaced at 60° angles and tonnes of concrete, falling 52m to the
base diameters of 109m. Their diameter around the tower’s circumference, took over ground below (Figures 3 and 4). There were
and thickness vary with height, and their the hoisting role. no survivors.
hyperbolic profile allows for natural drafting. The system performed one jump or lift
The design and construction of the towers per day: it was jumped upwards by 1.5m in Investigation
was undertaken by the Hamon Cooling Tower the morning and placement of a 1.5m high The incident was investigated by the National
Division of Research-Cottrell, Inc, which section of the tower shell circumference was Bureau of Standards (NBS) on behalf
used its patented lift-form system, consisting completed. The following day the process of the Occupational Safety and Health
of a formwork and scaffolding system that was repeated. So on a typical day, workers Administration (OSHA)2. The investigation
climbed the tower during construction in what would arrive on site at 6:30am and remove focused on three aspects of the collapse: the
was known as a series of ‘lifts’. Research- formwork and the lower jumpform beam. crane system, the scaffolding lift-form system,
Cottrell had successfully used this system in The detached lower jumpform beam was and the tower shell itself.
the construction of 36 other towers prior to then leapfrogged upwards, and the system The crane system was quickly ruled out:
commencing the Willow Island project. jumped. Formwork was reinstalled and it exhibited no damage and tests would
The lift-form system primarily consisted of the steel and concrete for that lift placed. confirm that its components met the relevant
four levels of scaffolding attached to jacking The workers would finish at 3pm, with the requirements. Similarly, the lift-form system
frames, which were in turn supported on concrete gaining strength throughout the itself was found to play no role in the failure.
jumpform beams attached to the tower shell night. The investigation now turned to the tower
(Figure 2). The jumpform beams, attached on Thus, above Lift 10, the entire lift-form shell structure itself.

TSE38_28-29 Pro guid Willow v3.indd 28 22/01/2015 12:20


www.thestructuralengineer.org

29

In order to estimate the strength of the Lift the failure would have occurred regardless S Figure 3
Cooling tower after collapse
28 concrete at the time of the failure, the NBS of the bolts being removed. They determined
investigators conducted tests using similar that failure was likely to occur if the concrete
concrete subjected to similar temperatures strength was below 6.9MPa. As we know, the
for a period of 20 hours – the estimated time strength at the time of failure was estimated
that had elapsed between the placement at 1.5MPa, a long way from 6.9MPa.
of the Lift 28 concrete and collapse. The This failure highlights the dangers of
results were disturbing. The concrete had governing a concrete construction schedule
a cube strength of approximately 1.5MPa based on time considerations alone, and it is
– shockingly low. The cold temperature not an isolated incident in the history of failure.
conditions on site were to blame – the Both the collapse of the Commonwealth

ASCE
temperature resulted in the concrete simply Avenue building in Boston in 1971, which killed
not having enough time to develop the four, along with the dramatic collapse of an
necessary strength to support the lift-form
system and applied loading.
apartment building at Baileys Crossroads
in Virginia in 1973, which killed 14, were also
S Figure 4
Debris within cooling tower after collapse

However, upon the release of the NBS contributed to concrete being given insufficient
report, Lev Zetlin Associates (LZA), which time to develop necessary strength. As with
had been engaged by the contractor in the Willow Island, the construction schedules were
aftermath of the failure, disagreed with the governed by time and did not consider the
official findings. They determined that a environmental conditions that the concrete
number of critical anchor bolts had been had to contend with.
removed from the structure prior to the
collapse. These bolts were located in the Aftermath
jumpform beams – and therefore played a role The OSHA was criticised for lax inspections

ASCE
in transferring the load from the scaffolding – it didn’t have enough safety inspectors on
to the tower shell concrete of Lift 27. LZA the ground to enforce regulations in West
argued that if the bolts had not been removed, Virginia. It did, however, adopt new guidelines
then failure would have been unlikely. to protect future workers, including requiring decisions from the designer to the contractor,
In response to this report, two of the detailed safety manuals be produced for and requiring mandatory testing of concrete
original NBS investigators would undertake construction projects. It also made changes samples prior to formwork removal when the
further investigation, which was released in to the US Construction Safety Act, such as concrete was being relied upon to carry load.
1980. They would ultimately conclude that moving more responsibility for formwork Many years later, 12-year-old Anthony Lauer,
while working on a school project, asked his
teacher why there was no memorial for the 51
fatalities in the incident3. His family had been
 Figure 2
Diagram of
lift-form system
devastated by the tragedy: his grandfather,
Larry Gale Steele, along with Larry’s four sons –
Emmett, Ernest, Miles and Ronald – were killed
in the disaster. Young Lauer seized upon the
idea for a memorial, and four years later he had
collected over US$50 000 to build one – the
very memorial that today stands across the
highway from the completed towers.

Sean Brady is the managing director of Brady


Heywood (www.bradyheywood.com.au), based
in Brisbane, Australia. The firm provides forensic
and investigative structural engineering services
and specialises in determining the cause of
engineering failure and non-performance.
Follow on Twitter @BradyHeywood

REFERENCES:
1) Delatte N. J. (2009) Beyond failure: Forensic case
studies for civil engineers, Reston, USA: ASCE

2) National Bureau of Standards (1979) Investigation


of Construction Failure of Reinforced Concrete
Cooling Tower at Willow Island, West Virginia [Online]
Available at: www.nist.gov/customcf/get_pdf.
cfm?pub_id=908824 (Accessed: January 2015)

3) Pope E. D. and Dayhoff R. A. (2009) Pleasants


ASCE

County, San Francisco, USA: Arcadia Publishing

TSE38_28-29 Pro guid Willow v3.indd 29 22/01/2015 12:20

You might also like