2. NPS Update
a. Liberia - MTN 45.0% Orange 47.0%. Plans have been put in place to optimize the
network in the areas where NPS is low and improvement is expected in the month of
September.
Liberia International Capacity - International link upgrade has been successfully completed
Ghana to UK and Abidjan to Portugal have all been upgraded to 5Gb capacity each. Total
combined Capacity is now 10Gb
4. Network Availability Improvement Drive
i. Liberia - Weekly Network Availability on all technologies are above the target for week
38 under review with 2G = 98.20%, 3G = 97.65% and 4G =99.23% with a percentage
growth of 0.71%, 0.15% and 1.74% respectively.
ii. 45% of the 3 Months Fuel Supply in Monrovia Phase 3 (August to October) has so far
been done and 90% of the 8 months fuel have been delivered.