Professional Documents
Culture Documents
Aji Studi Kasus Mengelola Risiko
Aji Studi Kasus Mengelola Risiko
KASUS
PROJECT RISK ANALYSIS
Project Scope
This project consists of constructing a debris boom upstream of the dam spillway and
Risk Level installing a temporary coffer dam around the construction area to dewater the bridge and
spillway notch construction zones for the fish passage. A prefabricated concrete bridge is
Likelihood of Occurrence
planned to extend across the notch in the spillway; and, will include a stop log water
Very control structure and improved roadway access to the lock and dam storage yard. The
Low Moderate High High High
Likely fish passage ramp and riffle structure is constructed of rock materials and will also
incorporate hydraulic dredging operations to use dredge spoil to fill voids in the large rock
materials of the fishway.
Likely Low Moderate High High High
This is a 100% Federal project and no lands and damage costs are included. No relocation
costs were expected for this project.
Unlikely Low Low Moderate Moderate High Cost
Impacts
For the Sample Project, any cost impact of $500K or higher should be
Very
Low Low Low Low High considered at least "Significant."
Unlikely Anything over $250 K should be considered
at least "Marginal."
Contract Risks (Internal Risk Items are those that are generated, caused, or controlled within the PDT's sphere of influence.)
MITIGATION/
CASE FAILURE RISK CAUSE AVOIDANCE LIABILITY
Building Piles & Mat Foundation Design & Proper Eng & Engineer
Foundation,NJ failure installation QA Contractor
CONSTRUCTION FORENSICS: c t s g r o u
construction technology services
p
MITIGATION/
CASE FAILURE RISK CAUSE AVOIDANCE LIABILITY
MITIGATION/
CASE FAILURE RISK CAUSE AVOIDANCE LIABILITY
East River Block fall Injury Improper Rewire block Crane Op.
Barge, NY rewiring set on barge Owner
CONSTRUCTION FORENSICS: c t s g r o u
construction technology services
p
MITIGATION/
CASE FAILURE RISK CAUSE AVOIDANCE LIABILITY
Tingkat Resiko & Frekwensi. T M R SHE Manager / Officer Site Manager Project Manager
EFFECT
T = TINGGI T T9 T8 M5
M = MEDIUM M T7 M6 M3
R = RENDAH R M4 M2 R1 Fedry, SKM Ir. Nurbadri Rakhmat Ir. Julius, MT
No revisi :
Ket. *) Pada kolom Evaluasi diberikan catatan: a). " OK " - jika berhasil sesuai rencana dan sesuai hukum/peraturan ; b) . REV - jika harus direvisi, karena ada kecelakaan /tdk sesuai rencana