Outline Programme - Rev A

Week 1 2 3 4 5 6
Date 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov ## ## 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov ## ## 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec ## ## 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec ## ## 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec
Task

Mobilisation
Item 1- Small Car Park: Clearnace Works
Burn off 9 nr. Existing car park markings & 2
disabled spaces and prepare surface (11nr)
Cut Tarmac, excavate and remove 80m long (400-
1000mm high timber log edging
Excavate & remove 1 steel kissing gate
Remove and dispose of remaining plants
Reduce 90m³ of planting bed soil to ground level
Cut and excavate link path tarmac (18.2m² 50mm
deep)
Remove bin and base and make good the tarmac
surface (Tarmacker's to do )
Item 2 - Small Car Park: Hard Works
Prepare and paint 8nr. Disabled parking bays
Supply and install hardwood railway timbers (71.5
m) with concrete bed and haunch
Spred and prepare retained soil for turf (156m ² ).
(Remove stones +25mm )
Supply and lay Rowlan Medallion Turf (156m ² )
Item 3 - Main Car Park: Clearance Works Phase 1
Remove dead tree and gub out root, Fill & compact
hole with Type 1
Excavate and remove timber post and rail fencing
(173.9m )
Excavate and remove steel field gate
Excavate and remove timber pedestrian gate
Excavate and remove timber field gate
Excavate and remove timber log horse style
Excavate grass, soil & tarmac ( 290mm deep, 350m²
and 340mm deep, 72.5 m²)
Plain off existing tarmac (30mm depth) (12.9m²)
Remove Post, Ground made good
Item 4 - Main Car Park: Hard Works Phase 1
Excavate and install 2 supplied triangular vehicle
barriers (3.6m wide) and paint
Relocate existing Boulder
Install new supplied boulders (73nr, 1.2m apart)
Excavate, Supply and lay pcc edging (197.5m) with
150x100 concrete bed and haunch
Supply and lay Terram and Type 1
Base Course Macadam & 10mm Hardstone SMA
30mm consilidated thickness (72.5m²)
Lay and peg down supplied grass reinforcement
mesh (160m²)
Supply and lay terram (350m²) + MoT type 3
Lay supplied paving grid (350m²) + supply, spread
and compact sand/soil mix (15.4m³ )
Clip supplied white parking markers into paving
Supply and sow grass seed (350m²)
Supply, Excavate, and plant Acer Campestre
'streetwise' (10nr.) Subcontractor
Item 5 - Oval Entrance: Clearance Works
Remove and safeguard bin for reuse
Remove and safeguard sign post (Dispose of 1)
Remove and dispose of steel kissing gate and
associated fencing
Excavate and dispose of existing footpath surface
(165mm deep, 15.5m²)
Excavate existing grass (250mm deep, 1.1m² )
Cut neat line in existing tarmac for new surface
(1.45m)
Excavate and use toptrec surfacing and Type 1 to fill
for this and previous grass excavation (2.9m²)
Item 6 - Oval Entrance: Hard Works
Supply and install new access restriction (46.9 lin m
and 12 nr posts)
Excavate, supply and install pcc edging (18.9m +
150x100 concrete bed and haunch)
Supply and install terram, MOT type 1 (14.6m²)
Tarmac base course, 6mm aggregate wearing
course consolidated thickness of 25mm (14.6m²)
Excavate and install safeguarded bin
(500x500x150mm concrete base)
Excavate and install safeguarded sign post (in-situ)
Prepare and paint access gates
Item 7 - Stoneyford Entrance: Clearance Works
Remove and safeguard bin for reuse
Fell tree, grind out stip and rootbal and fill void (Type
1)
Remove existing access restriction (10nr posts +
22.5m of timber rails)
Excavate, remove and dispose of existing 4 rail
timber fence (15.2m)
Excavate existing footpath 165mm deep (13.3m²)
Excavate existing grass (250mm deep, 7.8m² )
Excavate, remove and dispose remnant timber sign
board post
Item 8 - Stoneyford Entrance: Hard Works
Supply and install new access restriction (9nr posts,
35.2m+ 3nr 11.7m high tensile steel)
Excavate, supply and lay ppc edging (15m +
150x100mm concrete bed and haunch)
Supply and lay terram, MOT type 1 (13m² )
Tarmac base course, 6mm aggregate wearing
course consolidated thickness of 25mm (13m²)
Excavate and install safeguarded bin
(500x500x150mm concrete base)
Supply and install new timber post (1nr) and rails
(4nr) 11 lin m long
Extra over: Excavate, supply and install timber
corner fence post
Excavate and install supplied horse friendly vehicle
barrier (1nr, 3m wide)
Prepare, prime and paint vehicle barrier
Supply and lay MOT Type 1 (150mm deep, 7.8m²)
Lay toptrec (100mm thick, 7.8m²)
Item 9 - Brand Lane Entrance: Clearance Works
Remove and dispose of existing bin
Fell Hawthorn trees to ground level and grub out
roots and fill with compacted soil (2nr)
Prune epicormic growth and crown raise (8nr)
(Subcontractor?)
Remove hedge inc. roots and fill void with
compacted soil (5.8m)
Remove and dispose of brickwork to 50mm below
ground level (10.9m)
Remove and dispose of steel knee rail and posts
(3.1m)
Remove and dispose of existing entrance sign
Reduce Holly shrub to height of fence (5m)
Regrade area to remove spoil (128.4m²)
Excavate and remove damaged kerb+ prepare bed
for replacement
Item 10 - Brand Lane Entrance: Hard Works
Prepare, prime and paint vehicle barriers (2nr)
Excavate and install bin (500x500x150mm concrete
base)
Install new supplied entrance signs (2nr) 1300x850

Supply and install new timber fence (post+ 4 nr rail


fencing)(56.7m long)
Extra Over: Excavate and supply new morticed
fence post (5nr)
Prepare and paint new parking bay markings (5nr)
Excavate, supply and lay 125x255mm Half battered
kerb edging(1nr) + 300x150 concrete bed and
haunch
Prepare ground, supply and spread wildflower seed
mix (128.4m²)