Professional Documents
Culture Documents
This paper addresses the performance of epoxy-coated stirrups in stirrups. The two beams failing in shear achieved capacities
reinforced concrete beams under bending and shear. A review of of 60.7 kips for the beam using uncoated stirrups and 56.0
previous work in bond and detailing of stirrups is presented. The kips for the companion beam using epoxy-coated stirrups.
results of an experimental program are described. From these Choi and others9 have investigated the bond of epoxy-coated
results several conclusions are found, supported by ultimate failure
reinforcement and have concluded that for coatings between
load, deflection, stirrup strain, crack pattern, and crack width
data. All beams reinforced with epoxy-coated stirrups as well as 5 and 12 mils in thickness, deformation patterns control bond
those with uncoated stirrups failed at higher than calculated shear behavior in No. 6 and larger bars while epoxy-coating thick-
capacities from those in ACI 318-89 (Revised 1992)1 and the ness becomes more critical in No. 5 and smaller bars. Since
proposed AASHTO LRFD 1993 Bridge Specifications.2 most stirrups consist of smaller bar sizes, epoxy coating may
have a more significant impact on anchorage and crack
Keywords: anchorage (structural); crack width and spacing; detailing; patterns as well as crack width at service load levels.
epoxy resins;reinforced concrete; reinforcing steels; shear stress; stirrups. Work by Anderson and Ramirez10 demonstrated the effect
various forms of anchorage can have on the shear behavior
INTRODUCTION of concrete beams. In their study, narrow beam specimens (8
Epoxy coating of reinforcement has been used as a method x 20 in.), where the stirrup anchorage detail was the variable,
of corrosion protection for nearly 20 years. This added dura- reached failure at loads in excess of the current ACI Code1
bility has its trade-offs in the form of reduced bond strength. requirements; however, from the mode of failure and final
Studies performed by Johnson and Zia,3 Treece and Jirsa,4 crack patterns, they concluded that straight embedment
and others5 to examine the behavior of epoxy-coated longi- length of U-stirrups should be avoided and that free ends of
tudinal reinforcement have demonstrated this deficiency. U-stirrups should be anchored by standard hooks bent within
Anchorage tests of epoxy-coated hooked bars by Hamad et al.6 the confined concrete core. These tests were carried out
revealed that uncoated hooked bars developed greater using uncoated stirrups. In ACI 318-89, the practice of
anchorage capacities and resulted in less slip than epoxy- anchorage of stirrups by means of straight embedment was
coated hooked bars. These tests were based on No. 7 and No. eliminated. However, this detailing is still used in stirrups
11 hooked bars in beam-column joints. They recommended for precast pretensioned bridge girders. Since epoxy
that the modification factor of 1.2 be used when determining coating reduces the adhesion and friction between the steel
the basic development lengths for epoxy-coated longitudinal and the concrete, it is likely that the structural performance
bars in tension. As a result of these studies, ACI Committee of prestressed beams with coated, straight stirrups will be
3181 included a series of modification factors for deter- different from that of similar beams reinforced with
mining straight development lengths and anchorage of bars uncoated, straight stirrups.
detailed using standard hooks. These modification factors Work by Choi et al.9 suggested that epoxy-coated longitu-
were to be applied to all bars in tension including both longi- dinal reinforcement produces wider cracks during service
tudinal and transverse reinforcement, even though only the loads. Cleary11 also presented similar results. Beams rein-
longitudinal bars were studied. forced with epoxy-coated stirrups are likely to experience
Presently, epoxy-coated stirrups are being used as shear fewer but wider diagonal tension cracks. As the concrete is
reinforcement in precast pretensioned bridge girders. Indiana subjected to shear stress above its diagonal tensile capacity,
Bridge Specifications7 require that only epoxy-coated rein- it transfers the stress to the stirrup reinforcement on
forcement be used in the bridge deck. Thus, the horizontal cracking. The lower adhesion and friction of epoxy-coated
shear reinforcement in composite precast pretensioned girder steel could result in the formation of larger cracks in beams,
construction, which is provided by extending the girder stirrup thus increasing the strain in the stirrup legs, particularly at
reinforcement into the deck, must be epoxy-coated as well. service load levels.
It is more practical to simply use epoxy-coated stirrups than
to epoxy-coat only the stirrup extensions into the deck.
However, to date there has been very limited research8 on ACI Structural Journal, V. 93, No. 5, September-October 1996.
Received June 3, 1994, and reviewed under Institute publication policies. Copy-
the performance of epoxy-coated stirrups in beams. The right © 1996, American Concrete Institute. All rights reserved, including the making of
findings from Clarke’s research consisting of two beam tests copies unless permission is obtained from the copyright proprietors. Pertinent discussion
will be published in the July-August 1997 ACI Structural Journal if received by
only show a reduction in ultimate capacity with epoxy-coated March 1, 1997.
ACI member Douglas B. Cleary is a structural and coastal engineer with the Federal
Division of Black and Veatch, Kansas City, Missouri. He received a BSCE in 1987, an
MSCE in 1988, and a PhD in 1992 from Purdue University.
EXPERIMENTAL PROGRAM
In this program, 12 beams were tested under concentrated
loading. The experimental program was divided into three
phases, each consisting of two sets of companion beams in
terms of stirrup detailing used. Of the four beams in each
phase, two beams had epoxy-coated stirrups for shear rein-
forcement while the remaining two beams had uncoated
shear reinforcement. The stirrups were No. 3 U-bars on 8-in.
Fig. 1—Typical Phase 1 and 2 test specimens. centers in the longitudinal direction. The average epoxy
coating thickness on the No. 3 stirrups for Phases 1 and 2 was
9.8 ± 2.3 mils. Phase 3 coating thickness was 13.8 ± 1.7 mils.
The anchorage of free ends of epoxy-coated stirrups is Tensile flexural reinforcement was provided by four No. 9
further complicated by the fact that they should be properly bars (ρw = 0.0303). In addition, two No. 8 bars were placed
anchored throughout their entire height. Belarbi12 reported in the flexural compression zone of the beams. To eliminate
that stirrups experience the largest strains at the point where the flexural behavior as a variable in a shear study, all longi-
the diagonal tension crack crosses them. Earlier work by tudinal reinforcement was uncoated. The steel used was
Kani13 demonstrated that the critical stirrup anchorage Grade 60. All bar deformation patterns were a diagonal rib
condition exists where the failure crack intersects the stirrup. pattern. Actual concrete compressive strengths ranged
Anderson and Ramirez’s9 experimental results further between 5120 and 8215 psi as given in Table 1, Column 2.
confirmed Kani’s findings. They concluded that since the Four different stirrup details were employed. Fig. 1 and 2
diagonal tension crack crosses stirrups at different locations, show a typical beam and the various stirrup details included
the stirrups must be required to mobilize their yield strength in the experimental program. The specimen identification is
at any location along their height. Failure of a stirrup to “B” for uncoated stirrups or “E” for epoxy-coated stirrups.
achieve its yield will result in anchorage pullout and The next two or three letters identify the type of stirrup
premature shear failure. detailing used: U-stirrup (U), inverted (I), straight embed-
ment (S), and hooked anchorage (H). The phase number is
RESEARCH SIGNIFICANCE given as the last term. Beams BUH-1, EUH-1, BUIH-2,
Epoxy-coated stirrups are currently being used in precast EUIH-2, BUH-3, and EUH-3 met ACI code1 requirements
pretensioned bridge girders, and it is likely that where for development of web reinforcement. In the remaining
epoxy-coated longitudinal bars are used, the stirrups will be beams the stirrup legs were anchored by means of straight
epoxy-coated as well. There is limited research concerning embedment length. Although the current ACI code1 does not
the performance of epoxy-coated shear reinforcement. This allow this type of anchorage for the free ends of stirrups, it is
lack of information and the known reduction in bond still a popular detail in precast pretensioned bridge girder
strength of epoxy-coated bars warrant an investigation into and cast-in-place bridge girder construction because of
the performance of epoxy-coated shear reinforcement. The manufacturing or construction convenience. This detailing
reduction in adhesion and friction between the epoxy-coated was also included in this study to establish a lower bound for
reinforcement and the concrete could result in a reduction in available anchorage, since the modification factor of 1.2
shear capacity due to improper anchorage of the free ends or adopted by the code4 has not been experimentally verified
insufficient load redistribution, as well as larger crack widths when applied to stirrup leg development lengths.
during service loads. Current ACI 318 shear design All the specimens were loaded as shown in Fig. 2. This
requirements1 as well as stirrup anchorage details have not resulted in an a/d ratio of 3.27. The load was applied in
been verified with tests of specimens reinforced with epoxy- increments of approximately 2500 lb at each load point. For
coated stirrups. The same lack of verification is found with the beams in Phase 1, monotonic loading continued incre-
ANALYSIS OF RESULTS
Nominal strength
The failure shears listed in Column 3 of Table 1 indicate
that one-half of the beams using epoxy-coated stirrups
achieved higher capacities than their uncoated counterparts.
Therefore, epoxy coating did not clearly influence ultimate
load capacity within the bounds of scatter normally associ-
ated with shear tests. Fig. 3 shows typical midspan deflec-
tions for beams with similar stirrup detailing comparing Fig. 3—Deflection comparison between beams with similar
coated against uncoated performance. Larger deflections stirrup detail and different bar coating.
were recorded initially in beams reinforced with epoxy-
coated stirrups. The difference increased with the additional
load cycles, but at failure loads the difference decreased. indicate that some slip of the stirrups did occur in 10 of the
A comparison of the test failure values to the ACI calcu- 12 beams. However, the slip did not prevent yielding of the
lated capacities is presented as the ratio of the experimental stirrups.
shear strength to the ACI shear strength for each beam in In one case, inspection of the stirrups after failure
Table 1, Column 4. It should be noted that the ACI code1 revealed damage to the epoxy coating caused by apparent
limits the yield strength of the deformed bar shear reinforce- slipping. Fig. 4 presents this damage along Stirrup Leg 4 in
ment to 60 ksi. The yield strength of the uncoated and coated Beam EUIS-3 with the free ends of the stirrup anchored by
stirrups and the longitudinal steel in this study exceeded 60 ksi. means of straight embedment. There was no apparent epoxy
A procedure based on a modified compression field theory damage in any of the other five beams utilizing epoxy-coated
approach has been implemented for shear design in the stirrups. The strain readings indicate that stirrups without the
proposed AASHTO LRFD Bridge Specifications.2 Using the epoxy coating are just as likely to slip along the anchorage
proposed design process, shear capacities were estimated for length as the epoxy-coated stirrups and that the stirrup detail
each specimen. The results of a comparison between used has more effect on preventing slip to occur than does
proposed AASHTO capacities and test results is presented in the absence of epoxy coating. The torn epoxy further verifies
the form of a ratio of experimental results to calculated the presence of slip, particularly in details using straight
capacities as seen in Table 1, Column 5. These ratios show the embedment. These observations are limited to No. 3 stirrups
AASHTO approach as being more conservative than the ACI for the anchorage details tested in this study.
design method. As with the ACI code,1 a prescribed limit of The use of U-stirrups with 90-deg hooks, whether upright
60 ksi is imposed on the yield strength of the reinforcement. or inverted, increased the shear capacities for all of the
Both approaches result in conservative estimates of the shear beams whether using uncoated or epoxy-coated shear
capacity of all specimens tested for nominal average shear reinforcement. Examination after failure of the beams
stresses up to 7.5 f c ′ as shown in Column 6 of Table 1. using U-stirrups with 90 deg hooks revealed that the
hooks had been opened.
Stirrup detailing An increased brittleness at failure was observed in the
All test specimens exceeded their calculated shear Phase 2 beams with the stirrups anchored in the flexural
strengths according to the ACI code.1 Stirrup strain readings tension zone. Large portions of the tension side concrete
disintegrated at failure, exposing the longitudinal steel. This northeast quarter of the beam. From Fig. 6 the measured
was noticeably different to the failures of Phases 1 and 3 strain readings at the stirrup midheight for Stirrup Legs 10
beams that failed in a far less brittle manner. Fig. 5 shows the and 12 are found below the yield strain for No. 3 bars.
tension side of Beam EUIS-2 after failure. Beams BUIS-3 Measured strains in Stirrup Legs 4 and 6 reveal that the yield
and EUIS-3 also had inverted U-stirrups and did not fail in a strain was achieved. The gage on Stirrup Leg 8 was
brittle mode. However, their failure loads were below those damaged, so no readings were available.
of Phase 2, as shown by the normalized average shear stress The failure crack pattern for Beam BUH-1, presented in
in Column 6 of Table 1. Fig. 6, shows the diagonal shear cracks crossing Stirrups 10
and 12 near the stirrup ends. In contrast, cracks are shown
Stirrup strains crossing Stirrups 4, 6, and 8 at the midheights, producing the
Strain gages were placed at the midheight of each stirrup largest strain readings. The importance of anchorage length
leg for Phases 1 and 2 (see Fig. 1). Stirrups, at locations is apparent when looking at these results since the failure
where cracks crossed a gage, showed higher strains than crack produces the largest strains at the intersection with the
those where cracks crossed stirrups away from the gage. The stirrup leg. With the Phase 3 gage placement pattern, strains
largest strains were found to occur in the stirrups where the were recorded on stirrup legs closer to the ultimate failure
failure crack crossed the gage. In an attempt to record crack. Fig. 7 presents the southwest side of Beam BUH-3
maximum strain readings, strain gages were placed on each and the failure crack pattern for that portion of the beam as
stirrup leg in a pattern reflecting the expected failure crack well. Stirrup Legs 17, 19, 21, and 23 reached yield. From the
for beams in Phase 3. The locations were selected based on figure it appears that Stirrup Leg 25 is within the compres-
the failure crack patterns observed in Phases 1 and 2. The xes sion zone of the point load and therefore undergoes small
in Fig. 2 represent stirrup strain gage placement. tensile strains. The crack diagram shows the failure cracks
Beams BUH-1 and BUH-3 typify the varied stirrup strain crossing the stirrup legs near the gage locations.
behavior of test specimens using the same reinforcement Because stirrup strain behavior is highly influenced by
detail. Fig. 6 shows the stirrup strains for the northeast side crack location relative to the gages, a comparison of average
of Beam BUH-1. Included is the failure crack pattern for the strain readings was used. This was particularly useful when
Crack widths
Crack widths were measured on all Phase 2 and 3 beams,
beginning at the start of diagonal cracking and continuing at
various load increments for all cycles. Cracks were monitored
on both ends of the beams. In Phase 2, the crack monitored
was the crack predicted to be the ultimate failure crack.
Three points were measured on each crack, with the average
taken as the crack width at that particular location. The crack
behaviors were erratic as the beams redistributed applied
load. Cracks in Beam BUIS-3 remained very small (< 0.001
in.) before growing very wide just prior to failure (> 0.060
in.). The cracks in Beam BUH-3, on the other hand, grew
steadily with each incremental load to a width of 0.038 in.
before failure. Averaging the crack widths for an entire beam
seemed an appropriate means to form crack width compari-
sons between beams with epoxy-coated and uncoated stirrups. Fig. 7—Stirrup strains and failure cracks for northeast
Using a ratio of the average of all crack widths at a partic- quarter of Beam BUH-3.
ular load for epoxy bars to an average of all crack widths for
uncoated bars at the same load, an E/U ratio was plotted
versus load for all Phase 2 and 3 beams. Fig. 9 shows that
initially the E/U ratio is greater than 1 for all but the 3. Regardless of the end anchorage detail, epoxy-coated
companion pair of beams with the inverted stirrups and stirrups were associated with wider cracks in the beams. This
straight embedment for free ends in Phase 3. A more was determined from stirrup strain readings and average
comprehensive crack measurements program must be estab- crack width measurements.
lished to completely verify this observation. 4. The inverted stirrup details result in a more brittle and
explosive failure, at least at higher shear stress levels as
SUMMARY OF FINDINGS shown by the specimens in Phase 2. The beams with stirrup-
An investigation into the performance of epoxy-coated free ends anchored with 90-deg hooks achieved slightly
stirrups in beams was carried out using stirrups with various higher capacities than beams using stirrups with only straight
anchorage schemes for the free ends. A total of 12 beams embedment.
were tested utilizing both uncoated and coated No. 3 stirrups. 5. Measured stirrup strains indicate that a low number of
An examination of the test data reveals the following: slow load cycles with the largest average stress range of 44 ksi
1. Both ACI 318-89 (revised 1992)1 and the proposed in the stirrups resulted in larger slip to occur in the epoxy-coated
AASHTO LRFD Bridge Specifications’2 calculated capaci- stirrups and larger midspan deflections. However, nearly all
ties were conservative when compared to test values of spec- beams, both uncoated and coated, had some stirrup legs slip
imens with coated and uncoated stirrups. prior to failure as the load redistributed internally.
2. Epoxy-coated stirrups for the size and anchorage
schemes tested had no negative impact on the ultimate shear RECOMMENDATIONS
strength of the beams within the bounds of scatter normally Based on findings from this exploratory study, the
associated with shear tests. The anchorage detail for the free anchorage of free ends of No. 3 epoxy-coated stirrups for
ends of the stirrups played a more significant role in terms of shear provided by current ACI requirements1 and the shear
failure capacity than the absence or presence of epoxy-coating strength provided by this reinforcement are adequate.
for the tests conducted in this study. Caution should be exercised in extending these findings to
Fig. 9—E/U ratio comparison of average crack widths for Phase 2 and 3 beams.
larger diameter bars used as shear reinforcement. Despite determine the adequacy of some details for shear of epoxy-
conservative ultimate capacities when compared with ACI coated longitudinal reinforcement, for example, anchorage
and AASHTO, and based on the larger slip observed during at simple supports and points of inflection.
these tests for epoxy-coated stirrups in conjunction with the
earlier findings by Hamad et al.,6 it is recommended that ACKNOWLEDGMENTS
The work described formed part of the MS thesis of the first author under
further testing of beams with No. 4 and 5 stirrups verify the direction of the third author. The tests in Phase 1 were conducted by the
current anchorage details for stirrup-free ends in larger bar second author under the direction of the third author. The research was funded
sizes. The observed larger slip, particularly at service load with partial support from Purdue University, the Indiana Department of
Transportation, and the Federal Highway Administration. Any opinions,
levels, implies larger crack widths and increased exposure to findings, and conclusions expressed in this paper are those of the authors
environmental conditions. Further work is also necessary to and do not necessarily represent the views of the sponsors.