Professional Documents
Culture Documents
PLUMBING, DRAINAGE,
& SANITARY SYSTEM
Prepared by:
PLUMBING, DRAINAGE,
& SANITARY SYSTEM
TABLE OF CONTENTS
INSTRUCTION TO CONTRACTORS
The engineering plans, design criteria and specifications are prepared and
written with this general intention and the close coordination between all the
trade contractors and the Construction Manager should ensure the successful
implementation of the project. All interpretations of the plans and specifications
shall be done through the Owner, the Project Manager and the Mechanical
Consultant.
The bidders are required to inform themselves of the conditions under which the
work is to be performed, the site of the work, the obstacles which may be
encountered, as well as the permits and licenses, and all other relevant matter
concerning shall not be allowed any extra compensation by reason of any matter
or thing concerning which such bidder might have fully informed himself, because
of his failure to have informed himself prior to the bidding.
The work shall include the furnishing of equipment, materials, tools, scaffolding,
rigging, transportation, labor, supervision, and other services required to install,
complete, test and make operational the parts of the plumbing system as
described herein, in the bid plans and in the technical specifications as prepared
by the Plumbing/Sanitary Consultant.
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - INSTRUCTION TO CONTRACTORS SECTION 15000-B
NGAC - GOVERNMENT HOUSING PAGE 1 - 4
Guevara & Partners, Inc.
Specifically the work includes the following:
C. Water Supply Distribution from the Domestic Water Tanks thru the
use of Constant Pressure System (CPS), to individual fixtures.
D. All building sanitary drains, soil and waste piping including vents,
from toilet areas and kitchen areas.
R. Furnish written one (1) year warranty of the plumbing sanitary and
drainage system.
1.4.1 The cost of providing the overall security for the project shall be by
Owner. However, individual contractors such as the plumbing contractor
shall be responsible for the storage and safekeeping of their equipment
and materials until the final completion and turnover of the project to the
Owner.
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - INSTRUCTION TO CONTRACTORS SECTION 15000-B
NGAC - GOVERNMENT HOUSING PAGE 3 - 4
Guevara & Partners, Inc.
1.4.2 The contractor shall provide all the necessary tools, gadgets, manpower,
materials, and other items to complete the work and shall not borrow from
the Owner at the site. The contractor shall provide their own warning
signs, fire extinguishers, barricades, ladders, etc., for the safety of the
absence of these items at the jobsite shall be enough reason for the
Owner to stop the work.
1.4.4 The contractor shall always observe good housekeeping. The jobsite
shall be broom-cleaned after every working day. All scrap waste and
excess materials shall be dumped at the trash area to be designated by
the Owner or the Project Manager.
1.4.6 Upon completion of work, the contractor shall submit to the Owner the
required as-built plans, test results, and certification of completion.
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - INSTRUCTION TO CONTRACTORS SECTION 15000-B
NGAC - GOVERNMENT HOUSING PAGE 4 - 4
Guevara & Partners, Inc.
SECTION 15010-B
GENERAL REQUIREMENTS
1.0 INTENT
It is the intention of these specifications and drawings to call for finished work,
tested, and ready for operation. Where the word "provide" is used, it shall mean
"furnish and install complete and ready for use".
Minor details not usually shown or specified, but necessary for the proper
installation and operation, shall be included in the work, the same as if herein
specified or shown.
The plumbing contractor shall give all necessary notices, obtain all permits and
pay all government sales taxes, fees, and other costs, including utility
connections or extensions, in connection with his work; file all necessary plans,
prepare all documents and obtain all necessary approvals of all governmental
departments having jurisdiction; obtain all required certificates of inspection for
his work and deliver same to the Construction Manager before request for
acceptance and final payment for the work.
The plumbing contractor shall include in the work, without extra cost to the
Owner, any labor, materials, services, apparatus, drawings, in order to comply
with all applicable laws, ordinances, rules, and regulations, whether or not shown
on drawings and/or specified.
The plumbing contractor shall base all measurements, both horizontal and
vertical from established benchmarks. All work shall agree with these established
lines and levels. Verify all measurements at site and check the correctness of
same as related to the work.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - GENERAL REQUIREMENTS SECTION 15010-B
NGAC - GOVERNMENT HOUSING PAGE 1 - 8
Guevara & Partners, Inc.
4.0 DRAWINGS
The plumbing contractor shall follow drawings in laying out work and check to
verify spaces in which work will be installed. Maintain maximum headroom and
space conditions at all points. Where headroom or space conditions appear in
adequate, the Owner shall be notified before proceeding with installation.
If directed by Owner, the contractor shall without extra charge, make reasonable
modifications in the layout as needed to prevent conflict with work of other trades
or for proper execution of the work.
The plumbing contractor shall submit for approval detailed shop drawings of all
equipment and all materials required completing the project, and no material or
equipment may be delivered to the jobsite or installed until the contractor has in
his possession the approved shop drawings for the particular material or
equipment. The shop drawings shall be complete as described herein. The
contractor shall furnish the number of copies required by the General and Special
Conditions of the contract, but in no case less than five (5) copies.
Failure of the plumbing contractor to submit shop drawings in ample time for
checking shall not entitle him to an extension of contract time, and no claim for
extension by reason of such default will be allowed.
6.0 DEVIATIONS
Where the plumbing contractor proposes to use an item or equipment other than
that specified or detailed on the drawings which requires any redesign of the
structure, partitions, foundations, piping, wiring, or any other part of the
mechanical, electrical or architectural layout, all such redesign, and all new
drawings and detailing required therefore, same shall be prepared by the
plumbing contractor at his own expense and approved by the Owner and
Plumbing / Sanitary Consultant.
The plumbing contractor shall give full cooperation to other trades and shall
furnish in writing to the Owner, with copies to the Plumbing / Sanitary Consultant,
any information necessary to permit the work of all trades to be installed
satisfactorily and with the least possible interference or delay.
Where the work of the plumbing contractor will be installed in close proximity to,
or will interfere with work of other trades, he shall assist in working out space
conditions to make a satisfactory adjustment. If so directed by the Owner, the
contractor shall prepare composite working drawings and sections at a suitable
scale not less than 1:50M, clearly indicating how his work is to be installed in
relation to the work of other trades. If the contractor installs his work before
coordinating with other trades, or so as to cause any interference with work of
other trades, he shall make the necessary changes in his work to correct the
condition without extra charge.
The plumbing contractor shall furnish to other trades, as required, all necessary
templates, patterns, setting plans, and shop details for the proper installation of
work and for the purpose of coordinating adjacent work.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - GENERAL REQUIREMENTS SECTION 15010-B
NGAC - GOVERNMENT HOUSING PAGE 3 - 8
Guevara & Partners, Inc.
8.0 PROTECTION
The plumbing contractor shall protect all work and material from damage by his
work or workmen, and shall be liable for all damages thus caused.
The plumbing contractor shall be responsible for work and equipment until finally
inspected, tested, and accepted; he shall protect work against thefts, injury or
damage; and shall carefully store materials and equipment received on site
which is not immediately installed. He shall close open ends of work with
temporary covers or plugs during storage and construction to prevent entry of
obstructing materials.
The plumbing contractor shall furnish all scaffolding, rigging, hoisting and
services necessary for erection and delivery into the premises of any equipment
and apparatus furnished. Remove same from premises when no longer required.
All materials and apparatus required for the work, except as specifically specified
otherwise, shall be new of first-class quality and shall be furnished, delivered,
erected, connected and finished in every detail and shall be so selected and
arranged as to fit properly into the building spaces. When no specific kind or
quality of material is given, a first-class standard article as approved by the
Construction Manager shall be furnished.
11.0 MOTORS
Motor shall be built in accordance with the latest International Standards and the
Philippine Electrical Code. Motors shall be tested in accordance with these
standards and conform thereto for insulation resistance and dielectric strength.
Each motor shall be provided for quiet operation.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - GENERAL REQUIREMENTS SECTION 15010-B
NGAC - GOVERNMENT HOUSING PAGE 4 - 8
Guevara & Partners, Inc.
12.0 QUIET OPERATION AND VIBRATION
All work shall operate under all conditions of load without any sound or vibration,
which is objectionable in the opinion of the Owner. In case of moving machinery,
sound, or vibration noticeable outside of room in which it is installed, or
annoyingly noticeable inside its own room, will be considered objectionable by
the Construction Manager shall be corrected in an approved manner by the
mechanical contractor at his expense. Vibration control shall be by means of
approved vibration eliminators in a manner as recommended by the
manufacturer of the eliminators.
13.0 ACCESSIBILITY
The plumbing contractor shall be responsible for the sufficiency of the size of
shafts and chases, the adequate clearance in double partitions and hung ceilings
for the proper installation of his work. He shall cooperate with the General
Contractor and all other contractors whose work is in the same space, and shall
advise the General Contractor of his requirements. Such spaces and clearances
shall, however, be kept to the minimum size required.
The plumbing contractor shall locate all equipment, which must be services,
operated, or maintained in fully accessible positions. Equipment shall include but
not limited to: valves, traps, clean-outs, motors, controllers, switchgear, and drain
points. If required for better accessibility, furnish access doors for this purpose.
Minor deviations from drawings may be made to allow for better accessibility and
any change shall be approved.
The plumbing contractor shall provide the General Contractor the exact locations
of access panels for each concealed valve, control, dampers or other device
requiring service. Access panels shall be provided and installed by the General
Contractor and as specified in the architectural sections of the specifications.
Locations of these panels shall be submitted in sufficient time to be installed in
the normal course of work.
The Electrical Subcontractor shall furnish and install all power wiring up to the
designated terminals except: (a) temperature control wiring; (b) equipment
control wiring; and (c) interlock wiring. The plumbing contractor shall furnish and
install all power wiring connections to all motors and controllers complete from
power source or equipment junction box, including power wiring thru starters.
The plumbing contractor shall install all starters not factory mounted on
equipment.
The plumbing contractor shall, regardless of voltage, furnish and install all
interlock wiring, and equipment control wiring for the equipment that the
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - GENERAL REQUIREMENTS SECTION 15010-B
NGAC - GOVERNMENT HOUSING PAGE 5 - 8
Guevara & Partners, Inc.
contractor furnishes.
After all circuits have been energized and completed, the Electrical Contractor
shall be responsible for all power wiring, and all control wiring shall be
responsibility of the Plumbing Contractor. Motor and equipment shall be provided
for current characteristics as shown on the drawings.
The plumbing contractor shall provide all cutting and patching necessary to install
the work specified in this section. Patching shall match adjacent surface.
No structural members shall be cut without the approval of the Owner, and all
such cutting shall be done in a manner directed by him.
The plumbing contractor shall provide and locate all sleeve and inserts required
before the floors and walls are built, or shall be responsible for the cost of cutting
patching required for pipes and ducts where sleeves and inserts were not
installed, or where incorrectly located. The Plumbing Contractor shall do all
drilling required for the installation of his hangers.
Where sleeves are placed in exterior walls below grade, the space between the
pipe or conduit and the sleeves shall be packed with oakum and made
completely watertight.
Sleeves shall be constructed of 18 gauge galvanized sheet steel with lock seam
joints for all sleeves set in concrete floor slabs terminating flush with the floor. All
other sleeves shall be constructed of galvanized steel pipe unless indicated on
the drawings.
Fasten sleeves securely in floors, walls, and so that they will not become
displaced when concrete is poured or when other construction is built around
them. Take precautions to prevent concrete, plaster, or other materials being
forced into the space between pipe and sleeve during construction.
17.0 WATERPROOFING
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - GENERAL REQUIREMENTS SECTION 15010-B
NGAC - GOVERNMENT HOUSING PAGE 6 - 8
Guevara & Partners, Inc.
18.0 OPERATING INSTRUCTIONS
Upon completion of all work and all tests, the Plumbing Contractor shall furnish
the necessary skilled labor and helpers for operating his system and equipment
for a period of three (3) days of eight (8) hours each, or as otherwise specified.
During this period, instruct the Owner or his representative fully in the operations,
adjustment, and maintenance of all equipment furnished. Give at least forty-eight
(48) hours notice to the Owner in advance of this period.
The plumbing contractor shall furnish the Project Manager five (5) complete
bound sets of typewritten or blue-printed instructions for operating and
maintaining all systems and equipment included in this contract, for delivery to
the Owner. All instruction shall be submitted in draft, for approval, prior to final
issue. Manufacturer's advertising literature or catalogs will not be acceptable for
operating and maintenance instructions.
19.0 MAINTENANCE
Operation - The plumbing contractor shall receive calls for any and all
problems experienced in the operation of the equipment
provided under this work, and shall take steps to
immediately correct any deficiencies that may exist.
Check List - The plumbing contractor shall provide a checklist and shall
post a copy of it on the equipment or near the equipment
concerned. The checklist shall be a list of each piece of
equipment found in the scope of these specifications. The
checklist shall have a space for each of the next 12 months
to provide a space for check-off.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - GENERAL REQUIREMENTS SECTION 15010-B
NGAC - GOVERNMENT HOUSING PAGE 8 - 8
Guevara & Partners, Inc.
SECTION 15121
PART 1 GENERAL
1.03 REFERENCES
B. Expansion Calculations:
1. Installation Temperature: 75 degrees F (24ºC).
2. Domestic Hot Water: 140 degrees F (60 ºC).
3. Steam at max. pressure of 125 psig: 450 degrees F (232ºC).
4. Safety Factory: 30 percent.
1.05 SUBMITTALS
B. Product Data:
C. Samples: Submit two low pressure compensators 1 inch (20 mm) in size.
1.08 QUALIFICATIONS
B. Accept expansion joints on site in factory packing with shipping bars and
positioning devices intact. Inspect for damage.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PIPING EXPANSION COMPENSATION SECTION 15121
GOVERNMENT HOUSING PAGE 2 - 5
Guevara & Partners, Inc.
1.10 WARRANTY
PART 2 PRODUCTS
A. Steel Piping:
1. Manufacturers or approved equal:
a) JORD BELLOWS (AUST.)
b) THERMAFLEX (U.K.)
c) METRAFLEX (U.S.A.)
2. Inner Hose: Stainless Steel or Bronze.
3. Exterior Sleeve: Double braided, stainless steel or bronze.
4. Pressure Rating: 125 psig (862 kPa) WSP and 450 degrees F (232
degrees C).
5. Joint: Flanged, Threaded or Threaded with Union or as specified for
pipe joints.
6. Size: Use pipe sized units.
7. Maximum offset: 1 inch (25mm) on each side of installed centerline.
B. Copper Piping:
1. Manufacturers or approved equal:
a) JORD BELLOWS (AUST.)
b) THERMAFLEX (U.K.)
c) METRAFLEX (U.S.A.)
2. Inner Hose: Bronze
3. Exterior Sleeve: Braided bronze.
4. Pressure Rating: 125 psig (862 kPa) WSP and 450 degrees F (232
degrees C).
5. Joint: Soldered as specified for pipe joints].
6. Size: Use pipe sized units.
7. Maximum offset: 1 inch (25mm) on each side of installed centerline.
2.03 ACCESSORIES
PART 3 EXECUTION
3.01 INSTALLATION
G. Provide victaulic piping with minimum one joint per (inch) (25 mm) pipe
diameter instead of flexible connector supported by vibration isolation.
Victaulic piping need not be anchored.
MECHANICAL IDENTIFICATION
PART 1 GENERAL
A. Nameplates.
B. Tags.
C. Stencils.
D. Pipe Markers.
1.03 REFERENCES
1.04 SUBMITTALS
B. Submit lists of wording, symbols, letter size, and color coding for
mechanical identification.
C. Submit valve chart and schedule, including valve tag number, location,
function, and valve manufacturer's name and model number.
2.01 NAMEPLATES
A. Manufacturers
1. Locally manufactured.
2. Other acceptable manufacturers offering equivalent products.
2.02 TAGS
A. Manufacturers
1. Locally manufactured.
2. Other acceptable manufacturers offering equivalent products.
B. Metal Tags: Aluminum or Stainless Steel with stamped letters; tag size
minimum 1½ inch (40mm) square with smooth edges.
2.03 STENCILS
A. Manufacturers
1. Locally manufactured.
2. Other acceptable manufacturers offering equivalent products.
A. Manufacturers
1. Locally manufactured.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - MECHANICAL IDENTIFICATION SECTION 15190
GOVERNMENT HOUSING PAGE 2 - 4
Guevara & Partners, Inc.
2. Other acceptable manufacturers offering equivalent products.
D. Plastic Tape Pipe Markers: Flexible, vinyl film tape with pressure sensitive
adhesive backing and printed markings.
A. Manufacturers
1. Locally manufactured.
2. Other acceptable manufacturers offering equivalent products.
PART 3 EXECUTION
3.01 PREPARATION
3.02 INSTALLATION
E. Install plastic tape pipe markers complete around pipe in accordance with
manufacturer's instructions.
G. Identify air handling units, pumps, heat transfer equipment, tanks, and
water treatment devices with plastic nameplates. Small devices, such as
in-line pumps, may be identified with tags.
H. Identify control panels and major control components outside panels with
plastic nameplates.
K. Identify air terminal units and radiator valves with numbered tags.
M. Identify piping, concealed or exposed, with plastic tape pipe markers. Use
tags on piping 3/4 inch (20 mm) diameter and smaller. Identify service, flow
direction, and pressure. Install in clear view and align with axis of piping.
Locate identification not to exceed 20 feet (6 m) on straight runs including
risers and drops, adjacent to each valve and Tee, at each side of
penetration of structure or enclosure, and at each obstruction.
N. Provide ceiling tacks to locate valves or dampers above T-bar type panel
ceilings. Locate in corner of panel closest to equipment.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - MECHANICAL IDENTIFICATION SECTION 15190
GOVERNMENT HOUSING PAGE 4 - 4
Guevara & Partners, Inc.
SECTION 15260
PIPING INSULATION
PART 1 GENERAL
A. Piping insulation.
1.04 REFERENCES
F. ASTM C585 - Inner and Outer Diameters of Rigid Thermal Insulation for
Nominal Sizes of Pipe and Tubing (NPS System).
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - PIPING INSULATION SECTION 15260
GOVERNMENT HOUSING PAGE 1 - 4
Guevara & Partners, Inc.
1.05 SUBMITTALS
1.07 QUALIFICATIONS
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - PIPING INSULATION SECTION 15260
GOVERNMENT HOUSING PAGE 2 - 4
Guevara & Partners, Inc.
PART 2 PRODUCTS
2.01 GLASS FIBER (FOR CALORIFIER AND HOT WATER PIPING INSULATION)
A. Manufacturers:
1. ACI FIBERGLASS (PHIL.)
2. JOHNS MANVILLE
3. Other acceptable manufacturers offering equivalent products.
D. Tie Wire: 18 gage stainless steel with twisted ends on maximum 12 inch
(300mm) centers.
F. Insulating Cement/Mastic
1. Manufacturers:
a) 3M or equivalent.
2. ASTM C195; hydraulic setting on mineral wool.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that piping has been tested before applying insulation materials.
B. Verify that surfaces are clean, foreign material removed, and dry.
3.02 INSTALLATION
3.03 TOLERANCE
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - PIPING INSULATION SECTION 15260
GOVERNMENT HOUSING PAGE 4 - 4
Guevara & Partners, Inc.
SECTION 15400
VALVES
A. GENERAL
1. WORK INCLUDED
a. Gate valves.
b. Globe or angle valves.
c. Check valves.
d. Butterfly valves.
e. Drain valves.
f. Float valve.
2. RELATED WORK
3. SUBMITTALS
B. PRODUCTS
1. ACCEPTABLE MANUFACTURERS
2. VALVE CONNECTIONS
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - VALVES SECTION 15400
NGAC - GOVERNMENT HOUSING PAGE 1 - 5
Guevara & Partners, Inc.
e. Provide butterfly valve with tapped lug body when used for isolating
service.
3. GATE VALVES
a. 2" and smaller: Bronze, non-rising stem, inside screw, double wedge or
disc, or solder or screwed ends.
b. Bigger than 2": Iron body, bronze trim, rising stem, OS&Y, renewable
composition disc, flanged ends.
a. 2" and smaller: Bronze, rising stem, inside screw, renewable composition
disc, solder or screwed ends.
b. Bigger than 2": Iron body, bronze trim, rising stem, renewable
composition disc, flanged ends.
5. CHECK VALVES
a. 2" and smaller: Bronze, swing disc, solder or screwed ends. Compliance
to ASTM standards.
b. Bigger than 2": Iron body, bronze trim, swing disc, renewable disc and
seat, flanged ends.
6. PLUG COCKS
a. Iron body, brass plugs and washers, air tested, solder or screwed ends.
7. BUTTERFLY VALVES
a. Iron body, bronze disc, resilient replaceable liner seat, plain, flanged, or
grooved ends.
8. DRAIN VALVES
9. VALVE OPERATORS
a. Provide suitable hand wheels for gate, globe or angle, drain valves and
inside hose bibbs.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - VALVES SECTION 15400
NGAC - GOVERNMENT HOUSING PAGE 2 - 5
Guevara & Partners, Inc.
b. Provide one plug cock wrench for every ten plug cocks sized 2 inches
and larger. For smaller sizes provide each plug cock sized 2½ inches and
larger with a wrench, with set screw.
c. For butterfly valves, provide gear operators for sizes 8 inches and
smaller, minimum of one. For smaller sizes provide lever lock handle with
toothed plate for shut-off service and infinitely adjustable handle with lock
nut and memory stop for throttling service.
d. Provide valves located more than 7 feet from floor in equipment room
areas with chain operated sheaves. Extend chains to about 5 feet above
floor and hook to clips arranged to clear walking aisles.
10. Float Valve: Shall be "CLA-VAL" Model 124-01 or 124-02. The float valve is a
non-modulating valve which accurately controls the liquid in tanks. The valve
shall be designed to open fully when the liquid level reaches a preset low point
and close drip tight when the level reaches a preset high point. The valve shall
be hydraulically operated, diaphragm valve with the pilot control and float
mechanism mounted on the cover of the main valve. The float positions the pilot
control to close the valve when the float contacts the upper stop. The high and
low liquid levels are adjusted by positioning the stop collars on the float rod. The
difference between high and low levels can be adjusted to as little as one inch, or
to as much as 19 inches by adding optional float rod extensions.
11. Surge Anticipator Valve - Shall be "CLA-VAL" Model 52-03 combination pressure
relief & Surge Anticipator valve. These valves shall be provided for protecting
transfer pumps, pumping equipment and all applicable pipelines from dangerous
pressure surges caused by rapid changes of flow velocity within a pipeline. When
pumping systems are started and stopped gradually, harmful surges do not
occur. However when a power failure takes place, the abrupt stopping of the
pump can cause dangerous surges in the system which result in severe
equipment damage.
Power failure to a transfer pump will usually result in down surge in pressure,
followed by an up surge in pressure. The surge control valve opens on the initial
low pressure wave from the system. In effect, the valve has anticipated the
returning high pressure wave and is open to dissipate the damage causing
surge. The valve shall then close slowly without generating any further pressure
surges.
12. Pump Control Valve: Shall be "CLA-VAL" Model 60-31 or approved equal. Pump
Control Valve shall be a pilot operated valve designed for installation on the
discharge of transfer pumps to eliminate pipeline surges caused by the starting
and stopping of the pump.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - VALVES SECTION 15400
NGAC - GOVERNMENT HOUSING PAGE 3 - 5
Guevara & Partners, Inc.
The pump starts against a closed valve. When the pump is started, the solenoid
control is energized and the valve begins to open slowly, gradually increasing
line pressure to full pump piping head. When the pump is signaled to shut-off the
solenoid control is de-energized and the valve begins to close slowly, gradually
reducing flow while the pump continues to run. When the valve is closed, a limit
switch assembly, which serves as an electrical interlock between the valve and
the pump stops.
When a power failure occur, a built-in lift type check valve closes the moment
flow stops, preventing reverse flow regardless of solenoid or diaphragm
assembly position. Solenoid valve power supply shall be 220V/1ph/60Hz.
C. EXECUTION
1. INSTALLATION
b. Install gate valves for shut-off and isolating service, to isolate equipment,
part of systems, or vertical risers.
c. Install globe or angle valves for throttling service and control device.
f. Provide drain valves at main shut-off valves, and low points of piping and
apparatus.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - VALVES SECTION 15400
NGAC - GOVERNMENT HOUSING PAGE 4 - 5
Guevara & Partners, Inc.
SECTION 15410
PLUMBING PIPING
A. GENERAL
1. SECTION INCLUDES
b. Valves.
2. RELATED SECTIONS
3. REFERENCES
d. ASME B16.1 - Cast Iron Pipe Flanges and Flanged Fittings Class 25,
125, 250 and 800.
c. ASTM A53 - Pipe, Steel, Black and Hot-Dipped Zinc Coated, Welded and
Seamless.
e. ASTM C564 - Rubber Gaskets for Cast Iron Soil Pipe and Fittings.
f. ASTM D1785 - Poly (Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40,
80, and 120.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING PIPING SECTION 15410
NGAC - GOVERNMENT HOUSING PAGE 1 - 8
Guevara & Partners, Inc.
g. ASTM D2241 - Poly (Vinyl Chloride) (PVC) Plastic Pipe (SDR-PR).
h. ASTM D2466 - Poly (Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule
40.
i. ASTM D2564 - Solvent Cements for Poly (Vinyl Chloride) (PVC) Plastic
Pipe and Fittings.
4. SUBMITTALS
b. Product Data: Provide data on pipe materials, pipe fittings, valves, and
accessories. Provide manufacturers catalog information. Indicate valve
data and ratings.
7. QUALITY ASSURANCE
8. QUALIFICATIONS
9. REGULATORY REQUIREMENTS
d. Provide temporary end caps and closures on piping and fittings. Maintain
in place until installation.
B. PRODUCTS
a. PPR Pipes
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING PIPING SECTION 15410
NGAC - GOVERNMENT HOUSING PAGE 3 - 8
Guevara & Partners, Inc.
4. WATER PIPING FOR RESIDENTIAL FLOORS
A. UPVC Pipe: ASTM D3033 or D3034, SDR 35. Fittings: PVC. Joints:
ASTM F477, elastomeric gaskets.
1. Ferrous pipe: 150 psig (1034 kPa) malleable iron threaded unions.
1. Ferrous pipe: 150 psig (1034 kPa) forged steel slip-on flanges;
1/16 inch (1.6 mm) thick performed neoprene gaskets.
8. GATE VALVES
a. Manufacturers
9. GLOBE VALVES
a. Manufacturers
c. Over 2 Inches (50mm): Iron body, bronze trim, rising stem, handwheel,
OS&Y, plug-type disc, flanged ends, renewable seat and disc.
a. Manufacturers
c. Over 2 Inches (50mm): Cast steel body, chrome plated steel ball, Teflon
seat and stuffing box seals, lever handle gear drive handwheel for sizes
10 inches (250mm) and over, flanged.
a. Manufacturers
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING PIPING SECTION 15410
NGAC - GOVERNMENT HOUSING PAGE 5 - 8
Guevara & Partners, Inc.
1. “KITZ”, “TOYO”, “TOZU”, “PEGLAR”
2. Other acceptable manufacturers offering equivalent products.
c. Over 2 Inches (50mm): Cast iron body and plug, non-lubricated, Teflon
packing, flanged ends.
C. EXECUTION
1. PREPARATION
a. Ream pipe and tube ends. Remove burrs. Bevel plain end ferrous pipe.
2. INSTALLATION
d. Install piping to conserve building space and not interfere with use of
space.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING PIPING SECTION 15410
NGAC - GOVERNMENT HOUSING PAGE 6 - 8
Guevara & Partners, Inc.
j. Where pipe support members are welded to structural building framing,
scrape, brush clean, and apply one coat of zinc rich primer to welding.
l. Prepare pipe, fittings, supports, and accessories not prefinished, ready for
finish painting. Refer to Section 09900.
o. Pipe vents from gas pressure reducing valves to outdoors and terminate
in weatherproof hood.
3. APPLICATION
c. Install brass male adapters each side of valves in copper piped system.
Sweat solder adapters to pipe.
d. Install gate valves for shut-off and to isolate equipment, part of systems,
or vertical risers.
e. Install globe valves for throttling, bypass, or manual flow control services.
4. ERECTION TOLERANCES
a. Establish invert elevations, slopes for drainage to 1/8 inch per foot, one
percent minimum. Maintain gradients.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING PIPING SECTION 15410
NGAC - GOVERNMENT HOUSING PAGE 8 - 8
Guevara & Partners, Inc.
SECTION 15430
PLUMBING SPECIALTIES
A. GENERAL
1. SECTION INCLUDES
b. Cleanouts.
c. Hose bibs.
d. Trench Drains.
f. Interceptors.
2. RELATED SECTIONS
3. REFERENCES
4. SUBMITTALS
B. PRODUCTS
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING SPECIALTIES SECTION 15430
NGAC - GOVERNMENT HOUSING PAGE 2 - 6
Guevara & Partners, Inc.
c. Canopy/Cornice Drains (RD-3): Lacquered or Galvanized cast iron body
with aluminum flashing clamp collar and nickel bronze flat strainer.
2. TRENCH DRAINS
a. At Pump Room, Mechanical Room: Storm drainage for this level shall
utilize a polychannel which are manufactured from polycrete, a
combination of thermosetting resins and silica fillers which form a unique
and rigid lightweight material.. Channels shall be of low porosity and
virtually nil absorption with resistance to acids and chemicals and shall
have superior compressive, tensile, shear and flexural strengths, up to
more than four times that of concrete. Channel shall be pre-cast,
precision moulded, smooth semi-circular internal surfaces dramatically
improve waste liquid discharge and promote self-cleaning. Grating shall
be of the same material as the channel and shall be fabricated from
lightweight plastic:
3. AREA DRAINS
4. FLOOR DRAINS
a. FD-1: ANSI A112.21.1; Lacquered cast iron two piece body with double
drainage flange, weep holes, reversible clamping collar, and round,
adjustable nickel-bronze strainer.
c. FD-3: FD-1 except with polished bronze funnel or anti- splash rim type
strainer.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING SPECIALTIES SECTION 15430
NGAC - GOVERNMENT HOUSING PAGE 3 - 6
Guevara & Partners, Inc.
5. PARKING DRAIN
a. PD: FD-1 except with extra heavy-duty strainers with hinged grate and
sediment bucket.
6. PLANTER DRAINS
7. CLEANOUTS
b. Exterior Unsurfaced Areas (CO-2): Line type with lacquered cast iron
body and round epoxy coated gasketed cover.
d. Interior Finished Wall Areas (CO-4): Line type with lacquered cast iron
body and round epoxy coated gasketed cover, and round stainless steel
access cover secured with machine screw.
8. HOSE BIBS
b. Inlet Assembly: Two piece heavy-duty cast steel or cast iron frame and
grate with ground or machined grate and frame bearing surfaces.
1. Curb and gutter style: Rectangular grate and storm back, capacity
2.5 cu ft/sec (70 cu dm/sec).
2. Standard: Round frame and grate with capacity 2.0 cu ft/sec (55
cu dm/sec).
c. Minimum 6 feet (1.8m) cover over outlet and slope bottom slab 10
percent to outlet invert, minimum 2 feet (300mm) sump below outlet.
12. MANHOLES
2. Cover: Standard cast iron with minimum sized pick hole, and
frame. Use heavy-duty cover and frame in vehicular traffic areas.
C. EXECUTION
1. PREPARATION
a. Coordinate cutting and forming of roof and floor construction to receive drains
to required invert elevations.
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING SPECIALTIES SECTION 15430
NGAC - GOVERNMENT HOUSING PAGE 5 - 6
Guevara & Partners, Inc.
2. INSTALLATION
_________________________________________________________________________________________________________________________________
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING SPECIALTIES SECTION 15430
NGAC - GOVERNMENT HOUSING PAGE 6 - 6
Guevara & Partners, Inc.
SECTION 15440
A. GENERAL
1. WORK INCLUDED
a. Furnish hanger and support inserts sleeves for placement into formwork.
3. RELATED WORK
4. REFERENCES
5. QUALITY ASSURANCE
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - SUPPORTS AND ANCHORS SECTION 15440
NGAC - GOVERNMENT HOUSING PAGE 1 - 6
Guevara & Partners, Inc.
B. PRODUCTS
a. Hangers for Pipe Sizes ½ to 1-½ Inch (15 to 40mm): Malleable iron or
Carbon steel, adjustable swivel, split ring.
b. Hangers for Pipe Sizes 2 to 4 Inches (50 to 100mm) and Cold Pipe Sizes
6 Inches and Over: Carbon steel, adjustable clevis.
d. Wall support for Pipe Sizes to 80mm: Cast iron hooks or approved
equivalent.
e. Wall support for Pipe Sizes 4 (100mm) Inches and Over: Welded steel
bracket and wrought steel clamp; adjustable steel yoke and cast iron roll
for hot pipe sizes 6 (150mm) inches and over or approved equivalent.
g. Floor Support for Pipe Sizes to 4 Inches (100mm) and All Cold Pipe
Sizes: Cast iron adjustable pipe saddle, locknut nipple, floor flange, and
concrete pier or steel support.
i. Shield for Insulated Piping 2½ Inches (65mm) Larger (Except Cold Water
Piping): Pipe covering protective saddles.
j. Shields for Insulated Cold Water Piping 2½ (65mm) Inches and larger:
Hard block non-conducting saddles in 90 degree segments, 12 inch
(300mm) minimum length, block thickness same as insulation thickness.
2. HANGER RODS
3. INSERTS
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - SUPPORTS AND ANCHORS SECTION 15440
NGAC - GOVERNMENT HOUSING PAGE 2 - 6
Guevara & Partners, Inc.
a. Inserts: Malleable iron case of galvanized steel shell and expander plug
for threaded connection with lateral adjustment, top slot for reinforcing
rods, lugs for attaching to forms; size inserts to suit threaded hanger rods.
4. FLASHING
b. Lead Flashing: 5 lb./sq. ft. sheet lead for waterproofing; one lb./sq. ft.
sheet lead for soundproofing.
5. EQUIPMENT CURBS
6. SLEEVES
a. Sleeves for Pipes Through Non-fire Rated Floors: Form with 18 gage
galvanized steel.
b. Sleeves for Pipes Through Non-fire Rated Beams, Walls, Footings, and
Potentially Wet Floors: Form with steel pipe or 18 gage galvanized steel.
c. Sleeves for Pipes Through Fire Rated and Fire Resistive Floors and
Walls, and Fireproofing: Prefabricated fire rated sleeves including seals,
UL listed or equivalent, or fire rated insulation metals and seals. Test
requirements shall follow standards UL 1479 and ASTM E 814.
7. FABRICATION
a. Size sleeves large enough to allow for movement due to expansion and
contraction. Provide for continuous insulation wrapping.
8. FINISH
1. INSERTS
e. Where inserts are omitted, drill through concrete slab from below and
provide thru-bolt with recessed square steel plate and nut recessed into
and grouted flush with slab.
f. Support vertical piping at every floor. Support vertical cast iron pipe at
each floor at hub.
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - SUPPORTS AND ANCHORS SECTION 15440
NGAC - GOVERNMENT HOUSING PAGE 4 - 6
Guevara & Partners, Inc.
g. Where several pipes can be installed in parallel and at same elevation,
provide multiple or trapeze hangers.
b. Provide rigid anchors for pipes after vibration isolation components are
installed.
4. FLASHING
b. Unless detailed on drawings, flash vent and soil pipes projecting 3 inches
minimum above finished roof surface with lead worked one inch minimum
into hub, 8 inches minimum clear on sides with 24 x 25 inches sheet size.
For pipes through outside walls, turn flanges back into wall and caulk,
metal counterflash and seal.
c. Flash floor drains in floors with topping over finished areas with lead, 10
inches clear on sides with minimum 36 x 36 inch sheet size. Fasten
flashing to drain clamp device.
5. SLEEVES
b. Extend sleeves through floors one inch above finished floor level. Calk
sleeves full depth and provide floor plate.
c. Where piping or ductwork penetrates floor, ceiling, or wall, close off space
between pipe or duct and adjacent work with fire stopping insulation and
calk seal airtight. Provide close fitting metal collar or escutcheon covers at
both sides of penetration.
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - SUPPORTS AND ANCHORS SECTION 15440
NGAC - GOVERNMENT HOUSING PAGE 6 - 6
Guevara & Partners, Inc.
SECTION 15450
PLUMBING EQUIPMENT
A. GENERAL
1. SECTION INCLUDES
e. Ultra-Violet Filters.
2. RELATED SECTIONS
3. REFERENCES
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING EQUIPMENT SECTION 15450
NGAC - GOVERNMENT HOUSING PAGE 1 - 5
Guevara & Partners, Inc.
4. SUBMITTALS
b. Shop Drawings:
c. Product Data:
6. QUALITY ASSURANCE
b. Provide temporary inlet and outlet caps. Maintain caps in place until
installation.
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING EQUIPMENT SECTION 15450
NGAC - GOVERNMENT HOUSING PAGE 2 - 5
Guevara & Partners, Inc.
8. WARRANTY
B. PRODUCTS
c. Casing: Cast iron volute with radial clearance around impeller, inlet
strainer.
e. Support: Cast iron pedestal motor support on steel floor plate with gas
tight gaskets.
g. Drive: Flexible coupling to vertical, solid shaft ball bearing electric motor.
c. Casing: Cast iron pump body and oil filled motor chamber.
f. Accessories: Oil resistant 6 foot (2m) cord and plug with three-prong
connector for connection to electric wiring system including grounding
connector.
_____________________________________________________________________________________________________________________________ ____
PLUMBING, DRAINAGE & SANITARY SYSTEM - PLUMBING EQUIPMENT SECTION 15450
NGAC - GOVERNMENT HOUSING PAGE 5 - 5
Guevara & Partners, Inc.