Crust Thickness as Per IRC 37-2018 Here consider 5MSA and CBR is 10% taken as per

ur location : Red soil

BC 0.03 m 30 mm
DBM 0.05 m 50 mm
WMM-1 0.125 m 125 mm
WMM-2 0.125 m 125 mm
GSB 0.15 m 150 mm
SG 0.5 m 500 mm

40 Feet Road Total Length = 560m


Length 560 m
Width 12 m Shoulder 3m

Length Width Depth Qty Rate Total Amount


BC 560 9 0.03 151.2 9,300.00 1,406,160.00
DBM 560 9 0.05 252 8,200.00 2,066,400.00
WMM-1 560 9.16 0.125 641.2 936.00 600,163.20
WMM-2 560 9.41 0.125 658.7 936.00 616,543.20
GSB 560 10.92 0.15 917.28 689.00 632,005.92
SG 560 12 0.5 3360 340.00 1,142,400.00
Shoulder 560 3 0.33 554.4 340.00 188,496.00
6,652,168.32

30 Feet Road Total Length = 1000m


Length 1000 m
Width 9m Shoulder 1.8 m

Length Width Depth Qty Rate Total Amount


BC 1000 7.2 0.03 216 9,300.00 2,008,800.00
DBM 1000 7.2 0.05 360 8,200.00 2,952,000.00
WMM-1 1000 7.36 0.125 920 936.00 861,120.00
WMM-2 1000 7.61 0.125 951.25 936.00 890,370.00
GSB 1000 9 0.15 1350 689.00 930,150.00
SG 1000 9 0.5 4500 340.00 1,530,000.00
Shoulder 1000 1.8 0.33 594 340.00 201,960.00
9,374,400.00

33 Feet Road Total Length = 480m


Length 480 m
Width 9.9 m Shoulder 0.9 m

Length Width Depth Qty Rate Total Amount


BC 480 9 0.03 129.6 9,300.00 1,205,280.00
DBM 480 9 0.05 216 8,200.00 1,771,200.00
WMM-1 480 9.16 0.125 549.6 936.00 514,425.60
WMM-2 480 9.41 0.125 564.6 936.00 528,465.60
GSB 480 9.9 0.15 712.8 689.00 491,119.20
SG 480 9.9 0.5 2376 340.00 807,840.00
Shoulder 480 0.9 0.33 142.56 340.00 48,470.40
5,366,800.80

Total Amount Excluding Profit and Over heads 21,393,369.12


Over heads Taken 10% 2,139,336.91
Profit Taken 10% 2,139,336.91
Total Amount 25,672,042.94
2.567 Cr